1 / 34

Energy-Efficient Fitness Center Design in Houston, TX - 2006 Thesis Outline

Explore a senior thesis outlining the design parameters, air and hot water alternatives, and recommendations for a sustainable fitness facility in Houston, TX, completed in 2005.

rigsby
Download Presentation

Energy-Efficient Fitness Center Design in Houston, TX - 2006 Thesis Outline

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LA Fitness, West Oaks Houston, Texas David Melfi Mechanical Option The Pennsylvania State University Department of Architectural Engineering Senior Thesis Spring 2006

  2. Presentation Outline • Building Description • Goals & Metrics • Design Parameters • Air Side Alternatives • Hot Water Alternatives • Discussion of Original Design • Desiccant Dehumidification • Recommendation

  3. Building Description Building Information • 45,000 ft2 • Exercise Facility • Houston, TX • Construction Started: 5/9/05 Finished: 12/09/05 • Cost of Building: $4.5 Million Primary Project Teams • Owner: LA Fitness International, LLC • General Contractor: Ridgemont Construction • Construction Manager: LA Fitness International, LLC • Architects: Heights Venture Architects, LLP • MEP Engineers Advanced Technologies, Inc. • Structural Engineers: BGA Engineers • Civil Engineers: Cobb Fendley & Associcates • Interior Designers: Senninger Walker Architects

  4. Presentation Outline • Building Description • Goals & Metrics • Design Parameters • Air Side Alternatives • Hot Water Alternatives • Discussion of Original Design • Desiccant Dehumidification • Recommendation

  5. Goals & Metrics Design Goals • Energy Reduction Compared to Original Design • Lower Environmental Impact • Economic Feasibility • Gain Practical Experience Designing and Integrating Mechanical Systems Metrics • Annual Energy Consumption • Emissions • Economics Analysis

  6. Presentation Outline • Building Description • Goals & Metrics • Design Parameters • Air Side Alternatives • Hot Water Alternatives • Discussion of Original Design • Desiccant Dehumidification • Recommendation

  7. Design Parameters • Ventilation Requirements • Standard 62.1-2004 Reevaluation • Cooling & Heating Loads • Lighting Loads • Building Envelope • Humidity Control • Critical Zones

  8. Ventilation Design Parameters ASHRAE Standard 62.1-2004 Requirements:

  9. Design Parameters Critical Zones • Indoor Pool & Locker Room Spaces • Relatively Negative Pressure • 4-6 Air Changes/Hour • 800F & 55% Relative Humidity • Pool Water Temperature: 820F • Latent Load From Pool 102,950 Btu/hr

  10. Presentation Outline • Building Description • Goals & Metrics • Design Parameters • Air Side Alternatives • Hot Water Alternatives • Discussion of Original Design • Desiccant Dehumidification • Recommendation

  11. Air Side Alternatives Original Design • Cooling Loads Met by 13 Packaged Rooftop Units • Constant Volume • Primarily Single Zone • Economic Advantage Over Other Equipment • OA Rebalance and Redistribution Is Necessary

  12. Air Side Alternatives Hydronic System – Water Cooled Chiller • Screw Compressor • 200 ton Chiller Performing at 0.66 kW/ton • Cooling Tower Necessary • 4 AHU Needed to Condition the Air • Higher Associated Maintenance Cost/Year

  13. Air Side Alternatives Hydronic System – Air Cooled Chiller • Screw Compressor • 200 ton Chiller performing at 1.22 kW/ton • Less Maintenance Cost Compared to WC Chiller • Less Efficient Performance • Relatively Good Part Load Performance

  14. Air Side Alternatives Discussion of Energy Sources • Hydronic Systems • Lower Annual Energy Consumption? No • Lower Annual Energy Costs? No

  15. Presentation Outline • Building Description • Goals & Metrics • Design Parameters • Air Side Alternatives • Hot Water Alternatives • Discussion of Original Design • Desiccant Dehumidification • Recommendation

