440 likes | 525 Views
PMS is the host of Washington state’s first full-size Community Solar Project. Even Jay Leno heard about it. . The North Kitsap Herald made it into Leno’s weekly “Headlines” segment. Installation began in early January with the mounting system.
E N D
PMS is the host of Washingtonstate’sfirst full-size Community Solar Project.
The North Kitsap Herald made it into Leno’s weekly “Headlines” segment.
Installation began in early January with the mounting system.
The mounting system provides underlying support for the modules.
Each community solar project is custom-designed to fit its host facility.
Next is the racking system, which holds the modules in place.
Once the racking was fabricated off-site, it took only two days to install.
Wiring comes after the mounting and racking systems are in place.
The modules have to be manufactured in-state to receive the full state incentives.
390 modules were delivered in two separate loads two weeks apart.
Distributing the weight puts less stress on the underlying roof structure.
The state requires that modules be installed by certified electricians.
A team of two electricians can install about 60 modules a day.
The “racking feet” provide a strong anchor for high winds, etc.
Silicon Energy modules have a unique self-contained wiring system.
Air circulation gaps increase efficiency by reducing surface temperature.
Entire system installation took about 13 weeks (including inverters).
Inverters convert the solar-generated DC to AC grid-tie-compatible electricity.
The project was designed by Hans Frederickson of Frederickson Electric.
State inspection was passed on March 10th. The PSE production meter was installed on March 15th.
The system started generating energy and incentives at 11:59 a.m., March 15, 2011.