170 likes | 200 Views
Stay informed about the latest construction progress on V.R. Eaton High School Outdoor Learning Center, Steele HVAC and Roof Renovation, and other facilities projects. Get insights into planning, bidding, and completion dates.
E N D
Facilities, Planning, and Construction November 16, 2015 – Monthly Construction Report Report
Area Currently Under Construction/ Planning Facilities Under Construction: V.R. Eaton High School Outdoor Learning Center Facilities in Planning/Bidding Stage: Transportation Complex Steele HVAC and Roof Renovation
Remaining Work at Eaton High School • Landscape • Weather Pending • Pond C is the last area to be finished (behind baseball and softball fields) • 3rd Floor Academic Wing • Finish up this area
Outdoor Learning Center Architect: Stantec Architects Contractor: Northstar Builders Const. Start Date: February 2015 Completion Date: August 2016 Status: • Piers Completed: • 100% completed excluding the Overlook B • Geo wells 100% completed • Large Pavilion Moisture Conditioning is 75% Complete (12’) • Anticipation wall grade beams are poured • Septic Demo is 80% Complete
Transportation Complex Contractor: Const. Start Date: January 2015 Completion Date: June 2015 Program: • Central Bus Complex Update: • Advertising begins November 17th • Presented Contractor with cost in December • Durham School Services, L.P. agrees to contribute $745,000 to the Paving Project
Steele HVAC and Roof Replacement Engineer: MetCo Roof Consultant: Amtech Const. Start Date: June 2016 Completion Date: August 2016 Status: • Working with consultants on design • Method of Delivery to the Board in December • Drawings to be completed at the beginning of 2016 • Bid out project beginning of 2016
Facilities, Planning, and Construction November 16, 2015 – Monthly Construction Report Report