URBAN SETTLEMENTS DEVELOPMENT GRANT CITY OF JOHANNESBURG REPORT ON PROGRESS

URBAN SETTLEMENTS DEVELOPMENT GRANT CITY OF JOHANNESBURG REPORT ON PROGRESS PORTFOLIO COMMITTEE ON HUMAN SETTLEMENTS – 12 SEPTEMBER 2012. Presentation Content. Strategic Spatial Overview 2011/2012 Delivery 2012/2013 Planned projects.

Download Presentation

URBAN SETTLEMENTS DEVELOPMENT GRANT CITY OF JOHANNESBURG REPORT ON PROGRESS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. URBAN SETTLEMENTS DEVELOPMENT GRANT CITY OF JOHANNESBURG REPORT ON PROGRESS PORTFOLIO COMMITTEE ON HUMAN SETTLEMENTS – 12 SEPTEMBER 2012

  2. Presentation Content • Strategic Spatial Overview • 2011/2012 Delivery • 2012/2013 Planned projects

  3. GROWTH DEVELOPMENT STRATEGY (GDS) / INTEGRATED DEVELOPMENT PLAN (IDP) * Components to achieve Desired Urban Form POLICY SIGNIFICANCE < REGION / NEIGHBOURHOOD PROVINCIAL / CITY > < Detail / Guidelines > Status Quo / Development Trends Growth Management Strategy SHS Urbanisation Plan Capital Investment Framework Sub-Area D’ment Objectives Tables REGIONAL SDFs (RSDFs) Detail Design / Dev. Controls PRECINCT PLANS / URBAN DF’s Desired Urban Form / Objectives: Efficient, Sustainable, Accessible City SPATIAL DEVELOPMENT FRAMEWORK (SDF)* BUILT ENVIRONMENT PERFORMANCE PLAN

  4. BROAD REGIONAL CONTEXT Population Deprivation Index

  5. Informal Settlements – Citywide Assessment • +/-156 000 Informal Settlement • 43 000 in Ivory Park • 27 000 in Soweto • 21 000 in Diepsloot • 17 000 in Greater Orange Farm • 12 000 in Alexandra • 1 000 in CBD

  6. Backyard Shacks – Citywide Assessment • +/- 320 800 Backyard Shacks Citywide • 164 000 in Soweto • 72 000 in Ivory Park • 41 600 in Dieplsoot • 27 000 in Greater Orange Farm • 7 000 in Alexandra • 3 000 in CBD

  7. Priority Growth Areas Ivory Park+ Soweto + Alexandra + Orange Farm + Dieplsoot + 1km distance from • Existing / Upgraded Rail + • Developing Gautrain + • Developing Phase1 BRT= • Densification priority • Infrastructure priority • Capex priority • Development priority

  8. Sustainable human settlements City / State: • Opportunities for major transit orientated development linked to economic and job creation opportunities • BRT • Rail stations • Infill • Expansion • Redevelopment Market/private sector: • Introduction of Inclusionary housing along public transport corridors • Additional incentives to facilitate “gap” market housing within the prime development areas • Role of Backyard Shacks / Rooms (a market is providing this currently…)

  9. Land Acquisition Priorities • Provisional R250m p/a for strategic land acquisition • Immediate need in Princess, Diepsloot and Zandspruit areas • Medium term land acquisition • Diepsloot corridor • Doornfontein corridor • Rail and BRT network in support of TOD • SHSHUP strategic areas (work in progress) • City’s Joint Land Steering Committee

  10. 10/25/2014 10

  11. Current and medium-term housing projects Housing projects 2012/13 Housing projects medium-term

  12. Current and medium-term Joshco projects

  13. USDG COMMUNITY FACILITIES

  14. OUTPUTS AND PERFORMANCE 2011/2012

  15. USDG OUTPUTS AND PERFORMANCE – FY 2011/12 10/25/2014 15

  16. R’000 % 1ST QUARTER - R 56,942 6% 2ND QUARTER - R 149,858 16% 3RD QUARTER - R 254,400 26% 4TH QUARTER - R 508,437 52% TOTAL - R 969 637 92. 6% FINANCIAL PERFORMANCE PER QUARTER (PRELIMINARY FIGURES)

  17. PROJECTS TO BE ROLLED-OVER TO FY 2012/13 R’000’s PROJECTS PORTION % COMPLETEUNSPENT • Sol Plaatjie Roads and Storm-water 60% R 2,088 • Lakeside X 1 & 3 Roads and Storm-water 80% R 1,553 • Kliptown Roads and Storm-water 60% R 10,573 • Braamfischerville X 13 Roads and Storm-water 90% R 2,233 • Land Purchases (in neg) R 23,048 • Lufhereng Bulk Infrastructure 60% R 22,826 • Vlakfontein West Various Bulk Services 95% R 7,292 • Emma Flats Bulk Storm-water 95% R 498 • Formalisation of Informal Settlements 95% R 734

  18. PROJECTS TO BE ROLLED-OVER TO FY 2012/13 R’000’s PROJECTS PORTION % COMPLETEUNSPENT • Storm-water Master planning 78% R 3,613 • Conversion of Open Drains to Underground/Covered Drains 80% R 703 • Emergency Storm-water Projects 75% R 302 • Gravel Roads- Diepsloot, Ivory Park, Orange Farm 95% R 976 • TOTAL R 76,439 • NOTES • 1) Projects are contractually committed. • 2) NT request for roll-over submitted 28 August 2012.