LTU/Undulator Installation Status

LTU/Undulator Installation Status. Enzo Carrone June 17 th , 2008. Scope. Install, Commission and Test Controls by JAN 09. Subsystems: BPM Cable Plant (monitoring) LTU Motion Control - UCM (Undulator Control Modules) Magnet Power MPS Network PPS/BCS Timing Vacuum. AMO

pascha
Download Presentation

LTU/Undulator Installation Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LTU/Undulator Installation Status Enzo Carrone June 17th , 2008

  2. Scope • Install, Commission and Test Controls by JAN 09. • Subsystems: • BPM • Cable Plant (monitoring) • LTU Motion Control - UCM (Undulator Control Modules) • Magnet Power • MPS • Network • PPS/BCS • Timing • Vacuum

  3. AMO Experiment program begins XPP Experiment program begins LCLS Installation and Commissioning Time-Line First Light in FEE First Light in FEH PPS Cert. LTU/Dump LTU/Und/Dump Install X-Rays in NEH CD-4 (7/31/2010) FEE/NEH Install FEH Hutch BO FEH Install PEP-II run ends now J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A A M 2008 2009 2010 Down PPS LTU/Und Comm. Linac/BC2 Commissioning Re-commission Inj/BC2 to SL2 FEE Comm. April 18, 2008

  4. Phase 4 Installation

  5. Ion Pump Undulator Magnet BFW QUAD Girder RFBPM WPM RF Receiver Box HLS Interface Cable Box 5

  6. Undulator Segment (Wall side) (Courtesy of Scott Doran, ANL) EIA(Raceway) Vacuum chamber

  7. BFW Undulator Segment (Aisle side) Quad/Corrector BPM Translation Stage Electronics Rack (UCM) CAM Mover

  8. UIR- (Undulator Instrumentation Rack)

  9. Electronic Interface Assembly (EIA)

  10. Electronic Interface Assembly (EIA)

  11. Time Management • Schedule • Three levels of scheduling: System (working), Controls (management), Master (communication). • Owners: System Leads, LCLS Installation Manager, LCLS Project Office. • Structure: waterfall approach.

  12. Schedule Control: • Weekly Master Installation Schedule Management Meetings: review of schedule, action items, technical, personnel and safety issues. • Same for Weekly Controls Schedule Management. • Master Schedule organized both by geographical and system representation.

  13. Management Schedule

  14. Milestones

  15. ANL Delivery • A delegation from SLAC visited ANL in May, 08 (A. Alarcon, E. Carrone, E. Williams). • The outcome has been very satisfying: • An assembly line has been setup at ANL to populate the Undulator Instrumentation Racks (“Mini Racks”); • EIA are manufactured outside; • The whole manufacturing/subcontractor management process is very well organized; • LTT is remarkably accurate; • ANL has been doing heroic efforts to deliver in time.

  16. UIR Assembly Line

  17. ANL Racks shipping

  18. Undulator Motion Controls Installation • 16 pre-assembled UIR received from ANL on June, 16th; • EIA will be shipped on next June, 24th. • Installation is Davis-Bacon; • Begin: 6/16/08 – End: 6/26/08. • ANL has released a “Handover Plan”. • SLAC to follow a documented procedure for test and installation.

  19. Undulator Motion Control Installation Schedule

  20. Racks – Weekly Readiness Status

  21. Rack Population Tracking System Building 24 assembly area

  22. Racks in the field 0 of 39 25 of 70

  23. Vacuum • All LTU PLCs assembled and programmed; • Complete: • BTH: 7/25/08 • UH: 10/2/08

  24. MPS • Link Processor and Link Node complete; • Beam Loss Monitor complete; • A nice test bench is in use. • Complete: • BTH: 10/28/08 • UH: 10/29/08

  25. BPM • 50 BPM Chassis complete, tested and installed; • Cavity BPM Receiver Power Supply and Signal Distribution Panels complete; • Complete: • BTH: 10/14/08 • UH: 10/27/08

  26. PPS/BCS • New organization: Documentation Office (Leader: M. Saleski); • PLC firmware updated; • Critical safety software complete (PILZ).

  27. New Organization

  28. PPS/BCS • A LION mockup has been installed in the Undulator Hall during last week; • Complete: • BTH: 20/6/08 • UH: 9/30/08 (a little ahead) • Certification: 10/20/08 to 10/31/08

  29. Network • Cable Fibers are being pulled; • Complete: • BTH: 6/30/08 • UH: 9/18/08 Cable Plant • Davis-Bacon contract. • Complete: • BTH: 9/9/08 • UH: 9/23/08

  30. Magnets Power Supply Timing • All Racks in B912 Installed; • DataBase and displays ready; • Complete: • BTH: 12/09/08 • UH: 10/7/08 • Complete: • BTH: 9/23/08 • UH: 10/28/08

  31. Installation J. Murphy

  32. SLAC On-Field Installation Management • Daily tailgate meetings (by K. Ratkliffe/M. Zurawel) • Review parts availability, deliveries, acceptance, inventories; • Discuss daily work plan, technical and transportation issues, personnel issues and safety issues. • Turner and LCLS meet weekly for co-occupancy schedule integration • A set of procedures and documentation is available on line (sharepoint).

  33. Installation Management - Safety • System Leads are being “Green Dot” trained and certified by SLAC/TCCo. • LCLS Project Office has put in place a systematic procedure for construction area access. • A Pilot Project (BCS LION Installation) paved the road.

  34. Areas to watch carefully • Tight Installation Schedule • ANL is delivering in time. • MPS (new system); • BLMs (schedule, budget); • Downtime → PPS (Certification, upgrades, preventive maintenance); • Motion Controls; • Co-occupancy with TCCo.

  35. Summary • Controls installation expected on schedule; • Controls will not be in the way of the beam delivery to LTU in next Jan 09; • SLAC can count on the assistance of ANL system experts on site, if needed.

  36. Special thanks to the ANL team for working so hard to deliver in time!