1 / 29

Integration of Renewables

Integration of Renewables. ….Catalyst for change. Power Grid Corporation of India Ltd. Presentation Flow. Overview Renewable Integration Transmission Challenges & Technologies Way Forward. Overview. Indian Power Scenario. Total Installed Capacity – 304.7 GW. Peak Demand met: 148 GW.

richards
Download Presentation

Integration of Renewables

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Integration of Renewables ….Catalyst for change Power Grid Corporation of India Ltd

  2. Presentation Flow • Overview • Renewable Integration • Transmission Challenges & Technologies • Way Forward

  3. Overview

  4. Indian Power Scenario Total Installed Capacity – 304.7 GW Peak Demand met: 148 GW Renewable: 44.2 GW Type Wise Capacity As on 31-07-2016 Source: Perspective Transmission Plan for 2022-36 Annual Consumption 1100 BU Power Market 9-10%

  5. Indian Power System : Transmission Indian Power System : Transmission • 765 kV Backbone Network: • 25,647 ckm • 147000 MVA • HVDC (±500kV, ±800 kV) • 12938 ckm • 15000 MW • 400 kV : • 150021 ckm • 216282 MVA • Inter-regional Capacity: 61150 MW

  6. High Capacity Transmission Corridors

  7. National Grid – Present and Envisaged NR NER SR Present IR Capacity: 61,150 MW Existing Planned IR Capacity by XII Plan end: 78,050 MW Envisaged (Cumulative) by Mar’17 6,000 MW 22,530MW 16,920MW 2,860MW 19,530MW 12,920MW 2,860MW 12,790 MW ER WR 16,990 MW 7,920 MW 3,630MW 7,920 MW 7,830MW Present & Targeted IR Capacity include Pvt. Sector lines also • Figures do not include 600MW (in aggregate) pertaining to various 132kV

  8. Renewable Integration

  9. Renewable Addition Plan RE Penetration

  10. Renewable Integration - Challenges • Issues • Short Gestation period (9-12 months) • Variability & Intermittency • Low Utilisation Factor

  11. Initiatives

  12. Green Energy Corridors

  13. Green Energy Corridor-I Green Energy Corridors-Inter State Transmission • Green energy corridor to facilitate Grid integration of large scale renewables • About 33GW capacity addition envisaged through wind & solar in next 4-5 years • The Plan includes • Transmission Strengthening(s) –Intra & Inter • Dynamic reactive compensation • Energy Storage • Smart grid applications • Establishment of Renewable Energy Management Centre enabling forecasting of renewable generation, real time monitoring, etc. ​

  14. Envisaged Solar Parks Locations of Solar parks Total-20 GW

  15. 400 kV Pooling Substation, Anantpur (AP)

  16. Enabling Framework for Renewable Integration

  17. Transmission Challenges and Technologies

  18. Challenges & Measures

  19. 1200 kV National Test Station, Bina

  20. 800 kV HVDC 765 kV D/C

  21. WIDE AREA MEASUREMENT

  22. WAMS • PHASE I • Installation of 1186 PMUs along with 32 PDCs at control centers • 416 Nos. PMUs already installed • Development of Analytics etc. • PHASE II • Installation 550 PMUs, 11000 km OPGW along with associated terminal equipment etc.

  23. URTDSM System Hierarchy Remote Consoles at CEA (1) PDC at NLDC PDC at Back up NLDC Remote Consoles at RPC (5), UT(3), States(5) Super PDCs at five RLDCs Master PDCs at SLDCs PMUs located at State Sector Substations PMUs located at IPPs across the Grid PMUs located at Central Sector Substations Router Router Router PMU- n PMU- n PMU- n PMU -1 PMU -1 PMU -1

  24. PMU Installations

  25. Battery Energy Storage System (Pilot Project)

  26. POWERGRID’s Pilot Project for Battery Energy Storage System Applications Frequency Regulation, Energy Time Shift

  27. Investment Envisaged

  28. Way Forward

  29. THANK YOU

More Related