120 likes | 135 Views
This report provides an overview of current and upcoming construction projects in school facilities, including progress updates, start and completion dates, and key milestones for V.R. Eaton High School, Peterson E.S., and Beck E.S. additions.
E N D
FACILITIES, PLANNING, AND CONSTRUCTION JANUARY 30, 2014 CONSTRUCTION REPORT
Area Currently Under Construction/ Planning Facilities under Construction: V.R. Eaton High School 540,000 SF __________ Total 540,000 SF Facilities in Planning/Bidding Stage: Peterson E.S. Addition 14,000 SF Beck E.S. Addition 8,000 SF ____________ Total 22,000 SF Total Projects under Construction, Planning and Bidding: 562,000 SF
V. R. Eaton High School Architect: Corgan Associates Contractor: Pogue Construction Company Const. Start Date: Spring 2013 Completion Date: August 2015 Status: • Pier drilling is complete • Geothermal wells are being drilled • Grade beams are 45% complete • Foundation pours are underway • Rough electrical and plumbing is being installed • Site grading and utility installation is underway • Steel erection will begin in March
May 2013 January 2014
Peterson Elementary School Addition Architect: SHW Architects Contractor: Northstar Builders Const. Start Date: Spring 2014 Completion Date: August 2014 Status: • Design Complete • GMP submitted for School Board approval • Construction begin in February
Beck Elementary School Addition Architect: SHW Architects Contractor: Balfour Beatty Construction Const. Start Date: Spring 2014 Completion Date: August 2014 Status: • Design Complete • GMP will be submitted for School Board approval in February • Construction begin in March
SECO Energy Grant • OLC- Wind Turbine and Solar Array Operational • Central Campus- Wind Turbine and Solar Array Operational
FACILITIES, PLANNING, AND CONSTRUCTION JANUARY 30, 2014 CONSTRUCTION REPORT