260 likes | 344 Views
BNL - FNAL - LBNL - SLAC. Model Quadrupoles DOE Review of the LHC Accelerator Research Program July 13-14, 2009 Gian Luca Sabbi. Presentation Outline. 90 mm aperture Model Quadrupoles (TQ): Design Features Progress since the last DOE review Next steps
E N D
BNL - FNAL - LBNL - SLAC Model Quadrupoles DOE Review of the LHC Accelerator Research Program July 13-14, 2009 Gian Luca Sabbi
Presentation Outline • 90 mm aperture Model Quadrupoles (TQ): • Design Features • Progress since the last DOE review • Next steps • 120 mm aperture Model Quadrupoles (HQ): • R&D Goals • Coil and Structure Design • Status of the HQ01 model fabrication • Work plan through FY10
LARP Technology Quadrupole (TQ) • Double-layer, shell-type coil • 90 mm aperture, 1 m length • Two support structures: • - TQS (shell based) • - TQC (collar based) • Target gradient200 T/m TQC TQS Winding & curing (FNAL - all coils) Reaction & potting (LBNL - all coils)
TQ Status at the 2008 DOE Review • Two coil/model series using different wire design • 30 coils fabricated, distributed production line • 11 tests performed (FNAL, LBNL and CERN) • Surpassed 200 T/m with 10% margin (TQS02a/c) • All training quenches >200 T/m in TQS02c/d TQ01 OST-MJR 54/61 TQ02 OST-RRP 54/61 61 Results of TQS02c test (CERN) • Issues: • Variability in the coil production process • Localized degradation, not systematic • Best results achieved by coil selection • Best results are still ~8% below SSL • For TQS02 models: • Best results were obtained at 4.4 K • Quenchlevels at 1.9K were 5-10% lower SSL 1.9K SSL 4.4K
TQS02c Characterization at 1.9K Additional tests performed at CERN in September 2008: 200 T/m • Interpretation: conductor instability at 1.9K, enhanced by local degradation: • Limiting quenches in the same coil & location (c23 ramp) at 4.5K and 1.9K • 1.9K stability limit in magnet is lower (half) than expected from strand data
TQ Tests with OST-RRP 108/127 Strand Goal: verify conductor performance in a well defined magnet environment • TQM03 Model (FNAL core program) • Magnetic mirror for testing of single coils • Mechanical support through bolted shell • One virgin coil was recently tested: • 1.9 K quench levels are well above 4.5 K • Corresponds to expected margin increase • TQS03 Model (LARP + FNAL / LBNL core programs and CERN) • Full quadrupole coil in shell-based structure • Same preload as in previous TQS models • Four virgin coils, under testing at CERN: • Confirm expected improvement 4.5K to 1.9K • Verify reproducibility over a set of four coils
Next Phase: 120 mm Quadrupoles • IR Studies show large aperture quads are required for L=1035 cm-2 sec-1 • Phase 1 (L=2 1034 cm-2sec-1) will use NbTi Quads with 120 mm aperture • The same aperture was chosen for the next series of Nb3Sn models (HQ) • Full qualification based on Phase 1 luminosity requirements • Providing performance reference for Phase 2 upgrade design Aiming at:
HQ Progress since the 2008 DOE Review 2008 June Presented conceptual designs for 114 and 134 mm bore July Selection of 120 mm quadrupole aperture for Phase 1 Aug. Practice cables fabricated, test windings completed Aug. Cable and coil cross-section geometry finalized Sep. Winding and curing tooling in procurement Nov. 3D magnetic and coil design completed 2009 Jan. Mechanical analysis completed, shell in procurement Feb. Coil parts, reaction/potting tooling in procurement Mar. All structure components in procurement Apr. Two cable UL fabricated (modified 54/61) June (Practice) coil 1 winding/curing completed June Reaction and potting tooling received June Three cable ULs fabricated (modified 54/61) July Coil 1 reaction and coil 2 winding completed Design and fabrication timeline is comparable to NbTi technology
HQ Task Distribution by Laboratory • Cable design and fabrication LBNL • Magnetic design FNAL & LBNL • Mechanical design LBNL • Coil parts design and procurement FNAL • Quench protection and heaters LBNL • Winding and curing tooling design LBNL & FNAL • Reaction and potting tooling design BNL • Instrumentation traces LBNL • Coil winding and curing LBNL • Coil reaction and potting BNL & LBNL • Coil handling and shipping tooling BNL • Structure fabrication and test LBNL • Magnet assembly LBNL • Magnet test FNAL
