1 / 30

Tracker Integration Activities at CERN: TIB/TID Preparation and Installation

Detailed summary of the preparation, installation, and testing activities for the TIB/TID subdetectors at CERN, including control rings check, module handling, cable connections, and cooling system tests.

Download Presentation

Tracker Integration Activities at CERN: TIB/TID Preparation and Installation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Stato Tracciatore All subdetectors in the TST TEC- • Attività integrazione: • TIB/TID + @CERN • TIB/TID- @CERN • TOB • TEC • Test TIB/TID+ @TIF • Slice test TIB/TOB • preparazione installazione • pianificazione • manpower 21-Mar-07

  2. TIB/TID+ - Activity at Cern (A.Venturi R. Dell’Orso L. De Maria) Reception test: check all control rings, no modules loss. Medusa cables routing Ribbon map ; Ribbon connection to optical margherita Preparation of grounding and shielding, slice test, survey.

  3. TIB/TID

  4. TIB/TID+ slice test 30% of TIB+ and 50% of TID+, 22 Control rings out of 60, 642 modules, 424K strips 88 power groups for modules (LV, HV), 88 (LIC+CAB) cables 22 Control Power groups, 22 (PLCC+CTRL) cables Operation at 350V,DCS (HW+SW) ,13 outputs from cooling manifold (fluid @15 0C) 44 Pt1000 sensors readout by TSS + Interlock Z=0 view M. Meschini, L. De Maria Side view

  5. Noise: Table of Results

  6. TIB/TID+ - coupling test and Pixel Tube ins. (F. Raffaelli, F. Palmonari, T. Lomtadze) 5-8 DEC ‘06 scope of the test: Make trial insertion of TIB+ and TIB- layers and Pixel Tube outside the TST. Preparatory work: Survey of the z=0 side for TIB+ and TIB- Layers adjustment with pillars , Survey repeated after intervention.

  7. TIB/TID+ insertion Raffaelli, Basti, Lomatdze Palmonari Insertion cradle inside TST TIB/TID+ on the Antti chariot In position 20-DEC-06

  8. Cu pipes initially tested at 18 bar (air); then cleaned with C6F14 installed and tested at 12 bar Hepressure (leak detector in air with sensitivity of ~5 10-6mbar l/s) Optical Fibers grouped and placed on the Al panels CAB60 Al cables connected to Margherita and placed on the Al panels Slice test control rings checked 40% of the remaining control ring to be checked MTCC chiller working (after intervention of the producing company) Characterisation of each cooling loop with C6F14 (T=200C)done, (pressure drop vs flow curves). Results consistent with the measurements in Pisa. TIB/TID+ activity after insertion (L. De Maria, V. Radicci, F. Palmonari)

  9. TIB/TID+ 6-FEB-07 sealing

  10. TIB/TID- insertion Ready 29-01-07 In position 01-02-07

  11. Pixel Tube insertion 8-Feb-07

  12. Tracker slice test (25%) TOB: 14% TIB:37% TEC:25% TEC TOB TIB

  13. TIB+TOB+ sync TIB+NoisePeak-On(not normalized)pedestal noise 20-Feb-07 TIB+ alone TIB+TOB+ async

  14. TOB Integration Last ROD insertion 688 RODS 6 layers First rod inserted: March 3rd Last rod inserted: November 3rd

  15. Noise Performance Layer 1 Layer 2 Layer 3 Layer 4 Layer 5 Layer 6

  16. TEC+ The Aachen Team with TEC + End Cover Removed to show Silicon

  17. TEC+ installation 28-Feb-07

  18. TIB/TID- before TEC- installation 20-March-07

  19. TK slice test data Cosmic rays data taking started on March 9. 4 week-ends at ~200K events/week-end. Now in the slice test also TEC+

  20. Access events (cosmic/pedestal) from Storage Manager in streaming mode The Web Interface accessed from (CERN, Fermilab, Pisa, Lyon....) Online DQM

  21. Summary plots are generated from individual detector level histograms...... Summary Plot Number of Digis in TOB

  22. Cosmic track seen in TIB and TOB layers IGUANA Event Display

  23. Looking at the level of Cluster

  24. superato il 50% della produzione sia per il fwd che per il barrel In fase di completamento il primo dei quattro half-cylinder Il rivelatore (FPIX) per lo engineering run spedito al CERN alla fine di Gennaio :Funziona! Allestito il lab (PIC) , con la necessaria strument. e il chiller I test sono gia’ in svolgimento con una prima versione (rudimentale) di DAQ Pixels

  25. Il primo mezzo disco in costruzione

  26. Installazione prevista in Ottobre ‘07. Rivelatore finale al Cern entro Ottobre. I pixel per lo engineering run in fase di test al PIC del CERN

  27. CMS Tracking System Up-date - February 07 CMS has set-up a Specific Project to Manage the Installation of Services onto YB0 to ensure the Tracker is installed on Schedule. Monday 16 July

  28. YB0 Services Installation Up-date - February 07 TK cables TK fibers Unp TK Move TK Conn TK Pack Tk for move

  29. Per il rispetto della schedule di integrazione e’ stato determinante l’impegno INFN al Cern a partire dall’estate ‘06. La presenza di persone in Dicembre è stata sostenuta grazie agli aiuti delle sezioni. Le tabelle preparate per le richieste ‘07 sono realistiche per la parte di integrazione, sottostimate per il lavoro di software commissioning. Il progetto YB0 messo inpiedi da CMS per permettere l’installazione e operazione del Tracker prima della fine del 2007 richiede pero’ il contributo di ulteriore manpower rispetto a quello previsto. Come mostrato nelle tabelle precedenti l’inserimento di ulteriori ~8 FTE per I prossimi 6-8 mesi risulta determinante. Cio’ rappresenta ~30% del personale aggiuntivo necessario. Il resto e’ fornito dalle altre agenzie. La richiesta è quindi di ~ 60 mu (240 KCHF). Richiesta manpower

  30. Per il completamento del Tracker, oltre ai finanziamenti avuti con la seconda tranche di extracosti, e’ necessario acquistare da Caen: 22 moduli di alimentazione di controllo A4602, necessari dopo la finalizzazione del rack layout 2 mainframe, senza display, SY1527 richiesta 70 K€ Richiesta CORE

More Related