HMI Instrument Status HM/AIA Science Meeting February 13, 2006

HMI Instrument Status HM/AIA Science Meeting February 13, 2006. Outline. A year in the life of HMI development HMI assembly progress HMI testing progress Near term events Schedule summary The last time we met, we had finished CDR and were starting structural model testing.

otto-wilder
Download Presentation

HMI Instrument Status HM/AIA Science Meeting February 13, 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HMIInstrument StatusHM/AIA Science MeetingFebruary 13, 2006

  2. Outline • A year in the life of HMI development • HMI assembly progress • HMI testing progress • Near term events • Schedule summary The last time we met, we had finished CDR and were starting structural model testing.

  3. HMI Assembly Status Feb Apr May Mar Structural model testing completed Received flight Michelsons All flight optics in house ETU oven testing completed BB HEB fabrication completed SUROM acceptance test completed mission CDR Jun Aug Jul Hollow core motors completed Received DM cameras Received 4 grade zero CCDs Received flight structure Start alignment on GSE bench Received flight metering tube Completed telescope alignment Nov Oct Sep Dec Alignment mechanism completed Started optical alignment of HOP Focal plane completed Oven completed First image BB HEB and EGSE ready Shutter & F/C wheels completed Internal harness completed Lyot completed Internal mechanisms tested

  4. Internal Harness (Flight, not complete) Shutters (Flight) BDS Fold Mirror (Flight) Alignment Mechanism (Flight, hidden in view) BDS Beamsplitter (Flight, hidden by shutter) Oven Assembly (non-flight) Parts to replace: E1 and E2 in Lyot NB Michelson Painted housing CCD Fold Mirror (Flight, hidden by detector) Detector Assembly (Non-Flight) Oven Controller (ETU) Flex-Cables (Eng Model) ISS Beam Splitter (Flight) CEB (Non-Flight, DM1) ISS Mirror (Flight) Limb Sensor (Non-Flight) Polarization Selector (Flight) Limb Pre-amp Box (Flight, not complete) Focus/Cal Wheels (Flight) Telescope (Flight) Structure W/ legs and heaters (Flight) Front Window (Flight) Optics Package Assembly • Primary work after Sun testing: • Bond optics in place • Replace painted parts (including the oven) • Replace one HCM and focus/cal optical mounts HMI Assembly Status

  5. “HMI is Alive” First Image “Special Target” First Lamp Image “Ready to Test” Instrument All Together “No More Moon” Better Laser Image “It’s a Beautiful Day” First Sun Image Laser dot Before holiday No relay lens No Lyot No frt Window Special target Lamp - stim tel Lyot installed Temp mnt for relay lens Not fully aligned stim tel Air Force target Lamp - stim tel All together Laser intensity improved Just sunlight With air/vac corrector 12/22/06 01/11/06 01/25/06 02/01/06 01/30/06 HMI Testing Progress Tests Performed: Initial set up w/ lamp Focus test w/ lamp Distortion, field curvature and MTF w/ lamp Focus test w/ Sun Filter wavelength dependence w/ Sun Tests In Progress: Filter wavelength dependence w/ laser Field curvature and MTF w/ Sun Polarization calibration w/ Sun

  6. HMI Testing Progress First Dopplergram First Magnetogram

  7. Upcoming Events • Near term key hardware items • Continue Sun testing • Continue ISS testing • Complete rebuild of oven • Replace Lyot E1 and E2 • Replace narrow band Michelson • Replace one wave plate mount and focus block mounts • Bond optics in mounts • Install flight focal planes and align CCDs • Further out • In air calibration Mid April – May • Vacuum calibration June – mid July

  8. Schedule Summary • Complete initial testing Feb 06 • Complete instrument integration April 06 • Except flight camera electronics box • Pre-Environmental Review April 06 • Instrument calibration April – July 06 • In air April – May 06 • Need brassboard camera interface board • Use demonstration camera electronics box • In vacuum June – July 06 • Mid-stream install flight camera electronics box • HOP vibration & acoustic test July 06 • Comprehensive performance test Aug 06 • With flight HMI electronics box • Instrument EMI/EMC test Sept 06 • HMI electronics box vibration test Oct 06 • Thermal vacuum cycling and balance test Nov – Dec 06 • Comprehensive performance test Dec 06 • Alignment with instrument module panel Jan 07 • Pre-Ship Review Jan 07 • Ship to Goddard Feb 07