Fall 2010 Rev A 08-23-10. Team Lightning Rod Critical Design Review. 10/7/2010. Trevor Luke Chris Bennett Matt Holmes Sushia Rahimizadeh Alex Shelanski Matthew Dickinson Jesse Ellison. Mission Overview. Objective

nuala
Download Presentation

Team Lightning Rod Critical Design Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fall 2010 Rev A 08-23-10 Team Lightning RodCritical Design Review 10/7/2010 Trevor Luke Chris Bennett Matt Holmes SushiaRahimizadeh Alex Shelanski Matthew Dickinson Jesse Ellison

  2. Mission Overview • Objective • To determine if future spacecraft will be able to utilize energy generated by vibrational and rotational motion as additional energy sources • To determine if more energy can be generated from vibrational motion or rotational motion • What we hope to prove and discover • A significant amount of energy can be produced from the motion of the satellite • A satellite can generate enough energy to power some systems • Hypothesis • Rotational motion will produce more energy than vibrational motion • Why we are doing this mission • To develop an alternative method of generating power for spacecraft

  3. Requirements Flow Down Goal: The goal of team Lightning Rod is to send a balloon satellite equipped with an electromagnetic generator to an altitude of thirty kilometers to determine if vibrational and rotational energy can be harnessed as a supplemental and renewable energy source for future spacecraft. Level 0 Objective 1: Fly a satellite to 30 km.

  4. Level 0 Objective 2: Keep the internal temperature of the satellite above -10 degrees Celsius. Level 0 Objective 3: Keep the overall weight of the satellite below 850 g.

  5. Level 0 Objective 4: Fly a Cannon Camera and the HOBO datalogger on the satellite. Level 0 Objective 5: Capture and store kinetic energy using the vibrating electromagnetic generator.

  6. Level 0 Objective 6: Capture and store kinetic energy using the rotational electromagnetic generator. Level 0 Objective 7: Compare the results of the rotational generator and the vibrational generator to see which one is most effective

  7. Design • We will design and construct two electromagnetic generators • One rotational generator • One vibrational generator • We will test them to make sure that they are both efficient and reliable • Energy output data during the flight will be processed and stored on the micro-controller • We will analyze the data when Satellite Zeus returns to determine which generator was more efficient • Our mission will achieve success when we demonstrate the ability to generate electricity from the g-forces that act upon Zeus

  8. The Generators Vibrational Generator Rotational Generator

  9. 2D Model

  10. 3D Model

  11. Functional Block Diagram

  12. Budget • Parts that have been ordered: • 20 Capacitors • Data Storage • Development Board • LDO Regulator • 16 Neodymium magnets • Microcontroller • 4 Relays • Spring Steel • 2 Switches • *All parts have been delivered already. • Parts that need to be purchased: • Batteries • Wire • Nylon Washers • Plexi-glass • Rubber Bumpers • 25 machine screws • **Parts are to be purchased before this weekend

  13. Schedule Complete proposal and presentation and submit online—Due 9/16 by 7:00 am Fill out order form and order hardware—9/23 at 11:30 Team meeting-10/4 at 3:00 Cut out generator structures-10/4 Wrap copper coils-10/4 Write presentation-Due 10/5 by 7:00 Team meeting-10/5 at 3:00 pm Test structure—10/5 to 10/8 Assemble magnets and spring steel for vibrational generator-10/5 Complete construction of vibrational and rotational generators—10/8 Team meeting-10/10 at 2:00 pm Test and adjust generator design to optimize voltage-10/10 Assemble and wire satellite—10/10 to 10/15 Complete the wiring of satellite—10/16 Team meeting-10/17 at 2:00 pm Program satellite hardware—10/17 to 10/22 Final Construction Completed—10/23 Team meeting-10/24 at 2:00pm Final Testing—10/24 to 10/29 Project Finished—10/30 Buffer Week—10/31 to 11/5 Finish Critical Design Review-11/2 Launch—11/6 Write final presentation-11/30 Finish Analysis and Final Report- 12/4 Team video due-12/4

  14. Test Plan

  15. Expected Results • The generators will produce a measurable amount of power • More power from rotational generator than from the vibrational generator • Higher energy output during turbulence • Highest energy output during burst • Results independent of temperature and pressure

  16. Team Org Chart • Trevor Luke • Team Leader • —Scheduling, Communications, Documentation • Chris Bennett • Structure Co-Head • —Presentation Collaborator • Matthew Dickinson • Structure Co-Head • —Testing Assistant • Jesse Ellison • Electronics Head • —Drafting/Design • SushiansRahimizadeh • Programming Head • —Mission Design • Alex Shelanski • Testing Head • —Film • Matt Holmes • Budget Head • —Programming Assistant, Documentation

  17. Biggest Worries • Time constraint • Vibration generator failure • Glitches in the programming • Component failure • Generator breaking on impact