Lessons from the December storm

Lessons from the December storm. Board Meeting January 26, 2011. 4. Storm chronology – major storm affecting entire region. 4. Successfully managing storms has 4 phases. 1. Track storm forecasts Continuously assess storm impact and response required Update and disseminate alert levels

patch
Download Presentation

Lessons from the December storm

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lessons from the December storm Board MeetingJanuary 26, 2011

  2. 4 Storm chronology – major storm affecting entire region

  3. 4 Successfully managing storms has 4 phases 1 • Track storm forecasts • Continuously assess storm impact and response required • Update and disseminate alert levels • Formulate plan for operation and recovery Storm tracking and readiness 2 Mobilization • Pre-position equipment • Call in staff • Activate situation rooms, as required • Issue customer advisories 3 Execution • Fight snow/ice/water • Endeavor to maintain service while being mindful of customer/employee safety and impacts on equipment • Be prepared to switch from service delivery to curtailment/suspension strategy • Care for stranded customers and employees • Provide up-to-date service information 4 • Restore normal service • Provide up-to-date service information • Assure storm equipment is ready for next storm Recovery Effective coordination with OEM’s and other external agencies required throughout

  4. 4 MNR successfully adapted to quickly changing conditions but had some issues with delayed and disabled trains and restoring service Positives Issues 1 Storm tracking and readiness • Early meeting of Emergency Management Task Force 2 Mobilization • Situation room activated early • Equipment and employee pre-deployment 3 Execution • Rapid observation-based decision to suspend service reduced duration of service outage and recovery time • Detailed and consistent messages delivered through all channels • Delayed and disabled trains in the Bronx and Westchester 4 Recovery • Imbalance of service supply and rider demand on Tuesday left some customers waiting on platforms • Negative effects on New Haven Line fleet availability • Advance creation and deployment of recovery service plans • Successful execution of recovery service plans in the face of rapidly changing conditions

  5. 4 LIRR’s pro-active suspension of service and early mobilization avoided stuck trains but some communication and recovery issues Positives Issues 1 Storm tracking and readiness • Level 4 (highest level) staffing activated on Dec 24 even though storm at Level 1 due to forecast volatility 2 Mobilization • Situation room activated early • Clear pre-storm communications regarding potential service interruption • Employee availability not optimal 3 Execution • Pro-active suspension of service avoided stuck trains • ‘Comfort trains’ successfully deployed • Clear and timely communications • Only limited service available • Inability to keep Jamaica switches functioning 4 Recovery • Only limited service available Tuesday • Platform communication systems crashed • Did not clearly communicate train times for limited service operated during recovery period (on platforms in particular) • Effective staged restoration of service

  6. 4 Subways’ inability to quickly adapt to deteriorating conditions led to stuck trains and under-estimation of stranded customer issues Positives Issues 1 Storm tracking and readiness • Frequent planning conference calls to monitor changing storm forecasts • Internal alert level not formally upgraded until storm well underway 2 • Several aspects of Plan IV activated – underground train storage; deployment of storm fighting equipment system-wide • No formal implementation of Plan IV • Situation room not activated Mobilization 3 • Large portion of network delivered un-interrupted service • Clear and consistent communications • Inadequate central coordination of field actions • Not curtailing/suspending service led to stuck trains, stranded customers and slow recovery • No robust plan to care for customers on stuck trains • Insufficient number of experienced managers on duty Execution 4 • Prioritized recovery strategy • Clear and consistent communications Recovery • Not understanding implications of providing full service before and during storm

  7. 4 Buses’/Paratransit’s not quickly curtailing service led to large numbers of stuck vehicles. Monday service updates were untimely. Positives Issues 1 Storm tracking and readiness • Highest internal alert level not activated 2 Mobilization • Pre-storm mobilization of personnel and snow-fighting equipment • Night and articulated buses equipped with chains as planned • Situation room not activated 3 Execution • Poor coordination with non-MTA transport modes left some riders stranded • Not curtailing/suspending service led to increased numbers of stuck vehicles, stranded customers and slow recovery • Insufficient route-level detail in service interruption communications • Held back some service that could not be operated effectively 4 Recovery • Route-specific service detail eventually communicated • Bus radio system crashed

  8. 4 Bridges and Tunnels performed well Positives Issues 1 Storm tracking and readiness • Storm alerts issued and updated as forecast deteriorated 2 • Significant mobilization of staff despite holiday beginning early December 25 Mobilization 3 • No service interruptions • Successful sharing of equipment with Buses • GPS tracking of snow-fighting vehicles Execution 4 Recovery • Quickly assessed and assured serviceability of snow-fighting equipment immediately after storm

  9. 4 Learning and applying the lessons of the December storm • Immediate actions taken • Application to recent storms • In-depth review

  10. 4 Actions have already been taken to address the identified issues Actions completed since December storm 1 Storm tracking and readiness • MTA HQ disseminating incoming weather notifications across agencies • MTA HQ coordinating regular inter-agency calls to compare forecast information and approach and communications strategy 2 Mobilization • Situation rooms / incident command centers resourced and ready at operating and support agencies • Subways created a blizzard response ‘Plan V’ that includes specific service curtailment/suspension actions in response to high winds and high rates of snow accumulation • Pro-active cancellation of non-essential paratransit trips 3 Execution • Customer advocate role at all agencies • Coordinated effort by bus road operations and depot staff to assess service conditions route-by-route during storm and aftermath • Updated list of priority bus routes to be operated during curtailed service • Buses updated guidelines for applying chains and replacing articulated buses with standard-length buses to improve service resilience • Internal coordination procedures in place to provide route-specific bus service information through website 4 • LIRR developing limited service schedules for publication in advance • MNR established procedure to quickly add service (where possible) in response to customer demand during recovery period Recovery

  11. Actions were proven during recent storms • Incident centers activated at Bridges & Tunnels, Long Island Rail Road, Metro-North Railroad, NYC Transit and MTA Bus before the first snow fell • Near normal service for Subways and LIRR • Planned modifications to MNR service • No trains stuck for any significant period of time • No buses or paratransit vehicles stuck for any significant period of time • Full coordination with NYC OEM and regional OEM offices • Jan 7 – minor storm • Jan 11/12 – moderate storm in NYC; significant in MNR service area • Jan 21 – moderate storm

  12. 4 An in-depth review to be completed during the second quarter will identify additional actions that could improve response to all storms • Cross-agency effort led by MTA COO • Identify issues and solutions including: • Best practices in other systems around the world that contend with snow regularly • Review agencies’ internal assessments • Equipment and infrastructure vulnerabilities • Practices and rules that may inhibit effective storm mobilization or response • Equipment and technology that would make MTA agency response to storms more effective • Training and simulations that better prepare staff for infrequent events • Follow-up by Internal Audit to review relevant recommendations from previous storm reports and confirm implementation of agency-initiated actions • Generalizing from December snowstorm lessons to other weather-related events