HQ Design Features and Parameters • Coil peak field of 15.1 T at 219 T/m (1.9K un-degraded SSL: 19.5 kA) • 190 MPa coil stress at SSL (150 MPa if preloaded for 180 T/m) • Stress minimization is primary goal at all design steps (from x-section) • Coil and yoke designed for small geometric and saturation harmonics • Full alignment during coil fabrication, magnet assembly and powering
Coil and Cable Design Coil parameters: • 120 mm aperture, 2 layer • One wedge in each layer • 46 turns/quadrant Cable parameters: • 35 strands, 0.8 mm diam. • Width: 15.15 mm • Mid-thickness: 1.44 mm • Keystone angle: 0.750 Cable insulation: • Glass sleeve, 0.1 mm thick Sub-element deformation Edge facets Test windings
120 T/m Magnetic Design and Field Quality • Reference radius 40 mm (2/3 aperture) • Small geometric harmonics (2 wedges) • Saturation b6 ± 1 unit from 0 to 20 kA • Optimized for 120 T/m gradient • End design optimized for minimum field • No additional spacers in the ends
Mechanical Design • Main structural components: • Aluminum shell: 25 mm thick, OD = 570 mm (same as LHC dipole) • 4-split iron yoke • Iron pads provide space for axial rods and cooling channels • Iron masters house 50 mm wide bladders, loading and alignment keys • Aluminum collars align poles while transferring pre-load to the coils
Mechanical Analysis • Pre-loading for 219 T/m • Pole contact pressure: • 140 MPa compression at 0 T/m • 20 MPa max. tension at 219 T/m • Axial forces: • E.m. force: 1372 kN • 620 kN applied at 4.2 K • Mid-plane stress: • 193 MPa at 219 T/m 193 MPa @ 219 T/m
Heaters and Instrumentation Traces Each layer has two independent heaters , voltage taps, z/q strain gauges Layer 2 heater parameters: Layer 1 heater parameters: - 10.79 mm wide - 2.166 m long strip per side - Rstrip 300 K = 5.7 ohms - Rstrip 4.2 K = 3.9 ohms - Istrip = 67 A => 75 W/cm2 at 4.2 K - 15.5 mm wide - 2.158 m long strip per side - Rstrip 300 K = 3.95 ohms - Rstrip 4.2 K = 2.7 ohms - Istrip = 93 A => 75 W/cm2 at 4.2 K Layer 2 VT05 VT10 VT03 VT09 VT06 VT08 VT07 VT04
Coil and Structure Alignment • Alignment is controlled at all steps • Coil Fabrication: • Winding: mandrel to layer 1 to layer 2 • Alignment keys in curing cavity • Alignment pins for reaction / potting • Structure pre-assembly: • Pins between shell and yoke • Aluminum collars and pole keys • Assembly and pre-loading: • Master keys maintain alignment • Cool-down and excitation: • Pole keys remain in compression
Progress on Coil Fabrication Layer 1 Winding Layer 1 Curing Layer 2 Winding
Progress on Coil Fabrication (2/2) Reaction tooling Preparations for coil transfer Practice coil 1 in reaction tooling
Practice Coil 1 Reaction • Step 3 temperature is increased from 640C in TQ to 665C in HQ • 15 T critical current is about half of 12 T different trade-offs
Practice Coil Experience • In progress: • Improve fitting of outer layer parts • Revised length/angle of flexing cuts • Modifications for heaters, splices • To be addressed: • Step between layers after curing • Axial gaps during winding • End shoe holders during reaction Coil-spacer fit Flexing cuts Instrument. wire reliefs Nb3Sn-NbTi splice shims Layer 1-2 step after curing
HQ Budget in FY09 and FY10 HQ cabling (Materials R&D): +25k$ for one additional run (108/127) Some adjustments under discussion for FY09-Q4 to optimize schedule Complete HQ01; HQ01b retest (replacing 1-2 coils); start HQ02 coils Testing of single coils in the mirror structure is also being considered
HQ Optimization toward 2-meter scale-up • HQ01 models will establish baseline performance: • Mechanical support, quench training • Conductor performance, stress degradation • Quench protection and instrumentation • Field quality • In the meantime, Phase 1 requirements will be better defined • Parallel studies to understand implications for Nb3Sn magnets • HQ02 models will address key areas needing improvement • Field quality (geometric, saturation, magnetization) • Mechanical structure, alignment • Cooling, radiation hardness • HQ optimization results will provide a basis for the 2-m models (QA)
Summary • TQ Model Quadrupoles: • Surpassed 200 T/m performance target with 10-15% margin • Provided technology basis for Long Quadrupoles (LQ) • Further optimization and conductor studies are in progress • HQ Model Quadrupoles: • Significant increases in field, force and stress levels • Harness the full potential of Nb3Sn for the LHC upgrade • Key step forward toward an accelerator quality design • Phase 1 specifications will guide further optimization • Optimized HQ will provide technology basis for 2-m QA