320 likes | 446 Views
U.S. ROUTE 202 – SECTION 300 IMPROVEMENT PROJECT East Whiteland Township – Tredyffrin Township Chester County. TMACC Information Session January 24, 2011. U.S. Route 202 – Section 300 Project Limits. U.S. ROUTE 30 TO NORTH VALLEY ROAD. U.S. Route 202 – Section 300 Construction Sections.
E N D
U.S. ROUTE 202 – SECTION 300IMPROVEMENT PROJECTEast Whiteland Township – Tredyffrin TownshipChester County TMACC Information Session January 24, 2011
U.S. Route 202 – Section 300 Project Limits U.S. ROUTE 30 TO NORTH VALLEY ROAD
U.S. Route 202 – Section 300Construction Sections • Section 3IT: Intelligent Transportation System Installation (June 2005 - June 2008) • Section 310: 3 Overhead Bridge Replacements & 2 Intersection Improvements (March 2007 - May 2009) • Section 311: 3 Overhead Bridge Replacements (Feb. 2008 - Aug. 2010) • Section 320: US 202 Mainline Widening and Reconstruction North of PA 401 (March 2011 – June 2014) • Section 330: US 202 Mainline Widening and Reconstruction South of PA 401 (Early 2013 – Late 2015)
U.S. Route 202, Section 3IT Project Summary • Started June 2005 • Completed June 2008 • Construction Cost $14.7 million • Highways: US 202, US 30, PA 100 • Fiber Optic Cable • CCTV Cameras/Poles (33) • Dynamic Message Signs (20) • Roadside Incident Detectors (61) • Travel Time Display (Began Nov. 2008) • PennDOT Traffic Management Center Video Wall
Intelligent Transportation System Detectors, Message Signs & Cameras
U.S. Route 202, Section 310 Project Summary • Started March 2007 • Completed May 2009 • Construction Cost $20 million • Replaced Mill Lane, Church Road and Swedesford Road bridges over US 202 • Widened PA 401 (Conestoga Road) • Improved PA 401/Phoenixville Pike Intersection • Improved Swedesford Road/ Phoenixville Pike/Planebrook Road Intersection • Built storm water management sites • Stream Stabilization & Restoration • Wetland Mitigation/Replacement
U.S. Route 202, Section 311 Project Summary • Started February 2008 • Completed August 2010 • Construction Cost $25.1 million • Replaced Swedesford Road, PA 29 and Cedar Hollow Road bridges over US 202 • Elevated abandoned railroad bridge over US 202 (Bridge to be repainted under Section 320 contract)
U.S. Route 202 Construction Section 320 SECTION 320 NORTHERN MAINLINE WIDENING (VALLEY CREEK BRIDGE TO NORTH VALLEY ROAD); NB COLLECTOR-DISTRIBUTOR ROAD AT PA 29 INTERCHANGE; US 202 BRIDGES over VALLEY CREEK & NORTH VALLEY ROAD
U.S. Route 202, Section 320 Project Summary • Bid Opening December 9, 2010 • Apparent Low Bid $105,415,093 ($115.9 including construction inspection) • Apparent Low Bidder (Contractor) Richard E. Pierson Construction Company, Inc. • Anticipated Notice To Proceed March 2011 • Estimated Completion Date June 2014
U.S. Route 202, Section 320Project Summary • Widen Four Miles of US 202 to 3 Lanes in Each Direction • Build Two-Mile Long NB Collector-Distributor Road at PA 29 Interchange • Rehabilitate & Widen Bridges over Valley Creek & North Valley Road • Install Concrete Glare Screen Barrier to Separate NB & SB Travel Lanes • Erect 16 Sign Structures • Erect 10 Design-Build Sound Barrier Walls • Construct 3 Design-Build Retaining Walls • Install 9 Storm Water Management Basins • Install 10 Storm Water Mitigation Areas
FUTURE NB U.S. ROUTE 202 UNDER SWEDESFORD ROAD
U.S. Route 202, Section 320Construction Staging Overview • 5 Stages of Construction • Maintain 2 Lanes of Traffic in Each Direction on US 202 During Peak Travel Hours (No Restrictions Weekdays 5 a.m. to 10 p.m.; Weekends 10 a.m. to Midnight) • Nighttime Lane Restrictions • Temporary Off-Peak Ramp Closures at various stages of construction (NB Ramps in 2012; SB Ramps in 2013) • North Valley Road to Remain Open • Tow Truck Assistance During Construction
U.S. Route 202, Section 320Stage 1 Construction • Rebuild Outside SB US 202 Shoulder at Night (Weeknights 10 pm to 5 am; Weekends Midnight to 10 am) • Maintain 1 SB Travel Lane During Overnight Work Hours • Install Concrete Barrier on Outside SB Shoulder • Install Drainage Cross Pipes under US 202 • Stage 1 Construction – Spring 2011 Southbound Southbound Northbound Northbound
