320 likes | 331 Views
This presentation outlines the demand forecast, resource assessment, and transmission assessment for IMO's latest 18-Month Outlook. It compares inputs, presents results, and provides insights into the market rules and methodology used. The Outlook covers October 2003 - March 2005 and is available on the IMO website.
E N D
18-Month OutlookOctober 2003 - March 2005 Presented byGreg Hine IMO Long-Term Forecasts and Assessments
Presentation Outline • Introduction • Demand forecast • Resource assessment • Transmission assessment Inputs Comparisons Results
Separate Presentations • This presentation focuses on specific Outlook inputs, comparisons with previous Outlooks and results • Another presentation focuses on the market rules, market manuals and the methodology to complete demand forecast, resource assessment and transmission assessment
Introduction • IMO’s latest 18-Month Outlook covers October 2003 - March 2005 • published September 24, 2003 @ www.theIMO.com • four documents on IMO web-site: • 18-Month Outlook (main document) • 18-Month Demand Forecast • Outlook Methodology • Ontario Transmission System • spreadsheet tables
Demand Forecast • actual load, weather , economic data through to the end of June 2003 • impact of new data captures the latest relative sensitivity and relationships between load and weather • Forecast of economic variables as of July 2003
Variable Impact on Daily Peak Demand • Temperature >16 C +1C +380 MW • Temperature <10C -1C +110 MW • Wind Summer -1km/h +10 MW • Wind Winter +1km/h +10 MW • Christmas Day -4700 MW • Monday vs. Sunday +2000 MW
Data Impact on Model • System increasingly sensitive to high temperatures • but rate of increase is slowing • System continues to be less sensitive to low temperatures • but rate of decrease is slowing • Level of economic activity is having a smaller impact on demand • due to shifting demand to off-peak times • growth non-energy intensive sector of the economy • Applies to both peak and energy demand
Economic Outlook • Outlook for the Ontario economy positive but lower than the forecast in the previous 18-Month Outlook • World economic climate • Sluggish U.S. recovery • Economic data mixed • Risk to the forecast is mostly on the “downside”
Existing Resources: Total * Bruce “A” units not included
New Generation Projects (in Outlook period and currently under construction) • No additional Pickering A units are scheduled to be returned to service during the Outlook period.
Existing Resource Scenario all existing resources one Pickering-A unit is included no new generation project additions 0 MW of price sensitive demand Planned Resource Scenario all existing resourcesone Pickering-A unit is included new generation project additions 300 MW of price sensitive demand Resource Scenarios
Polling Question • On average what level of resources do you expect will materialize over the next 18 months? • (a) less than assumed under ERS • (b) about the same as assumed under ERS • (c ) more than ERS, but less than PRS • (d) about the same as assumed under PRS • (e) more than assumed under PRS
Available and Required ResourcesExisting Resource Scenario Ontario Market Demand (Normal Weather)
Available and Required ResourcesPlanned Resource Scenario Ontario Market Demand (Normal Weather)
Reserve Margins: Planned Resource Scenario Ontario Market Demand (Normal Weather)
Reserve Margins: Existing Resource Scenario andPlanned Resource Scenario Ontario Market Demand (Normal Weather)
Reserve Margins: Extreme Weather Existing Resource Scenario andPlanned Resource Scenario Ontario Market Demand (Normal Weather) Extreme weather is not expected every week
Sources of Risk • Demand uncertainty (RR) • Forced outage rate of resources (RR) • New generation projects coming into service (ERS, PRS) • Return of generators from planned outage (ERS, PRS, +) • Hydroelectric resource utilization (RR,+) • Extreme weather impact (separate scenarios,+)
Transmission • Some outages impact internal and inter-tie limits (appendix C of main document) • Windsor, Toronto and Thunder Bay reactive supply