1 / 8

Review of Trade and Transfer Winter 09/10

Review of Trade and Transfer Winter 09/10. Transmission Workstream 6 May 2010. Agenda. Overview Trade &Transfer for Oct 09 - Mar 10 Update on release of non obligated Oct 09 - Mar 10. Transfer and Trades Oct 09 to Mar 10.

rahim-mays
Download Presentation

Review of Trade and Transfer Winter 09/10

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Review of Trade and Transfer Winter 09/10 Transmission Workstream 6 May 2010

  2. Agenda • Overview Trade &Transfer for Oct 09 - Mar 10 • Update on release of non obligated Oct 09 - Mar 10

  3. Transfer and Trades Oct 09 to Mar 10 • All capacity requests satisfied in stage 1 (i.e by using capacity at the same ASEP) either by : • Unsold NTS Entry Capacity (remaining Unsold from QSEC and AMSEC auctions) • Surrendered NTS Entry Capacity (i.e. entry capacity made available by Shippers) • Surrendered capacity allocated for at least one month at • Bacton, Theddlethorpe, Easington, St Fergus • More unsold remaining for daily auctions • Stage 1 resulted in there being no unsatisfied bids. No Stage 2 required (i.e Transfer and Trade between ASEPs)

  4. ASEPs where capacity was offered for surrender

  5. ASEPs where capacity offered for surrender was allocated - Therefore, more unsold remained for daily auctions at these ASEPs

  6. Totals for period October 09 to Mar 10 (GWh)

  7. Pre - October 2009 (GWh)

  8. Non obligated October 2009 to March 2010 Currently 3 mechanisms for releasing non obligated entry capacity • QSEC • Allocations at Isle of Grain • WDDSEC • Allocations at Hornsea, Avonmouth, Easington, Glenmavis, Partington, St Fergus • DRSEC • July 2009 – National Grid NTS received a request to initiate a DRSEC Auction • National Grid NTS indicated, via letter to the Industry, 70 GWh available across 6 ASEPs for Oct 09 to Mar 10. • 26GWh was allocated at Isle of Grain in October, November, December, January, February, March.

More Related