U.S. Route 202, Section 320Stage 2 Construction • Shift SB US 202 Traffic to Reconstructed Outside Shoulder & Travel Lane • Install Concrete Glare Screen Barrier on SB 202 for Stage 3 • Widen SB US 202 20 feet into Median to Accommodate future NB Travel Lanes • Begin Rehabilitation/Widening of Bridges over Valley Creek & North Valley Road • Stage 2 Construction – Mid-Spring to Fall 2011 Southbound Southbound Northbound Northbound
U.S. Route 202, Section 320Stage 3 Construction • Shift 2 NB Lanes over to SB Side of US 202 • Four 12-Foot Wide Lanes on SB US 202 • Rebuild NB US 202, Bridges & Ramps • Build NB US 202 Collector/Distributor Road at PA 29 Interchange • Stage 3 Construction – Fall 2011 to Late 2012 Southbound Southbound Northbound Northbound
U.S. Route 202, Section 320Stage 4 Construction • Shift All Traffic over to Rebuilt Side of NB US 202 • Four 12-foot Wide Lanes on Widened NB US 202 & Collector/Distributor Road • Reconstruct SB US 202 Mainline, Bridges & Ramps • Stage 4 Construction – Late 2012 to Late 2013 Southbound Southbound Northbound Northbound
U.S. Route 202, Section 320Stage 5 Construction • Move 2 SB Lanes Over to Rebuilt SB Side of US 202 • Two 12-foot Wide Lanes on NB and SB US 202 • Reconstruct Center Median and Concrete Shoulders • Stage 5 Construction – Early 2014 to June 2014 Southbound Southbound Northbound Northbound
U.S. Route 202, Section 320Cross Section • US 202 with NB Collector/Distributor Lanes at PA 29 Interchange • US 202 in 6-Lane Area
U.S. Route 202Section 320 ITS • ITS coverage on US 202, US 30 and PA 100 • First Travel Time System in PA
U.S. Route 202Section 320 ITS • Intelligent Transportation System Deployments • Closed Circuit TV Camera • 1 location • Vehicle Detection System • 19 locations • Travel Time Systems • 22 locations • Communication System • 9 hubs
U.S. Route 202Section 320 ITS • Travel Time System • Expand existing system onto I-76, I-476, US 202, I-95 • Travel Times updated every 20 seconds and displayed on Dynamic Message Signs • Covers US 202 from Matlack Street to I-76; US 30 from US 202 to US 322; PA 100 from US 202 to PA Turnpike • Greater accuracy and reliability with tag reader technology • Includes tag reader cabinet & overhead lane components • Travel Time System based on TRANSCOM architecture that is used on I-76 and on highways in N.Y., N.J. and Conn.
U.S. Route 202 Construction Section 330 SECTION 330 SOUTHERN MAINLINE (US 30 TO VALLEY CREEK BRIDGE) – 2.5 Miles MAINLINE BRIDGES: US 202 over AMTRAK, PLANEBROOK ROAD, CHESTER VALLEY TRAIL, PA 401
Section 330 – Project Summary • Widen 2.5 Miles of US 202 to Three Lanes in Each Direction • Replace Bridges over Chester Valley Trail and PA 401 • Widen Bridge over Planebrook Road • Resurface Bridges over Amtrak • Install Concrete Glare Screen Barrier to Separate NB & SB Travel Lanes • Erect 4 Sign Structures • Erect 12 Design-Build Sound Barrier Walls • Construct 5 Storm Water Management Basins • Upgrade Existing ITS Fiber Optic Cable
Section 330 - Project Summary • Estimated Construction Cost $82.7M • Road, Bridge and Sound Wall Design • Acquire 7 Parcels of Property • Environmental Permit Submission Mid-2011 • Anticipated Final Construction Plan Submission June 2012
Section 330 – Project Summary • Advertise Construction Plans August 2012 • Anticipated Construction Bid Opening October 2012 • Expected Construction Start Early 2013 • Expected Construction Finish Late 2015
U.S. Route 202 Section 300 Congestion Mitigation Program • TMACC and GVFTMA Marketing Campaigns • Guide to Commuter Options Brochure • Supplemental SEPTA Bus & Rail Services • Beeline Bus Route • Cruise Line Shuttle • Exton Station Parking Expansion • Chester Valley Trail • Construct Park & Ride Lot at US 30/US 322 Interchange (Caln Township)
U.S. Route 202, Section 300Overall Project Costs DESIGN Preliminary $12.0 M Final $19.0 M* Utility / ROW $ 6.4 M* CONSTRUCTION Section 3IT $14.7 M Section 310 $20.0 M Section 311 $25.1 M Section 320 $115.9 M** Section 330 $82.7 M* Total Estimated Project Cost $295.8 M Total Cost Spent to Date $ 90.6 M * Current estimate ** Apparent low bid plus construction inspection costs
For More Informationwww.us202-300.com Project Website
Questions? U.S. Route 202, Section 300