Van Far R-I School District April 3, 2012 Bond Issue

Van Far R-I School District April 3, 2012 Bond Issue. WE ARE. Proposition A $ 1,400,000.00 NO-TAX-INCREASE GENERAL OBLIGATION BOND ISSUE APRIL 3, 2012 ELECTION. What improvements will be made to the school buildings?

petra
Download Presentation

Van Far R-I School District April 3, 2012 Bond Issue

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Van Far R-I School DistrictApril 3, 2012 Bond Issue WE ARE

  2. Proposition A $1,400,000.00 NO-TAX-INCREASE GENERAL OBLIGATION BOND ISSUE APRIL 3, 2012 ELECTION

  3. What improvements will be made to the school buildings? Our main goal of this bond issue is to address the critical needs of our aging buildings. Those high priority improvements are as follows: The roof on the elementary building has outlasted its life expectancy with many leaks. The proposed new roof will add insulation to the structure preventing moisture from entering the interior of the building in the future. The boiler system in the junior high and high school needs to be replaced with a new energy efficient, high capacity system. The exterior walls of both buildings are in need of repair and brick replacement. Tuck pointing, brick replacement, foundation repair and sealing the surface of the walls is necessary to keep moisture out of the building. One can easily see these deficiencies by walking around either building; especially the high school.

  4. High School Boiler Replacements • Current Conditions: • Boilers nearing end of useful life • More efficient technology available • Pumps-hard to find parts • Scope: • Replace with 4 more efficient boilers • Load analysis to be done • Replace pumps • Move hot water heater

  5. Elementary Roof Replacement • Current Conditions: • Past useful life • Leaking into interior spaces • Water between membrane • and decking • Visible punctures/tears to • surface • Loose patches • Scope: • New white membrane roof • 2” insulation • Wall Panel additions

  6. Tuckpointing at High School & Elementary • Current Conditions: • Deteriorating building exterior • Scope: • Waterproof all masonry • Patch all bad brick • Caulk all window sills • Cut out and recaulk expansion joints • Repair foundation corners • Downspout on front of high school relocated

  7. Informational Public Meetings March 12 at 4:30 at the Farber Library March 19 at 6:00 p.m. at the Lange Building in Vandalia March 26 at 6:00 p.m. at the Van-Far High School Cafeteria