Thanks for Being Here. THANKS FOR BEING HERE. Introduction to the Funding Analysis Tool BETA TEST VERSION. Funding the North Topsail Beach Beach Erosion Management Program Funding Workshop Series # 3A and 3B August 11 , 2012. PETER A. RAVELLA, PRINCIPAL PAR CONSULTING, LLC.
E N D
Thanks for Being Here THANKS FOR BEING HERE
Introduction to the Funding Analysis ToolBETA TEST VERSION Funding the North Topsail Beach Beach Erosion Management Program Funding Workshop Series # 3A and 3B August 11, 2012 PETER A. RAVELLA, PRINCIPAL PAR CONSULTING, LLC
Today’s Workshop Agenda • Funding Planning Process Schedule Update • Introduction to the Funding Analysis Tool (Beta Version) • Assumptions • Variables • Presentation of the Funding Analysis Tool (Beta Version) • Using the Tool • Feedback Today • Review and refinement before September 8
Funding Plan Workshops May 12: 1 - Funding Principles & Secrets June 23: 2 - Funding Concepts August 11: 3 - Funding Analysis Tool (Beta version) Sept. 8: 4 - Applying the Tool to the Updated Project Plan October 6: 5 - Draft Funding Plan & Initiation of Public Review Dec. 6: Funding Plan Recommendation to BOA
Working to Establish aBeach Erosion Capitol Fund • Dedicated 30-year fund to pay for projects, ensure FEMA eligibility for post-storm recovery, and prepare for possible Static Line Exception • Proposed Fund Purposes • Design & Permitting • Project Construction • Beach Monitoring Program • Dune Maintenance Program
Funding Analysis ToolPreliminary Project Assumptions(Beta Version) • Project Costs: Placeholder costs included • Project Timing: Four year project interval • State Share: 25% (BEST used 0% to 75%) • Outside Contributions: $500K to $1M • Onslow County • Parking or Beach User Fees • Occupancy Tax Rate Change (Requires legislation) • Others as may be indentified
Funding Analysis ToolPreliminary Bond Assumptions(Beta Version) • Bond Issuance: Contemporaneous with Project Phase • Bond Admin Cost: 2% • Bond Interest Rate: 4% • Bond Payback Period: 5 years • Maximum Bond Debt: $35 million at any one time • Repayment Method: Level principle plus interest
Cost Optimization:Can Projects Be Made More Affordable? • As the funding plan comes into focus, the tool allows the Town to examine the financial feasibility of various project options. • At the direction of the Town, CP&E is currently re-examining the beach erosion management strategy to determine if project cost savings can be found. • The September 8 workshop (tentative) is intended to integrate the updated Funding Analysis Tool and any updated project costs and savings.
Expected Improvements to theFunding Analysis Tool Beta Version • Addition of projects phases and bonds through 2042 • Correct any automation/formula flaws • Add capacity to change interest rate for each bond • Improve assessed valuation growth calculation • Ensure conformance with LGC requirements • Incorporate updated CP&E project costs and schedule • Integrate federal project cost & schedule assumptions