Integrated Safety and Environmental Management. M. Scharfenstein - ES&H Coordinator 13 May 2009. Construction, Commissioning, Operations Readiness for Users DOE O 450.1 / Safety Management System (ISM) DOE O 413.3A / Program and Project Management DOE O 420.2A / Accelerator Safety
E N D
Integrated Safety and Environmental Management M. Scharfenstein - ES&H Coordinator 13 May 2009
Construction, Commissioning, Operations Readiness for Users • DOE O 450.1 / Safety Management System (ISM) • DOE O 413.3A / Program and Project Management • DOE O 420.2A / Accelerator Safety The Environmental Assessment developed for the LCLS resulted in a Finding of No Significant Impact
Far Experimental Hall Near Experimental Hall 1st Undulator
Construction, Commissioning, Operations - Readiness for Users • DOE O 450.1 / Safety Management System • SLAC Integrated Safety and Environmental Management Plan • SLAC ES&H Manual and Guideline for Operations • DOE O 413.3A / Program and Project Management • Lessons Learned (413.3A) • SNS and NIF Lessons Learned documents • development of LCLS Project ES&H/Safety Lessons Learned • SLAC process driven by Operating Experience Program (210.2) • DOE O 420.2B / Accelerator Safety • Accelerator Readiness Reviews • Safety Assessment Document • Accelerator Safety Envelope • Experimental Area Readiness Reviews • Ready for Users
ISM Process Construction of buildings, installation of technical systems, commissioning and operations through the Electron Beam Dump • LCLS Requirement, Specification and Interface Documents • Physics Requirements Documents, Engineering Specification Documents, Preliminary & Final Design Reviews, etc • LCLS Work Authorization (Lab’s WPC process) • Preliminary and Final Design Review + SLAC SOC Reviews • Project Management sign-off • LCLS Project ES&H Plan(Lab’s ES&H process) • Job Safety Analysis • Daily Tailgate Safety Meetings • PM/UTR manages each subcontract • Management Safety Observation Process (adopted by Lab) • Positive reinforcement of safety • CF5 Feed back & Improvement • Lessons Learned
ISM Process cont’d Commissioning and Operations – Ready for Users • Injector • Accelerator Readiness Review (2007) • Beam Line to Beam Switch Yard • Undulator Complex • Accelerator Readiness Review (2008) • Front End Enclosure • Internal Review with SSO Approval (now) • Update of SAD and ASE • Beam Authorization Sheet • Safety Officer Approvals • Experimental Areas • Accelerator Readiness Review (June) • Instrument Readiness Review for each Experimental Station • AMO Commissioning (July) • Begin general User Program (Sept)
PROJECT SAFETY EXPERIENCEThrough March 2009 DART Rate • Total Project Hours • 2.16 M Hours worked • DART Rate 1.03 • SubContractors • 597 K Hours worked • DART Rate 3.02 (9 Incidents) • TRC Rate 4.02 (3 Incidents) • LCLS Collaboration • 1,566 K Hours worked • DART Rate 0.26 (2 Incidents) Injury rates based on 200 K hours (100 man years) of effort.DOE/SC Goal is a Reportable Case (TRC) rate of < 0.25 and a Days Away, Restricted, or Transferred (DART) rate < 0.65 per 100 FTEs.
CF & Technical Systems Stewardship • Excellent Safety Record • 120K+ hours w/o injury (TRC or DART) • S20, MMF, Injector, Linac TSI, S522, LTU • Project Managers / UTRs / Installation Managers • Direct management of subcontractors • Communicate ES&H Expectations • Guide them to success • Enforcement when needed • Thorough Work Planning and Control • Aggressive ISM management • Issues identified and addressed immediately • Positive Results • Ownership of safety
Dec ‘05 Feb ‘07
Nov ‘05 Dec ‘08
CF CMGC Stewardship • October ’06 thru April ’07 Ramp Up to Full Production : Procedural Violations • Stand Down of Construction Activities : All Hands Meeting • Review of Work Planning Process for field work – JSA process inadequate • PMT changes, Deficiency Notices, Fines • May ’07 thru November ’07 Full Production : DARTs • Multi-day Stand Down of Construction Activities : Corrective Action Plan • Communication with Corporate TCCo • Safety Stewardship Committee Established • Full time on-site medic (+30hr OSHA) • December ’07 thru April ’08 : Some progress, then… • Two DARTs associated with one sub • Work stopped • May ’08 thru December ’08 : No DARTs • Effective work planning & execution • Attendance at daily morning work planning meetings • JSA review with workers throughout the day • Identification / monitoring of specific trades or tasks for safe work practices
July ‘07 Nov ‘07 Dec ‘06 Apr ‘08
Near Experimental Hall November 2008 Far Experimental Hall December 2008
Conclusion • Integrated Safety and Environmental Management(450.1) • Following SLAC ISEMS Process • SLAC ES&H Manual • Work Planning and Control • Lessons Learned (413.3A) • SLAC program (210.2) • Following LCLS ISM management practices • LCLS Requirement, Specification and Interface Documents • Reviews, Authorizations, Continuous Improvement • Accelerator Safety • Safety Assessment Document • Accelerator Safety Envelope • Readiness Reviews • Accelerator • Experimental Areas Ready for Users