Outsourcing of Solid Waste Management Services in Six Cities. LAHORE WASTE MANAGEMENT COMPANY. Sequence. Contract Details Procurement procedure Design Financial Model Bid Opening Performance Monitoring Institutional Arrangements Timeline Risks of project. A- Contract Details

Download Presentation

Outsourcing of Solid Waste Management Services in Six Cities

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Outsourcing of Solid Waste Management Services in Six Cities LAHORE WASTE MANAGEMENT COMPANY

  2. Sequence • Contract Details • Procurement procedure • Design • Financial Model • Bid Opening • Performance Monitoring • Institutional Arrangements • Timeline • Risks of project

  3. A- Contract Details (Procurement, Design and Financial modeling)

  4. A(1)- Procurement Procedure

  5. Prequalification of firms • RFP( International) advertised on 22nd July 2013 • Submission Date was 22 August , 2013. • Pre-qualification Criteria • Business experience and certification (25 marks) • Personnel capabilities (20 marks) • Equipment & machinery (30 marks) • Financial capability (25 marks) • Total Qualifying Marks = 60% • Criteria encourage local contractors for bidding, the marks were allocated proportionate to capabilities

  6. Firms Pre –Qualified • For small cities ( Sialkot, Bahawalpur) • For large cities ( Faisalabad, Gujranwala, Rawalpindi, Multan)

  7. Components of the Bid Documents • Instruction to Bidders • General Conditions of the contract • Technical Specifications

  8. Cont’d... • Bid Security The amount of Bid Security for Large city (Multan, Faisalabad, Rawalpindi & Gujranwala) Local Rs 100 Million International USD 1 Million The amount of Bid Security for Small city (Bahawalpur & Sialkot) Local Rs 50 Million International USD 0.5 Million • Performance security 5% of Contract Price in form of Bank Guarantee for 7 Years.

  9. Cont’d... • Mobilization advance • 10% of the contract value in two equal installments • Mobilization advance is secured against Bank Guarantee • Recovery of mobilization advance in 24 installments within 36 months

  10. Approval of Bid documents • Bid Documents & cost estimates were approved by the Govt of the Punjab in the meeting held on 30th Sep 2013 under the Chairmanship of Chief Secretary of the Punjab • The BODs of six cities also approved the bid Documents • The bid documents were issued to prequalified bidders

  11. Details of issuance of bid documents

  12. Submission of Financial Bids • Bids were opened on October 08, 2013 • Bid opening ceremony was attended by all districts and bidders .

  13. Results of Financial Bids • Bids were examined and found responsive. Detailed attached

  14. A(2)- Project Design

  15. Waste Generation Statistics

  16. Scope of New SWM contract • Manual sweeping in streets • Vacuum sweeping on major roads • Mechanized Washing • Door-to Door Waste Collection • Container based Waste Collection • Transportation of MSW to the Disposal Site

  17. Design Parameters

  18. Cont’d…

  19. Location of proposed landfill site (Faisalabad)

  20. Location of proposed landfill site (Gujranwala)

  21. Location of proposed landfill site (Rawalpindi)

  22. Location of proposed landfill site (Multan)

  23. Location of proposed landfill site (Sialkot)

  24. Location of proposed landfill site (Bahawalpur)

  25. Phases Implementation

  26. Vehicles & Machinery Requirements • The contractor shall supply the vehicles and equipment required for the contract as per given Phases and timelines

  27. Vehicle and Machinery (Faisalabad)

  28. Vehicle and Machinery (Gujranwala)

  29. Vehicle and Machinery (Rawalpindi)

  30. Vehicle and Machinery (Multan)

  31. Vehicle and Machinery (Sialkot)

  32. Vehicle and Machinery (Bahawalpur)

  33. Man power requirement Details

  34. A(3)- Financial Modeling

  35. Financial Modeling • Main Features

  36. Summary of Unit Rates

  37. Total Cost & Mobilization Advance

  38. Long Term Cost 2013-to-2021 Amount in PKR in million

  39. Immediate Cost 2013-14 (Mar-June) Amount in PKR in million

  40. Factors Affecting Cost • Haulage from proposed Sanitary Landfill Site / Dumpsite • Haulage from proposed Waste Transfer Station • Haulage from Garage to the operational site • Proximity of the workshops, parking areas and water hydrants from city • Expenditures on residual functions

  41. B- Performance Monitoring

  42. Key Performance Indicators (KPIs) KPIs have been defined and made part of the bidding document for measuring performance of the contractors. KPIs have been linked with resolution time and penalties KPIs • Penalties The amount of penalty to be imposed during one month shall not, in any case, exceed 10 % of the monthly progress payment. (Details of Penalties)

  43. Service Delivery Indicators

  44. Cont’d…

  45. C- Institutional Arrangements

  46. Key Milestones • Formation of companies and Board of Directors Status – Completed • Services and Assets Management Agreement (SAAMA) Status – Submitted to Law Department • Identification of landfill site and improvement of existing dumpsites – Status – Identified • Hiring of key Staff Status – In progress

  47. Residual Functions of WMC • Construction of access road at waste disposal site; • Establishment of weighbridge; • Procurement of hardware for monitoring tools such as Vehicle Trip Counting System, Vehicle Tracking and Monitoring System, Android Based Monitoring, Complaint Management System, RFID System etc.

  48. Cont’d… • Development of software for monitoring of contractors; • Provision of land for development of Waste Transfer Stations; • Establishment of Water Hydrants • Hiring of machinery for managing waste disposal site

  49. Residual Functions Local Govt • Monitoring of performance of the WMC against agreed KPIs in SAAMA; • Enactment and Enforcement of relevant laws; • De-silting of roadside waste water open drains; and • Levying of charges and fees