Electrics Power requirement for Glasgow, Birmingham & Kent is 32 amp 3 phase.If you are hiring in a generator it will need to be a minimum 25KVA which will deliver 34.8 amps per phase. We also need it to deliver a clean stable feed as any “peaks” in the power could well cause projector lamps to blow.Also if you get the generator with tails terminating in either a 32 amp 3 phase or 63 amp 3 phase Cform socket we will supply distribution.Please position Cform socket to rear of stage.SpeedyHire do a range which would be suitable but I’m sure you will have accounts with some of the national tool hire companies.