An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Establishing an Electric Distribution GIS Using ArcFM Melissa A. Williams, P.E. Senior Project Engineer Stantec Consulting September 29 - 30, 2011 | Hyatt Regency Hotel | Columbus, Ohio

  2. Establishing an Electric Distribution GIS Using ArcFM • City of Columbus Electric Distribution Digital Conversion Project • Telvent Multispeak Data Model, ArcFM Software • Data Conversion Strategy • Data Analysis/QC

  3. City of Columbus Electric Distribution Digital Conversion Project • Existing Datasets • AutoCAD drawings • Hand drawn manhole/vault sketches • Access database • GPS points

  4. City of Columbus Electric Distribution Digital Conversion Project • Existing Datasets: AutoCAD Single Line Drawings (underground)

  5. City of Columbus Electric Distribution Digital Conversion Project • Existing Datasets: AutoCAD Single Line Drawings (overhead)

  6. City of Columbus Electric Distribution Digital Conversion Project • Existing Datasets: AutoCAD Detail Drawings (manholes/vaults)

  7. City of Columbus Electric Distribution Digital Conversion Project • Existing Datasets: AutoCAD Detail Drawings (padmount transformers)

  8. City of Columbus Electric Distribution Digital Conversion Project • Existing Datasets: Hand drawn manhole/vault sketches

  9. City of Columbus Electric Distribution Digital Conversion Project • Goals • Seamless data showing primary distribution lines • Locations/attributes • Connectivity • Allow for future development / analysis

  10. Telvent Multispeak Data Model, ArcFM Software • Data Model created/maintained by Telvent GIS (formerly Telvent Miner & Miner) • M&M provided electrical engineering services since 1946 • Automated Mapping/Facilities Management/GIS since 1986 • Business partner with ESRI • Telvent ArcFM Enterprise GIS is an extension for ArcGIS

  11. Telvent Multispeak Data Model, ArcFM Software

  12. Telvent Multispeak Data Model, ArcFM Software • Customization of data model: • Used Microsoft Visio to make changes to data model • Added / Changed / Deleted attributes to match existing Access database fields • Added / Edited domains, subtypes

  13. Telvent Multispeak Data Model, ArcFM Software • Advantages of using ArcFM software (vs data model alone) • Ability to perform more complex analyses and better QC (e.g. electric traces) • Additional functionality through other Telvent solutions • Conduit Manager • Responder

  14. Telvent Multispeak Data Model, ArcFM Software • Conduit Manager

  15. Telvent Multispeak Data Model, ArcFM Software • Responder

  16. Data Conversion Strategy • No heads-up digitizing with georeferenced images • Start with GPS’ed and ortho-verfied point features • GPS points for poles, manholes/vaults • Ortho-verified padmount transformers

  17. Data Conversion Strategy • Create manhole diagrams for Conduit Manager

  18. Data Conversion Strategy • Digitize conduits between manholes/vaults • One conduit per duct bank • Split conduit if different configuration on each end • Snap to manhole/vault points

  19. Data Conversion Strategy • Digitize underground conductors from manhole to manhole • Break, but not snap at manholes

  20. Data Conversion Strategy • Add switches and transformers within manholes/vaults • Connect to match detail drawings • Use ArcFM favorites for composite features

  21. Data Conversion Strategy • Associate conductors to ducts in manholes to complete Conduit Manager diagrams

  22. Data Conversion Strategy • Associate conductors to ducts in manholes • Can split by phase to different ducts

  23. Data Conversion Strategy • Digitize overhead conductors, transformers • Draw close to, but don’t snap to poles • Don’t need to break at poles

  24. Data Conversion Strategy • Add additional devices on poles • Capacitors • Switches (section points, tie points, auto-transfer) • Risers (potheads), circuit feeders • Regulators • Reclosers • Fault Indicators

  25. Data Analysis/QC • ArcFM Electric Traces • FeederID attribute populated for energized conductors/devices • Can trace by phase • Can open/close switches to see new circuit path

  26. Data Analysis/QC • ArcFM Electric Traces

  27. Data Analysis/QC • ArcFM Feeder Manager Locator Tool • Will detect loops, devices energized by more than one circuit, de-energized devices