1 / 15

AD and AD experimental areas: equipment tests and startup with beam Tommy Eriksson AB/OP/AD

AD and AD experimental areas: equipment tests and startup with beam Tommy Eriksson AB/OP/AD. AD and AD experimental areas: equipment tests and startup with beam. Planning Equipment tests HW status News for the 2006 run Beam requirements ccc Conclusion. 2006 Run planning.

Download Presentation

AD and AD experimental areas: equipment tests and startup with beam Tommy Eriksson AB/OP/AD

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AD and AD experimental areas: equipment tests and startup with beamTommy Eriksson AB/OP/AD AD equipment tests and startup with beam

  2. AD and AD experimental areas: equipment tests and startup with beam • Planning • Equipment tests • HW status • News for the 2006 run • Beam requirements • ccc • Conclusion AD equipment tests and startup with beam

  3. 2006 Run planning • Short run with only 3 months of physics. • AD run extended to cover weekends. • 2650 hours total (2040 physics) are scheduled, to be compared with 3400 in 2004. • OP/AD-LEIR section will cover either AD or LEIR operation, including LEIR commissioning. • AD: ops crew = 5 specialists on-call Mon 07:00 – Mon 07:00 24h/24. Shiftwork on AD during startups and md:s. AD equipment tests and startup with beam

  4. Shutdown work/startup planning AD equipment tests and startup with beam

  5. Equipment tests • Key dates: • 24/4: search + closure of AD ring and Target Area • AD Hall remains in free access unless major problems • Target area in controlled access (special access procedure) • Controlled access to AD ring if needed • 24/4 – 14/5: HW tests + cold checkout • 15/5: startup w. production beam • No critical days AD equipment tests and startup with beam

  6. HW status: e-cooler AD equipment tests and startup with beam

  7. HW status: e-cooler AD equipment tests and startup with beam

  8. Electron cooler/Vacuum: • Replacement of / add missing NEG:s • Repair of orbit pickups • Replacement of cathode • Alignment • Improvement of orbit correctors 2904/2917: Study completed, but no budget to go further AD equipment tests and startup with beam

  9. Electron cooler/Vacuum • Install non-magnetic support for VVS3105 • Install vacuum chamber in place of K35 • Repair of BIPM sect 42 • Isolate 8000-line • Modify VVS in ej. line AD equipment tests and startup with beam

  10. News for 2006 • ACE (AD-4) has requested 500 MeV/c pbars for cell irradiation. • Approval by SPSC in Jan. 06 ?? • This implies significant changes to the AD cycle: • Tests of SW during eq.tests • Use of some of the planned md-periods during the year for further tests • Final setting-up followed by physics to be done at end of 2006 run to avoid disturbing the other users; 160 hours in total requested (setup + physics). • If unexpected problems, ACE can go back to 300 MeV/c operation on short notice AD equipment tests and startup with beam

  11. News for 2006 AD equipment tests and startup with beam

  12. News for 2006 • Tests of ATRAP:s new 3T solenoid in 2004 revealed that no beam can be transferred to ATHENA due to the stray field • A new H dipole will be installed to compensate (DE0.DHZ87) • Tests during startup AD equipment tests and startup with beam

  13. Beam requirements • 26 GeV/c beam needed as from 15/5 • No use of 3.57 GeV/c protons is planned, BUT: • In case of serious problems, we might have to resort to proton operation with AD in reverse polarity; 3.5 GeV/c tst beam should be available on fairly short notice AD equipment tests and startup with beam

  14. Operation from ccc • Start-ups and md:s will continue to be carried out from the ACR • As far as tools/diagnostics, no major problems can expected for ccc operation; CCC=MCR as seen from the AD • The required AD modifications for efficient operation from the ccc were: • Improve stability with improved steering dipoles for pbar/e-beam alignment • Replace MWPC:s by non-destructive BPM:s in the ejection lines • None of the requested modifications were carried out – many trips to/from ACR, more downtime and delays can be expected AD equipment tests and startup with beam

  15. Conclusion • Main worries for the 2006 startup: • 18 months stop • Electron cooler behaviour after complete dismantling • No adaptation for ccc-operation AD equipment tests and startup with beam

More Related