DFW Connector Project Main Street Bridge Starting in March 2010 Subject to Change. PHASE 1A. The project consists of 7 total phases 1a thru 3b Phase 1a Begins on the east end of the project early 2010, west end begins mid 2010 Phase duration approximately 550 days
E N D
DFW Connector ProjectMain Street BridgeStarting in March 2010Subject to Change
PHASE 1A • The project consists of 7 total phases 1a thru 3b • Phase 1a • Begins on the east end of the project early 2010, west end begins mid 2010 • Phase duration approximately 550 days • Many stages within phase 1a • Major areas of work include: • West end: FM 1709 – SH 26 • TX 121 SB & NB widenings • Managed lanes: Texan Trail – International Pkwy • North east frontage roads • Main Street bridge
Main Street Bridge • Work commences March 2010 with asbestos abatement • NORTHGATE COLOR SCHEME for following maps: • BLUE = DETOUR CNST • YELLOW = CURRENT CNST • ORANGE = PREVIOUS CNST
DFW Connector Traffic Management • Goals of MOT team • Maintain mobility • Cooperation with stakeholders • Safe construction zone • Emergency / incident management • Contacts • Emergency assist • Location (mile) markers • Emergency pullouts • Courtesy patrol