Illiamna R. Bridge replacement on Williamsport to Pile Bay Road

Illiamna R. Bridge replacement on Williamsport to Pile Bay Road. Washed out bridge, Chinkelyes Creek Williamsport-Pile Bay Road (Replaced by Bailey Bridge in 2002). Williamsport to Pile Bay. Homer. Illiamna Region. Immediate needs on Williamsport to Pile Bay.

Download Presentation

Illiamna R. Bridge replacement on Williamsport to Pile Bay Road

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Illiamna R. Bridge replacement on Williamsport to Pile Bay Road Washed out bridge, Chinkelyes Creek Williamsport-Pile Bay Road (Replaced by Bailey Bridge in 2002)

  2. Williamsport to Pile Bay Homer Illiamna Region

  3. Immediate needs on Williamsport to Pile Bay • Replace Illiamna River bridge, single-lane truss • Weight limits on bridge • Width and height limits on bridge • Other immediate work • Rock cuts on pass that limit width of loads.

  4. Williamsport to Pile Bay Road • State-owned, state-supported maintenance • Pioneer road standard, 15.5 miles length • US Army COE and state analysis show significant demand for vessel and freight movement • Primary purpose: move freight and fuel, not general traffic

  5. Iliamna River Four Mile Creek Timberline Creek Chinkelyes Creek

  6. Williamsport to Pile Bay Road Benefits • Allows gillnetters to transport vessels • Provides Illiamna Lake communities with access and connectivity back to Homer • Strong support for road • Kenai Peninsula, Homer, Lake and Peninsula Borough, Alaska Miner’s Association • Significant freight movement benefits. • Alternative to Kvichak R. low water problems

  7. Bridges repaired in 2000 Four Mile Creek Timberline Creek

  8. Bridge upgrade in 2002 Chinkelyes Creek Joint project: Alaska DOT and US Navy SeabeesEstimated cost $200,000 + contributed labor

  9. Chinkelyes Ck. Bailey Double-Double HS-20constructed Summer 2002 by DOT&PF and US Navy

  10. Other considerations • Route has two other limitations: • Marine access is higher-tide limited, 3-4 days per month • Lake access is ice-limited • DOT&PF cost-benefit analysis found >$3M annual freight delivery savings despite these limitations • Wilder Construction plans on dredging the marine side in 2003, adding available tidal days to above

  11. Budget • Replace bridge on Illiamna R. including new sheet pile abutments $0.75M • Optional: Selective rock cut on mountain pass to widen key locations: $0.75M