An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MEG Beam Line Studies E5 Z-Branch NOW !!! MEG-Review February 2004

  2. Topics to be Addressed • Summary of Status at the time of the last Review • Current Component Status • Summary/Conclusions • Beam Line Schedule MEG-Review February 2004

  3. Summary Status (Review July 2003) • Beam Line Milestone just achieved – • Successful test of optics up to point of injection into COBRA Solenoid • As well as beam properties(Phase Space, Stopping rate, Separation Quality, etc.) • matching the proposed values • … using temporary components !!! Triplet I Separator II Triplet II PSC-Solenoid in: Nov. 2002 Defect !!! most Last Run Temporary Temporary out: Jun. 2003 out: Jun. 2003 out: Jun. 2003 out: Jun. 2003 -> LEM -> New -> Shorter -> Too Short Bore too small MEG-Review February 2004

  4. Summary Status (Review July 2003) – cont. • Beam Transport Solenoid BTS - under study • estimated earliest delivery …early summer 2004 • LN2 + LHe transfer Linesunder discussion • Remaining Beam Elements - under discussion MEG-Review February 2004

  5. Current Component Status – Triplet I + Separator • Triplet I: • - QSB Quadrupole magnetsbeing removed • during re-build of µE4 Area during • current Shutdown, will be assembled • as triplet • - Wagonfor triplet being constructed from • lower-part of shielding wagon • - High Acceptance +-slit Vacuum Chamber • under design •  Insertion Shutdown 2004 (~April) • Separator : • - New Vertical Separator was approved for MEG • design underway & HV-parts ordered •  not expected before October 2004 !!! MEG-Review February 2004

  6. Current Component Status – Triplet II + BTS • Triplet II: • -QSK Triplet + VacuumChamber removed from µE4 beam line • during current shutdown •  Available after shutdown 2004 (April) • Beam Transport Solenoid BTS: • - New superconducting solenoid which • replaces PSC-test Sol. used in Beam Tests • -Delayed !!! – due to • COBRA coupling problems more • complexthan envisaged • (ii) non-negligible amount of time • invested in beam & detector setup • simulation for LXe Large Prototype • test in 1 Oct. end Dec.2003 COBRA BTS MEG-Review February 2004

  7. Trip. Colli. WIEN Solenoid µ+ µ+ Triplet 2 e+ e+ Filter 1 Current Component Status – BTS cont. BTS – Complications: (i) focusing optics at Collimator found to be v. sensitive to STRAY FIELD solenoid excitation curve DESTROYED if Bfield TOO LARGE 50% of Stray Field from COBRA 5m away !!!  Compensation Coil Needed upstream of BTS under Design… MEG-Review February 2004

  8. COBRA BTS Deg1 Deg2 Current Component Status – BTS cont. • BTS – Complications: • (ii) • Requirements: • - BTS Bfield must have min. influence • on COBRA field in fiducial region • Min. beam-spot size at Target • contradictory!!! •  Only free parameters (coupled): • BBTS & ΔLCOBRA-BTS • Focus also dependent on how split degrader (M.S. vs. Background) Full Simulation underway: • TRANSPORT, TURTLE, Track  Optics • GEANT  spot-size, resolution • ANSYS  Magnetic influence • Delivery BTS not before ~Nov. 2004 MEG-Review February 2004

  9. Current Component Status – Cryo. Lines + Targets • LN2 & LHeTransfer Lines: • In planning phase • Targets: • simulation work concerning size underway in conjunction • with BTS studies, after which mechanics & He-Bag question • will be tackled MEG-Review February 2004

  10. Summary/Conclusions • Shutdown 2004 until mid April • Initially only Triplet I used for Timing-counter beam time while • COBRA installation runs in parallel (behind Concrete wall) • Old Separator + new Triplet II used for commissioning up to • BTS injection (June/July) • New Separator not until, at least October • BTS not before November so that commissioning 2nd part of • beam line (Need ~6 weeks for this) at end of year i.e. BTS must • arrive by beginning Nov. to use time effectively, otherwise Gotta • (PROBLEM GOTTA et al. 6 weeks BT end-of-year) • If beam line commissioned by end December •  Bfield Mapping COBRA during Shutdown 2004/5 Delay in Full Commissioning of MEG beam Line now expected Though Should NOT Delay Experiment Start !!! MEG-Review February 2004

  11. Provisional MEG Beam Schedule Gotta et al. ??? MEG-Review February 2004