300 likes | 313 Views
This chapter discusses the termination of projects, including the reasons for termination, the different ways projects can be terminated, and the process of project termination. It also covers the impact of termination on other areas and emphasizes the need to plan and execute termination with care.
E N D
Chapter 12 Project Termination
ProjectTermination AllThingsCometoanEnd 2
Introduction • All projects end • The objectives have been completed • Some project teams move on to other projects • Other times, members goes their own way
AllThingsCometoanEnd Termination –Impactonotherareas –Planandexecuteterminationwithcare 3
WhenDoProjectsTerminate? Upon successful completion, –or... When the organization is no longerwillingtoinvest 4
MostCommonReasonsProjectsTerminate 1. Low probability of success2. Low profitability 3. Increasing cost 4. Change in competitive factors 5. Un-resolvable technical problems6. Higher priority 7. Schedule delays Source: Dean, 1968 5
The Varieties of Project Termination • A project can be said to be terminated when work on the substance of the project has ceased or slowed to the point that further progress is no longer possible • There are four fundamentally different ways to close out a project: extinction, addition, integration, and starvation
The Varieties of Project Termination • Termination by extinction • Termination by addition • Termination by integration • Termination by starvation
Termination by Extinction • Extinction occurs in any scenario where the project goes away • Successful • Unsuccessful • Changes in environment • When work on a project stops, some organizational work continues
Termination by Addition • Applies to an in-house project • When the project is successful, it is institutionalized • While the project goes away, project personnel and assets are transferred to the new business
Termination by Integration • The most common way to terminate a project • The project comes into the business • It is absorbed into the existing structure • That structure absorbs the assets of the project
Termination by Starvation • Termination by starvation involves greatly reducing the budget of a project • There are many reasons why senior management does not wish to terminate an unsuccessful or obsolete project: • Used when it is politically dangerous to cancel a project • Terminating a project that has not accomplished its goals is an admission of failure
A Project is said to be terminated WHEN: • Work on the substance of the project has ceased or slowed to the extent that further progress on the project is no longer possible. • Project is indefinitely delayed. • Resources have been deployed to other projects.
Non-Technical Reasons for Termination • Political • Cross-cultural • Senescence
When to Terminate a Project • Some questions to ask when considering termination: • Has the project been hindered by technical advances? • Is the output of the project still cost-effective? • Is it time to integrate or add the project as a part of regular operations? • Are there better alternative uses for the funds, time and personnel devoted to the project? • Has a change in the environment altered the need for the project’s output?
When to Terminate a Project WHEN: • Work on the substance of the project has ceased or slowed to the extent that further progress on the project is no longer possible. • Project is indefinitely delayed. • Resources have been deployed to other projects. • Fundamental reasons why some projects fail to produce satisfactory answers to termination questions: • Insufficient support from senior management • Naming the wrong person as project manager • Poor planning
The Termination Process • The termination process has two distinct parts • First is the decision whether or not to terminate • Second, if the decision is to terminate the project, the decision must be carried out
The Termination Process • Must first decide to terminate • Next, must carry out the decision to terminate
The Decision Process • Sunk costs are not relevant to the decision about terminating a project • The main issue is if the cost to finish is more/less than the value of the project when finished
The Implementation Process • The actual termination can be planned and orderly. • Special termination managers are sometimes useful in completing the long and involved process of shutting down a project • The primary duties of the manager in charge of termination can be encompassed in nine general tasks
The Implementation Process • Duties of the termination manager: • Ensure completion of the work, including tasks performed by subcontractors • Notify the client of project completion and ensure that delivery is accomplished • Ensure that documentation is complete including a terminal evaluation of the project deliverables and preparation of the project’s Final Report • Clear for final billings and oversee preparation of the final invoices sent to the client
The Implementation Process • Duties of the termination manager (cont.): • Redistribute personnel, materials equipment, and any other resources to the appropriate places • Clear project with legal counsel or consultant • Determine what records to keep • Ascertain any product support requirements, decide how each support will be delivered, and assign responsibility • Oversee the closing of the project’s books
The Implementation Process • Most project managers delay the personnel reassignment/release issue as long as possible for three main reasons: • 1. A strong reluctance to face the interpersonal conflicts that might arise when new assignments and layoffs are announced • 2. Worry that people will lose interest and stop work on the project as soon as it becomes known that termination is being considered • 3. Concern that team members will try to avoid death by stretching out the work as far as possible
The Implementation Process • Termination can be orderly • Planning for an implementing an orderly shut down yields better results • Who leads the shut down project • A special termination manager may be used
Things to Do • Insure tasks are completed • Notify the client • Finish the paperwork • Send out final invoices to the client • Redistribute resources • Clear with legal • Determine what records to keep • Assign support • Close the project books
The Final Report—A Project History • Project performance • Administrative performance • Organizational structure • Project and administrative teams • Techniques of project management
The Final Report - A Project History • The final report is the history of the project • It is a chronicle of the life and times of the project, a compendium of what went right and what went wrong • The required information is contained in the master plan, all project audits, and evaluations • The precise organization of the report is not of great concern; the content is
The Final Report • Several Subjects should be addressed in the final report: • Project performance • Administrative performance • Organizational structure • Project and administrative teams • Techniques of project management
The Final Report • For each element covered in the final report, recommendations for changing current practice should be made and defended • Equally important are comments and recommendations about those aspects of the project that worked unusually well • The fundamental purpose of the final report is to improve future projects
Summary • A project can be terminated in one of four ways: by extinction, addition, integration, or starvation • Making a decision to terminate a project before its completion is difficult, but a number of factors can be of help in reaching a decision • Studies have shown that the factors associated with project success are different for different industries and the various types of projects