Plasma Gasification of Municipal Solid Waste. Tien Diep Kevin Estacio Sebastian Iskra Linda Quan Felix Velazquez Mentor: Dennis O’Brien. Questions from Meeting 3. Pressurized the system to 800psi Questions on Lo-Cat Cost of syngas is $100/ton Bi-product prices 88,000lb/hr of slag.
E N D
Plasma Gasification of Municipal Solid Waste TienDiep Kevin Estacio Sebastian Iskra Linda Quan Felix Velazquez Mentor: Dennis O’Brien
Questions from Meeting 3 • Pressurized the system to 800psi • Questions on Lo-Cat • Cost of syngas is $100/ton • Bi-product prices • 88,000lb/hr of slag
3D- Model • http://www.youtube.com/watch?v=9lnIxEnK2Co
Calculations – Absorber Sizing • Assumptions • 60% Flooding Velocity of 5 ft/s • 10 Stages • HETP = 3 ft • 4 ft for gas and liquid distributors • Height • H = (10 * 3 ft) + 4 ft • H = 34 ft
Calculations – Absorber Sizing Continued • Diameter: • Radius = (VGasIn/(π*.6 *Vflood))1/2 • R = (101576.3 ft3/hr /(π*10800 ft/hr))1/2 • R = 1.73 ft • D = 2R = 3.46 ft
References • http://www.dep.state.fl.us/Air/emission/construction/geoplasma/Geofigures.pdf