1 / 11

WCF 1-6 Alternatives For Compliance With The NC Lawsuit Orders

WCF 1-6 Alternatives For Compliance With The NC Lawsuit Orders. Prepared by: Bill McCollum Presented to: FSRA. Date: 3/11/09. Agenda. Issue Description Alternatives Considered Key Assumptions Cost Evaluation Changes from 2008 Global Insights. Issue Description. Issue Description:

Download Presentation

WCF 1-6 Alternatives For Compliance With The NC Lawsuit Orders

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WCF 1-6 Alternatives For Compliance With The NC Lawsuit Orders Prepared by: Bill McCollum Presented to: FSRA Date: 3/11/09

  2. Agenda Issue Description Alternatives Considered Key Assumptions Cost Evaluation Changes from 2008 Global Insights

  3. Issue Description Issue Description: • Prior to the NC lawsuit ruling, the Clean Air Plan did not include scrubbers or SCRs for WCF 1-6. • SO2 emissions are ~1.0 lb/MM Btu with low sulfur fuel. • NOx emissions are ~0.45 lb/MM Btu. • Compliance with an expected mercury MACT rule by 2015 would be achieved with low emitting Colorado coal. • The NC lawsuit ordered scrubbers and SCRs to be installed and operated by Jan 2014 and imposed annual emissions rate and tonnage caps for each unit beginning in 2014: • SO2: 0.15 lb/MM BTU, ~618 tons per unit per year • NOx: 0.06 lb/MM Btu, ~263 tons per unit per year • WCF 7-8 also have Court-ordered SO2 and NOx rate and tonnage caps but already have scrubbers and SCRs installed.

  4. WCF 1-6 Clean Air Capital Costs • The 2008 LRFP did not include scrubber and SCR costs for WCF 1-6. • The Base Study Case for this evaluation include scrubber and SCR capital cost. • The cost estimate to comply with the NC lawsuit order for WCF 1-6 is estimated to be $909 MM.

  5. Alternatives Considered Coal-Fired Alternatives With Emissions Controls • Install scrubbers and SCRs at WCF 1-6 (Base Study Case). • URS/Washington Group has prepared conceptual arrangements and cost estimates for scrubber and SCR installation Gas-Fired Alternatives • Retire WCF 1-6 by Jan 2014. Replace capacity with combined cycle at the WCF site by Jan 2014 (WCF On-Site). • Retire WCF 1-6 by Jan 2014. Replace capacity with technology and timing as determined by capacity expansion model (WCF CapEx).

  6. Assumptions For All Alternatives • The Court-ordered compliance date is Dec. 31, 2013. • The Feb 2009, 90% Confidence Hydro Gen Plan. For the Base Study Case • Scrubbers and SCRs are installed by Jan 2014. (The typical scrubber schedule is 60 months. April 2008-Jan 2014 is less than 60 months.) • Wet scrubber technology is installed. • A two-scrubber module arrangement is installed. • This alternative would also comply with expected mercury emissions limitations. For Gas-Fired Alternatives • WCF CapEx • Replacement capacity construction present no schedule problems. • Transmission upgrades would be required to compensate for the loss of capacity in the WCF area. • WCF On-Site • CC construction by Jan 2014 presents no schedule problems. • Permitting and NEPA review present no schedule problems. • Gas pipeline upgrades and firm gas transportation would be required. • Gas pipeline upgrades present no schedule problems.

  7. Assumptions, cont’d Cost Assumptions • Present value calculations use 8% discount rate. • The URS/Washington Group cost estimate (completed 2/20/09) for WCF 1-6 scrubber and SCRs is $909 MM ($1066/KW nameplate rating). • The CC replacement capacity for WCF B cost is $803 MM ($996/KW) in as-spent $. • Other costs considered in the evaluation: • Transmission system upgrade costs (WCF CapEx). Ten year completion schedule. $87 MM • Firm gas transportation (WCF On-site). Costs are based on a 25-year contract. $65 MM per year • Gas price at WCF 1-6 starting at $8.75/MM Btu in 2014 and escalating to $13.27/MM Btu by 2028.

  8. WCF1-6 Summary of Present Values of Cost(Differences in Cost) • Conclusions: • WCF1-6 base case has higher cost than and WCF CapEx (replace off-site as needed). • Without cooling towers in the base case, the costs are similar. Highlights: • System variable costs – High system cost difference because WCF1-6 (with controls) generation is replaced with higher cost gas-fired generation. In addition, gas prices rise faster in the future than coal prices. • Transmission Upgrades – If WCF1-6 is retired and not replaced on-site, TVA must perform substantial transmission system upgrades. • Clean air costs – WCF base case has costs for controls (scrubbers, SCRs). WCF1-6 controls are more expensive than other plants because of less economies-of scale (smaller units). Note: Lower cost is better

  9. Changes from 2008 • Impacts from North Carolina Ruling • Revised Forecasts for Natural Gas and Coal Prices • Impacts Due to Current Economic Situation • Reductions in revenue due to decreased demand • Increased expenditures caused by market impact on investments (e.g. Nuclear Decommissioning Fund, Retirement System) • Capacity expansion delayed due to decreased demand • Kingston ash spill recovery costs • Different Environmental Agenda • More emphasis on CO2 reductions and use of renewables • Regulatory outlook on mercury and other emissions • More Information about Plant Generation Alternatives and Fuel Supply • Increased State Oversight • System pond regulation / permitting • Clean Air Plan • Mercury • Revised cost estimates • North Carolina lawsuit

  10. Global Implications - WCF • North Carolina Lawsuit Ruling • If we shut down Widows Creek Units 1-6 and let system reoptimize, the lost energy is replaced by gas fired generation. • NOx and SO2 emissions will decrease slightly but not significantly with the gas option. However CO2 emissions due show a distinct drop. • Cashflow – Near Term vs Long Term • Gas option capital and firm gas costs may roughly balance controls fixed O&M and capital costs. • Assumptions of gas cost combined with its volatility drive the cost advantage / disadvantage for the gas options. • Transmission • The required transmission upgrades if WCF 1-6 are shutdown are much less expensive than the new transmission line required for a JSF shutdown • These transmission upgrades will likely be needed within the planning horizon anyway. • Environmental Implications - How does TVA want to be perceived • Adding controls and continuing to operate WCF 1-6 doesn’t promote a “green” perception. • Retiring and replacing WCF 1-6 with a natural gas-fired plant may be more acceptable to the “green” stakeholders.

  11. Other Global Implications • Trend to Renewables and DSM • If 1400 MW of DSM currently in planning assumptions doesn’t show up, coal and gas fleet generation will increase • Renewables up to 2000 MW may be purchased, but resulting energy into the system is small, ~13% capacity factor of wind and ~38% of solar • Fuel Portfolio • With one or more coal plants shut down, TVA’s fuel portfolio will shift toward more natural gas consumption • CO2 Legislation • Could be a cap on annual emissions with no allocation • Redispatching fleet may not be sufficient, may have to cap coal fleet capacity factors to comply • Completion of Planned Nuclear Units • Higher coal fleet capacity factors if a delay in nuclear unit completion

More Related