What we need

Partial Disassembly of the alignment devices on each ME11transfer plate, ME1/1 chamber and ME1/2 chamber. (6 on +Z and 6 on –Z side of the CMS). What we need. Cherry picker with free access to ALL of the IP side of YE±1 This means both far and near sides

Download Presentation

What we need

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Partial Disassembly of the alignment deviceson each ME11transfer plate, ME1/1 chamberand ME1/2 chamber.(6 on +Z and 6 on –Z side of the CMS)

  2. What we need • Cherry picker with free access to ALL of the IP side of YE±1 • This means both far and near sides • About 2h35’ per point (6 points per endcap) • About 5h20’ for just one point (see ahead)

  3. MAB LEGEND: ASPD 2D Sensor DISTANCEMETER Z DISTANCEMETER R LASER AR LASER LD LASER MAB COLLIMATOR / LASER SOURCE ME/1/3 BARREL YE/1 ME/1/2 Magnet Coil TP HB YN1 EB YN1 ME/1/1 RP HE EE TK LP LB LD AR

  4. Location of link sensors on ME±1/(1,2) DCOPS In ME1/3 8 14 2 20 32 26

  5. The *only* ME±1/2 CSCs that need to be removed in YE±1 are • ME+1/2/11 • ME+1/2/10 and ME+1/2/12 must also come off • ME+1/2/15 • ME+1/2/14 and ME+1/2/16 must also come off • Link has sensors on ME+1/2/14 • Apart from this, ONLY ME11 parts from link alignment need to be removed • In the following, the steps in blue are needed only at this particular point

  6. Disassembly Steps by point. • Access with the cherry picker to the position, 20’. • Open the cover of the ME11transfer plate Patch Panel, four M4 slotted countersunk (flat) head screws, 10’. • Unplug two Radial ASPDs cables, and one Radial proximity cables, 15’. • Open two covers of the ME11 transfer plate, five M4 slotted countersunk (flat) head screws each, 10’. (Open only one covers for the ME11 operation, 5’) • Unplug Z and RPhi proximity sensor cables and temperature sensor cables of the transfer plate, 20’. • Unplug of thetwo ME1/2 ASPDs cables, and un-routing cables onthe ME1/2. 25’. • Disassembly ME1/2 chamberASPDs. Two M6 slottedscrews and twopins. 20’. • Disassembly ME11 Z and RPhi proximity sensor and temperature piece of the transfer plate, have two allen M5 screws + two pins holes, 20’. • Unplug R proximity sensor cable of the ME1/1 chamber device, 10’. • Disassembly ME11 chamber device, have two allen M6 screws + two pins holes, 25’. • Disassembly the radial piece, of the +ME11 transfer plate, have two allen M5 screws + two pins holes. Back access too much complicate due to a lot of cables/tubes running around. 1h30’. • Closethecovers of the ME11 transfer plate and thePatch Panel and sealingallremainingdevicesonthisarea. 35’ (Only for the ME11 operation, 30’) • Descendwiththecherrypicker. 10’ • Total 5h20’ per point (only one such point in LS1) • For just ME11 stuff: 2h35’ (6 such points per endcap)

  7. Open the cover of the ME11transfer plate PP, four M4 slotted countersunk (flat) head screws, 10’.

  8. Open two covers of the +ME11 transfer plate, five M4 slotted countersunk (flat) head screws each, 10’.

  9. Disassembly ME1/2 chamber ASPDs. Two M6 slotted screws and two pins. 20’.

  10. Disassembly ME11 Z and RPhi proximity sensor and temperature piece of the transfer plate, have two allen M5 screws + two pins holes, 20’.

  11. Disassembly ME11 chamber device, have two allen M6 screws + two pins holes, 25’.

  12. Disassembly the radial piece, of the +ME11 transfer plate, have two allen M5 screws + two pins holes, 1h30’.

  13. The accessibility to the back side of the ME11transfer plate it is not easy…

  14. Assembly Steps • Access with the cherry picker to the position, 20’. • Open the covers of the ME11 transfer plate and the Patch Panel and the sealing. Five M4 slotted countersunk (flat) head screws each, 15’. • Assembly the radial piece, of the ME11 transfer plate, have two allen M5 screws + two pins holes, . Back access too much complicate due to a lot of cables/tubes running around. 2h15’. • Assembly ME1/1 chamber device, have two allen M6 screws + two pins holes, 35’. • Plug R proximity sensor cable of the ME1/1 chamber device, 15’. • Assembly ME1/1 Z and RPhi proximity sensor and temperature piece of the transfer plate, have two allen M5 screws + two pins holes, 25’. • Plug Z and RPhi proximity sensor cables and temperature sensor cables of the transfer plate, 25’. • Assembly ME1/2 chamber ASPDs. Two M6 slotted screws and two pins. 30’. • Plug the two ME1/2 ASPDs cables, and re-routing cables on the ME1/2. 35’. • Close two covers of the ME11 transfer plate, five M4 slotted countersunk (flat) head screws each,15’. • Plug two Radial ASPDs cables, and one Radial proximity cable, 20’. • Close the cover of the +ME11transfer plate PP, four M4 slotted countersunk (flat) head screws, 15’. • Sealing all devices on this area until the start of the next LHC running. 25’ • Descend with the cherry picker. 10’ • Total 7H00’