110 likes | 229 Views
Generation Use of System Charges. Nigel Turvey. Background. Regulatory incentive allows: Recovery of a percentage of any reinforcement costs A value per kW of generation connected An allowance for the O&M costs on the sole use and reinforcement assets
E N D
Generation Use of System Charges Nigel Turvey
Background • Regulatory incentive allows: • Recovery of a percentage of any reinforcement costs • A value per kW of generation connected • An allowance for the O&M costs on the sole use and reinforcement assets • The incentive applies to generation connected post April 2005 or to incremental additions to existing generators made post April 2005 • This results in a positive allowed revenue from generation
Existing Position • For generators connected at EHV: • LRIC methodology applies • which can result in positive or negative charges • Continue to be cost reflective and do not need further amendment • For generators connected at HV/LV: • Charges calculated from yardsticks which have characteristics derived from demand data • Originally set using cost data used in the last price control settlement • Concerns raised whether this approach is cost reflective and whether there are benefits not being reflected in the charges • For microgeneration: • Charges set to zero • At existing low level of activity neither costs nor benefits have been identified and zero charge continue to be appropriate
Proposed method for HV/LV generator charges - principles • Generation tends to be widely dispersed • Unlikely that benefits (or cost not recovered in connection charges) will be seen at voltage of connection • Some benefit likely at higher voltage levels due to the impact of multiple higher load factor generators • For consistency with security standards, benefits will not be applied to intermittent generation • Yardstick constructed including: • negative coincidences at voltage levels above the voltage of connection (for high load factor generators) • zero coincidence at the voltage level of connection • Positive service connection costs
Proposed method for HV/LV generator charges - scaling • Proposed method will result in negative export yardsticks whilst allowed revenue is positive • Whilst scaling to a positive allowed income will reduce the pricing signals it will reflect a recovery of other costs not in DRM yardsticks • Scaling by a £/kW adder will be required • Scaling to required revenue will result in low load factor generators (generally renewable) having higher UoS charges than at present • The only way to prevent this would be to recover some allowed generation revenue from demand – this would require Ofgem’s agreement
Proposed method for HV/LV generator charges – resulting charges
Proposed method for HV/LV generator charges - timetable • Draft modification report prepared • Expecting to issue a WPD consultation to get users views shortly • Modification request to Ofgem June/July • Implementation April 09