BILL OF MATERIALS AUTOMATION

BILL OF MATERIALS AUTOMATION. Adi Y. Nugroho. SYSM 6309: Advanced Requirements Engineering Summer 2013. June 22 nd , 2013. Table of Content. Background Process Flow and Description Situation and Description Input and Output BOM Format Problems Solution Implementation Aspect

Download Presentation

BILL OF MATERIALS AUTOMATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BILL OF MATERIALS AUTOMATION Adi Y. Nugroho SYSM 6309: Advanced Requirements Engineering Summer 2013 June 22nd, 2013

  2. Table of Content • Background • Process Flow and Description • Situation and Description • Input and Output BOM Format • Problems • Solution • Implementation Aspect • Cost Estimation and Comparison • Summary

  3. Background • Engineering team had to deliver Bill of Materials (BOM) for sales and project team based on solution requirement and final design output. • Bill of Materials must used products described on solution document and match with final microwave design.

  4. Process Flow

  5. Process Description Solution Requirement High Level Design + Products Nominal Design Line of Sight Survey Site Acquisition Bill of Materials Final Design Engineering Scope

  6. Situation 1. Every site has unique BOM since it might has different parameters: • Number of links • Related to indoor unit type that will be used: 2/5/20 slots. • Link specifications: • Antenna diameter size: 1/2/4/6 feet • Antenna type: Std (Standard)/HP (High Power) • Radio Frequency: 11/15/23/28/38 GHz • Radio modulation: 4/16/64/126/256/512 QAM • Capacity: 30/60/125/200/350 Mbps • Link specification example: • 15GHz 064T/16 ANT0.6 HP (not all sites has the same spec!) • Antenna placement location • Antenna location: rooftopor tower • Related to radio cable size that will be used. Cable length size: 1 - 400 feet

  7. Situation 2. Total number of sites: 6000 sites nationwide. 3. BOM must have accuracy with maximum error tolerance 1% 4. Timeline: 2 months 5. Maximum number of resources 2 engineers.

  8. Situation Description Site Link • Even though these two sites have same condition (they have 2 links), it does not mean the BOM will be same. • The link spec might be different so is the antenna location. • One site can have high tower and the other site can be roof top. • One link can have MLTN28/2X 194T/64X-140 spec and the other can have 2010 28 064T/16-20 spec.

  9. Input BOM Format

  10. Output BOM Format

  11. Problems • Huge effort to finish the work with limited resources. • Rough Calculation: • 6000 : 2 engineer = 3000 sites/2 month/engineer = 65 sites/day/engineer • Supposed 1 engineer can finish 1 site BOM within 15 minutes with 8 working hours per day, it will take 4 months to complete the work. • Human error probability is high for repetition work. • Difficulties to track the document if there are some changes or revision during BOM generation process.

  12. Solution • BOM generator automation is needed to produce the BOM faster, less errors, more accurate, consistent, easy to track, and convenient for all end users.

  13. Implementation Aspects • In order to create this automation, a programmer with competence in .NET and C# language, SQL database, and web programming is needed. • The programmer resource will be taken from internship since the project duration is only 1-2 months. • The programmer must collaborate with Subject Matter Expert (SME) to produce the correct algorithm for all automation processes.

  14. Cost Estimation and Comparison vs Up to 85% cost reduction!

  15. SUMMARY • Engineering team had to deliver BOM for sales and project team based on solution requirement and final design output. • After analyzing all possible risks, we found 3 major problems that must be handled. • BOM generator automation is proposed as a solution for the problems. • Based on rough cost estimation, the tool is not only will speed up the process but it can reduce the operational cost up to 85% as well.

  16. Thank You