ctcLink Project Update - November 7, 2018

This update provides information on the ctcLink project, including updates on the program status, remediation efforts, and deployment groups. It also includes a summary of other project activities as of October 26, 2018.

pearlw
Download Presentation

ctcLink Project Update - November 7, 2018

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ctcLink Project UpdatectcLink Executive Leadership Committee November 7, 2018 Choi Halladay - District Vice President for Administrative Services Pierce College, ctcLink SC Chair Christy Campbell – SBCTC ctcLink Project Director

  2. Agenda

  3. Ctclink Minutes – October 23, 2018 • Approval

  4. Ctclink program status • Remediation • Deployment Group 2 • Deployment Group 3

  5. Remediation Summary

  6. Other ctcLink Project Activities – Status as of October 26, 2018

  7. G R LEGEND: On track Some issues, under control Significant issues, not under control Y LEGEND: Critical High Moderate Low H C M L LEGEND: High Medium Low H M L

  8. Deployment Group 3 – DG3 • Completed DG3 Pre-Kick-Off – Nov. 2, 2018 • Begin bi-weekly DG3 meetings – Nov. 7, 2018 • Begin Peer Review meetings for readiness – TBD • College requested Pre-Kick Off meetings (Dec. 2018) • College Leadership Discussion • College ctcLink Project Team • College Individual Kick-Off meetings (Jan. 2019) • DG3 Kick-Off – Jan. 28, 2019

  9. Deployment Group 3: Gate 1 Initiation Phase Progress – as of October 26, 2018 Legend NR:Not Received, deliverable not posted to cDR IP:In Progress, draft deliverable has been posted to cDR C:Complete, final deliverable posted to cDR

  10. Staffing update Employee - Open Roles • 1 Student Financials Analyst - Posted • 2 Finance Analysts - Posted • 1 Applications Configuration Management – Posted • 1 Student Financials Analyst - Posted • 1 Communications/OCM Shared Role - Interviewing

  11. Ctclink Governance Update

  12. Recent PM/OCM Events Project & Organizational Change Management (PM/OCM Training • Project Management Training – 23 College and ctcLink PM participants • Organizational Change Management Training – 27 College and ctcLink PM/OCM participants Project Manager (PM) Summit • 26 College PM/OCM participated in person • 4 College PM/OCM participated remotely • High Level Discussions • Schedule and Status Reporting • Quality Management • Organizational Change Management / College Roles & Alignment • Life After Go-Live • Conversion/Data Validation • End User Training • User Acceptance Testing • Security Redesign

  13. Questions?

  14. Remediation Open – Finance

  15. Remediation Open – Finance, cont’d

  16. Remediation Open – Human Resources

  17. Remediation Open – Campus Solutions

  18. Remediation Open – Campus Solutions, cont’d

More Related