1 / 27

Senior Thesis

Eric Yanovich. Senior Thesis. E ric Y anovich. Structural Option. S tructural O ption. S chaumburg H otel and. Hotel and Convention Center. C onvention C enter. Schaumburg. S chaumburg, I llinois. P resentation O utline. B ackground p roject I nformation

reid
Download Presentation

Senior Thesis

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Eric Yanovich Senior Thesis Eric Yanovich Structural Option Structural Option Schaumburg Hotel and Hotel and Convention Center Convention Center Schaumburg Schaumburg, Illinois

  2. Presentation Outline • Background project Information • Existing structural System • Design Goals • Proposal and Solution Overview • Construction Impacts and Considerations • Overall Conclusions and Recommendations Omission of Presentation • Lighting Breadth (Typical guestsuite)

  3. Project Information General Information • 1551 Thoreau DriveSchaumburg, Illinois • 17 Story Hotelwith 500 guest suites covering over 436,000 SF • Project Total =$207 MillionHotel Structure =$99 Million • 5 Story Atrium, Restaurant, and 4 Star Accommodations • Design Partners • Architects: John Portmanand Assoc. & Daniel P. Coffey and Assoc. • Structural Engineer: Halvorson Partners Eric Yanovich Background Project Information

  4. Building Location Eric Yanovich Background Project Information

  5. Building Site Eric Yanovich Background Project Information

  6. Design Codes • International Code Council • 2003 International Building Code • 2003 International Fire Code • American Instituteof Steel Construction • 3rd Edition Manual of Steel Construction (LRFD) • American Societyof Civil Engineers • Minimal Design LoadsFor Buildings (ASCE 7-02) • American Concrete Institute • Building Code Requirementsfor Structural Concrete (ACI 318-02) Eric Yanovich Existing Structural System

  7. Existing Structural System • Cast-in-place Concrete Columnsand Beams • 10” Post-tensioned Concrete Flat Plate Slab • Circular(42” dia) Concrete Columnsin Atrium Space • Shear wallsfor lateral Force Resistance • 9’8” Typical Story Height Circular Atrium Columns Shear Walls Eric Yanovich Existing Structural System

  8. Lateral System • 11”-18” Thick Shear Walls • 6-8ksi Concrete • 9 walls creating 3C-Shaped Elements Eric Yanovich Existing Structural System

  9. Design Goals Conversion of the Concrete Frameto Steel Considerations and Project Scope • Removalof a rowof columns • Time/Cost savings • Replacement of post-tensioned slab system with composite slab • Analysis of Braced Frame Performance Eric Yanovich Design Goals

  10. Design Goals Conversion of the Concrete Frameto Steel Advantages • Additional Column-Free Space • Time savingsin erection • Less Specialized Construction Concerns • Lateral System Compatibility • Lateral System Performance • Increased Story Height (17”) Eric Yanovich Design Goals

  11. Structural Proposal Conversion of the Concrete Frameto Steel • Note Frame Layout Eric Yanovich Proposal and Solution Overview

  12. Structural Proposal Gravity System • Typical Beam Sizes Range from W12x311 to W24x55when part of the braced frames Please See Appendix B of the Final Report for Complete Beam/Girder Sizes Eric Yanovich Proposal and Solution Overview

  13. Structural Proposal Lateral System • Typical Column Sizes Range from W14x311 at the base to W14x90 on upper levels • Brace Member Average in Size to W12x45 for most of the frames* *Please see Appendix B for per member sizes Eric Yanovich Proposal and Solution Overview

  14. Structural Proposal Concerns of system Changes • Typical Window Sizes Located in the Corridor Eric Yanovich Proposal and Solution Overview

  15. Structural Proposal Proposal Summary • Deflections Including the Original Shear-wall System were well outside the L/480per story drift Limit • The Braced Fames reduce the overall drift to 5.1”resulting in a per story drift of L/470 • The Original System had a deflection equalto 4.4” (L/510) Eric Yanovich Proposal and Solution Overview

  16. Construction Impacts • What is the Economical Impact? Eric Yanovich Construction Breadth

  17. Construction Impacts • What is the Scheduling Impact? • Consideringthe on-site construction times to be the same, each project’s timelinecan be seen below Eric Yanovich Construction Breadth

  18. Final conclusions & Recommendations • Comparable Drift of the Proposed structure Vs. the current design • More Layout Flexibility • Cost Savings of Almost 16% • Schedule time saving of 10 weeks Personal Recommendation: Proposed Steel Structure with Braced Frames Eric Yanovich Final Conclusions and Recommendations

  19. Questions / Answers Eric Yanovich Questions and Answers

  20. Lighting Breadth • Whatdoes this structure frame? Eric Yanovich Over-Time

  21. Lighting Breadth • Whatdoes this structure frame? Eric Yanovich Over-Time

  22. Lighting Breadth Eric Yanovich Over-Time

  23. Construction Impacts Eric Yanovich Construction Breadth - Over-Time

  24. Construction Impacts Eric Yanovich Construction Breadth - Over-Time

  25. Construction Impacts Eric Yanovich Construction Breadth - Over-Time

More Related