An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Digital 395SECRBC– Board PresentationDiscussion Guide February 28, 2013

  2. Project Status

  3. Rights-of-Way & Permits • ROW Remaining • All in place (Recent Washoe BIA Approval this week) • NTIA Route Changes for 5 Route Changes (2 NV, 3 CA) • Encroachment Permits • City of Reno Permits for M101( Approval 3/4/13) • Caltrans (Big Pine to China Lake) • Distribution • County Licenses for Kern County approval 3/3/13 • County and City licenses include Anchor Access Agreements • NTIA Route Changes for 25 anchors and POIs For Discussion Purposes Only

  4. Construction Status - Nevada • Installed Plant • Reno / Carson Nodes • 28 miles fiber (Reno-Carson) • Conduit: 2 Segments • Present Operations • Curtis & Sons, Apex • Focused on 395 thru Carson • Issues • BIA Approval to Proceed in N111-N113 • 2 Route Changes (2,000 ft)

  5. Construction Status – Mono County • Installed Plant • Antelope, Bridgeport, Lee Vining, Mammoth Nodes • 39 miles fiber (Coleville-VL) • Conduit: 8 Segments • Present Operations • Kleven, Westech, Apex, ASI • Focused State Line to June, and South of Mammoth to Crowley • Issues • Inyo National Forest • 1 Route Changes (Mammoth)

  6. Construction Status – Inyo County • Installed Plant • Bishop, Independence, and Nodes (Olancha is in GS10) • 2 miles fiber (Reno-Carson) • Conduit: 3 Segments • Present Operations • Westech – Heavily Plowing • Focused on southward from Bishop • Issues • BLM Trespass (Resolved) • Caltrans Permits • 1 Route Change (Round Valley)

  7. Caltrans Permit Progress

  8. Construction Status – Kern & South End • Installed Plant • Reno / Carson Nodes • 104 miles fiber (Barstow-Pearsonville) • Conduit: 15 Segments • Cable: 14 Segments • Present Operations • Westech, McCullin Pipeline • Ridgecrest Distribution • Focus • K121 (Inyokern Lateral) • County of Kern Distribution

  9. Environmental Issues / Responses • BLM • Claim: Trespassing into WSA: Outcome 200’ conduit re-installationt • $15K Study Cost; $20K for project monitoring • Section 106 Violations • N103 alleged disturbing of sacred artifacts - NTIA validated our practices • ESA Breach: Contractor drove over ESA; Invalidated by NTIA Study • INF archeological concerns: NTIA working with USFS • Long Bores (over 2,000 ft): negotiating for pit excavations, break up • Biological • Construction crews would be locked out of bird nesting areas: accelerated work in sensitive areas and obtained relief on timeframes • DFG 1602 Violations: Audit found unsatisfactory training with Sub-Contractors. Proactive Ride-Alongs, Training Sessions For Discussion Purposes Only

  10. Node Construction

  11. Node Construction For Discussion Purposes Only

  12. Distribution Construction • Key Service Areas (Ridgecrest, Mammoth, Bishop) • Contract Awarded to Kleven • Construction underway in Ridgecrest • Mammoth construction starts post April. To be challenged in March • Other Areas: Benton, Walker, Coleville, Bridgeport, Lee Vining, Big Pine, Independence, and Lone Pine • Praxis Focus (Aerial and Smaller Areas) • Boron • InyoKern • Round Valley (Aerial) • Benton Tribe(Aerial) • Bridgeport Indian Colony • China Lake Distribution (Aerial) • June Lake (Aerial) • Randsburg / Johannesberg (Aerial) • Cerro Community College (Aerial) For Discussion Purposes Only

  13. Inyokern Distribution and Anchors

  14. Ridgecrest Distribution and Anchors For Discussion Purposes Only

  15. Ridgecrest – China Lake Blvd.

  16. Bishop Distribution and Anchors

  17. Independence Distribution & Anchors For Discussion Purposes Only

  18. Anchor Status For Discussion Purposes Only

  19. Anchor Service Trench • Anchor Service Trench Integration With Backbone Conduit Placement. • When the backbone work is being done in the street the backbone contractor will place the service trench and conduit to the customer location. • Cost savings over separate service trench. Using the same equipment and work setup as the backbone • Time savings. One crew completes backbone and service trench/conduit placement • Less disruption to anchor locations • Praxis fiber and NID installation follows For Discussion Purposes Only

  20. Anchor Service Trench Ridgecrest Regional Hospital This service trench will be completed by boring onto Hospital property using the same work setup and equipment as the backbone work on K104 that places conduit on N China Lake Blvd For Discussion Purposes Only

  21. Thank You • www.digital395.com For Discussion Purposes Only