NIRANTHARA JYOTHI SCHEME • Niranthara Jyothi Project is a prestigious scheme of Government of Karnataka, to provide 24 hrs 3 phase power supply to non-agricultural loads like domestic, commercial, water supply, street light, rural industries, milk dairies etc., in rural areas by segregating the agricultural loads, which is a boon to the rural economy. • Objectives : • This will enable BESCOM to give 24X7 supply to Non-Agricultural loads in Rural areas • Reduction in transformer failure • Increase in metered sales • Reduction in technical losses • Improved load management The plan of implementation and progress is shown separately. NIRANTHARA JYOTHI SCHEME:
STAGES OF IMPLEMENTATION • Phase I • 25 Lots, 261 feeders, 19 taluks. • Project cost :Rs 355.85 cr. • Expected completion : Dec-2013. • Phase II • 24 lots, 289 feeders, 23 taluks. • Project cost :Rs 385.71 cr. • Work Award issued for 6 Lots(86 feeders), • DWA issued in Nov 2011, Jan-2012 & works are under progress. • Work Award issued for 10 Lots (96 feeders) , • DWA issued in Oct, Nov 2012 & Works are under progress. • For the 5 Lots (57 feeders), LOI is issued , DWA issued in May 2013 Work under Progress • For the 2 Lot ( 34 feeders), LOI is issued , DWA issued in June 2013 Work under Progress • For the 1 Lot ( 14 feeders),DWA issued in Oct-2013 Work under Progress. • Note: Out of Proposed 289 feeders,287 feeders work executed by PTK and 2 feeders are to be executed by Departmentally.
BANGALORE ELECTRICITY SUPPLY COMPANY LIMITED Physical Progress of Phase-I
BANGALORE ELECTRICITY SUPPLY COMPANY LIMITED Physical Progress of Phase-II