An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Statewide Culvert Asset Management (SCAM) Team - Update Asset Management Steering Committee August 29, 2013

  2. Culvert Inventory Plan • High Level Status • Project Milestones • Budget • Accomplishments • Next Steps • Questions

  3. High Level Status • BCA data collection complete - non-interstate routes • Planned: Sept 2013 Actual: June 2013 • QA/QC of data and uploads is ongoing • Interstate data collection taking longer than anticipated - Culvert Steering Committee decision: ACA Data Collection on all interstates (July 2013) - Interstate progress increased from 4 miles per week to 6 • Planned: 8 miles/week Actual: 6 miles/week • ACA Application - ACA beta testing completed 7/22 - ACA pre-production testing completed 8/21 - ACA pre-final testing to be completed on 8/30 - Final ACA application delivery scheduled 9/6

  4. Map goes here

  5. High Level Status, continued • FieldCollection Efforts Remaining as of 8/12/2013 • Interstate • 96 crew weeks of work remaining • 1 interstate crew is 4 people. • 24 weeks to complete Interstate ACA (4 crews) • Non-Interstate • 67 crew weeks of work remaining • 1 non-interstate crew is 2 people. • 9 weeks to complete Non-Interstate ACA (8 crews) • Total remaining field collection for 2013/2014 = 33 weeks. • 2013: 12 collection weeks • 2014: 21 collection weeks

  6. Map goes here

  7. Culvert Inventory Target Milestones Note: No significant field work during winter months (Nov 2013 – March 2014)

  8. Budget • 2011-2013 • Budget Request: $827K • Budget Granted: $800K not including Allocated Costs • Actual Spent to Date: $654K as of June 30, 2013(includes Allocated Costs) • 2013-2015 • STP funds requested: $1.2m • Allocated cost: $527K Total Project Budget is $2.5m

  9. Accomplishments • Completed non-interstate BCA field data collection 3 months early • Completed beta and pre-production ACA application testing • Enhancement of special field equipment (“Grate Stick”)

  10. Next Steps • Field Crews to Work on Priority Routes thru Oct 31, 2013 • Manage Contractor Deliverables • Delivery of ACA ArcPad application • QA/QC of data collected in 2013 • DFMS upload of data • Publish results of work completed in 2013 • Manage Project Budget • Plan for work in 2014 • Culvert Inventory Steering Committee Decision Items • Revisit aged data proposal update • 2014 budget request • Construction conflicts • Culvert inspection intervals

  11. Questions?