250 likes | 261 Views
Congregational survey results and recommendations for church building improvements, including accessibility to bathrooms, worship space, fellowship space, and class rooms.
E N D
St. Luke Lutheran Church Building Task Force Presentation
Congregational SurveyNeeds/Recommendations for church building improvements Bathroom(s) Accessibility (To bathrooms/Fellowship Area/ Basement) Worship Space (size/layout) Fellowship Space (Size/Location) Class Rooms (Quantity/Size)
Our Current Building Specifications • 4,451 sq/ft- main level • 3,740 sq/ft -lower level. • Seating Capacity- 160 • Limited permanent parking + street parking • Multiple levels with only stair access
Church Planning & Liturgical Architecture Celebrating 65 Years of Architectural Excellence St. Luke Lutheran Church - Townhall Presentation
2016.02.06 E x i s t i n g P l a n s M A I N L E V E L B A S E M E N T St. Luke Lutheran Church - Townhall Presentation 2017.04.23
2016.02.06 E x i s t i n g B u i l d i n g M A I N L E V E L B A S E M E N T St. Luke Lutheran Church - Townhall Presentation 2017.04.23
2016.02.06 V I R T U A L M O D E L E x i s t i n g B u i l d i n g view from northwest view from southeast view from southwest St. Luke Lutheran Church - Townhall Presentation 2017.04.23
2017.02.20 S c h e m e ‘ D . 2 ’ preferred option M A I N L E V E L B A S E M E N T St. Luke Lutheran Church - Townhall Presentation 2017.04.23
Addition Remodel S c h e m e ‘ D . 2 ’ preferred option 2017.02.20 Addition Remodel M A I N L E V E L St. Luke Lutheran Church - Townhall Presentation 2017.04.23
Addition Remodel Schemes ‘D.1’ & ‘D.2’ preferred option Remodel 2017.02.20 Addition B A S E M E N T St. Luke Lutheran Church - Townhall Presentation 2017.04.23
2017.02.20 S c h e m e ‘D . 2’ COST PROJECTIONS (by SMSQ) ________ Scheme ‘D.2’ ________ $192,280 1.Link addition (2 floors) $796,600 2.North Wing addition $70,000 3.Restrooms @ Gathering $234,040 4.Worship space remodeling 5.East entry addition $36,120 $107,650 6.Basement remodeling $215,500 7.Contingency (15%) $75,000 8.Kitchen equipment allowance Projected Cost (Scheme ‘D.2’): $1,727,190 St. Luke Lutheran Church - Townhall Presentation 2017.04.23
Addition Remodel S c h e m e ‘ D . 1 ’ explored options 2017.02.20 M A I N L E V E L Addition Remodel St. Luke Lutheran Church - Townhall Presentation 2017.04.23
2017.02.20 V I R T U A L M O D E L ( a d d i t i o n i n y e l l o w ) S c h e m e ‘ D . 1 ’ view from southwest view from northwest view from northeast view from southeast St. Luke Lutheran Church - Townhall Presentation 2017.04.23
THANK YOU for this opportunity to present our Work! St. Luke Lutheran Church - Townhall Presentation 2017.04.23
Back to Task Force Presentation
Riverwood Community Church • Located in Cannon Falls on 15 acres • Steel butler building with modern style front • 12,000sq.ft. (103ft x 128ft) • Seating for 250 in main sanctuary. • Est $110 to 120 per sq/ft to build (land and parking excluded)(Est $1.5M)
Parking Lot Cost example • 2 acre lot (87,120 square feet)(140 car capacity) • 6’ of 3” screened as a base and 2” of Cl 5 road rock over that for an initial total of 8” = $21,888 initial approximate cost for rock • Other costs: • Purchase of Land • Land Preparation • Asphalt
How will we be the people of God in this place? • How does this building hinder ministry? • How will changes to the building allow ministry to grow? • Are we a place that has room for anyone and everyone? • Or are we a place that wants to stay just as we are?