1 / 12

Nursery Relocation Presentation 20 th November 2008 Sean Stewart

Nursery Relocation Presentation 20 th November 2008 Sean Stewart. Current Nursery. Location. Capacity. 56 max. Current Nursery. 1. 3. Home bases. Sleeping areas. 2. Toilets /changing. Catering areas. Staff room & office. Entrance. Stores. Diamond Land. Sep 07:

nuala
Download Presentation

Nursery Relocation Presentation 20 th November 2008 Sean Stewart

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Nursery Relocation Presentation 20th November 2008 Sean Stewart

  2. Current Nursery Location Capacity 56 max

  3. Current Nursery 1 3 Home bases Sleeping areas 2 Toilets /changing Catering areas Staff room & office Entrance Stores

  4. Diamond Land Sep 07: DLS served 12 months notice on STFC that it required the land coloured red

  5. Beam Line I13

  6. Timeline • Sep 07 - DLS serve 12 months notice • Sep – Dec STFC consider alternate solutions • Jan 08 - Initial design for R31 drawn up • Feb – Jun Design discussed and altered • Jul - Applied for Planning Permission • Oct - Permission granted • Nov - Presentation to parents • Jan 09 - Refurbishment of R31 begins • Jul 09 - Nursery relocates

  7. Interim Nursery Location Capacity 56 max

  8. Nursery Location ATLAS Centre Garden Ridgeway House R31

  9. Nursery Layout 3 2 1 Home bases Sleeping areas Toilets /changing Snack kitchen Staff room & office Entrance Stores

  10. Drop off/collection ATLAS Visitors 30~35 Ridgeway House 2~3 FERMI AVENUE Main entrance 5~8

  11. Questions

  12. Options STFC considered • Adjust the existing building • Cost, complexity and time • Ask Diamond not to build the beamline • It’s the only place it can go • Approach HSIC JV • There was no contract in place • Build a new nursery for the JV to buy off us • Not enough time for project • Alternatives inside the wire • All rejected as being unsuitable • Not to provide a nursery at all (Daresbury & UKATC) • R31