  16. Hot Water Alternatives Original Water Heating • Three Natural Gas Fired Water Heaters • 1200F Water • 300 MBH • 100 gal of Storage Each Solar Water Heating • Three Types Commercially Available • Unglazed Flat Plate Collector • Glazed Flat Plate Collector • Evacuated Tube Collector • Model Established Using RETScreen Solar Water Heating Program

  17. Hot Water Alternatives Solar Water Heating • Results of Analysis: • Use Glazed Flat Plate Collector In Final Design • Issues of Solar Reliability • Use Existing Water Heaters as Storage Tanks • Structural Analysis Necessary for Flat Roof

  18. Presentation Outline • Building Description • Goals & Metrics • Design Parameters • Air Side Alternatives • Hot Water Alternatives • Discussion of Original Design • Desiccant Dehumidification • Recommendation

  19. Discussion of Original Design Original Rooftop Unit Design • Pros: • Lowest annual primary energy • Lowest emissions • Lowest first cost • Cons: • High load on DX coil • RTU-1 & RTU-2 lose humidity control • Wasteful to cool & dehumidify air  reheat the air • cfm/ton limitations

  20. Discussion of Original Design • Original Rooftop Unit Design • RTU-1 & RTU-2

  21. Discussion of Original Design • Original Rooftop Unit Design • Reheat & Humidity Sensor Option

  22. Discussion of Original Design Is there a better way to meet the air side loads while satisfying the design criteria? Up until this point in the analysis, the focus of study was to find a completely new base system that could better meet the airside loads. Paradigm shift: Instead of finding better alternative from scratch the question became: How can the existing “good enough” equipment be modified to have better performance for this site?

  23. Presentation Outline • Building Description • Goals & Metrics • Design Parameters • Air Side Alternatives • Hot Water Alternatives • Discussion of Original Design • Desiccant Dehumidification • Recommendation

  24. Desiccant Dehumidification • Another means to control humidity • Low surface vapor pressure attracts moisture from air • System can be configured in a rotating “honeycomb” wheel arrangement • Sensible Heat Gain from Process • Active or Passive? • Decision Made to Use Active Desiccant • Sensible Wheel Also Necessary

  25. Desiccant Dehumidification Active Desiccant Configuration with Sensible Wheel • Air processed by desiccant leaves very hot and dry • Sensible wheel used to restore a hot, dry temperature • Air heater used to reactivate desiccant for further use • Result of process: significant reduction of latent load

  26. Desiccant Dehumidification • Psychrometric Analysis of Wheels

  27. Presentation Outline • Building Description • Goals & Metrics • Design Parameters • Air Side Alternatives • Hot Water Alternatives • Discussion of Original Design • Desiccant Dehumidification • Recommendation

  28. Recommendation Initial idea to modify each unit: • Requires 26 wheels for the 13 units • This idea was too expensive and labor intensive Rather: • Use 1 central dehumidification station to handle all of the OA for the building • Duct the OA from this central unit to the OA intakes of the 13 originally scheduled units

  29. Recommendation

  30. Recommendation Economic Analysis Energy Consumed/Year Includes New System Components: • Motor energy for wheels • Fan energy Payback Period Analysis • Conservative Payback Period: 11 Years • Interest Used: 6% • Natural Gas Escalation Rate: 3% • Modified Payback Period: 8.5 Years • Interest Used: 6% • Natural Gas Escalation Rate: 8%

  31. Many Thanks To... • Advanced Technologies, Inc • Penn State AE Mechanical Faculty • Dr. James D. Freihaut • Mike Prinkey • Tony Daniels • Karen Schulte • My Family • Friends and Colleagues

  32. Questions

  33. Integration of Design • The entire building requires 17,630 cfm of OA to meet the corrected Standard 62.1 requirements • Using an Active Desiccant Configuration, 6000 cfm of counterflow air is necessary • EF-5 from the original design was a perfect fit (6,300 cfm) • This exhaust air stream is centrally located near 7 of the 13 rooftop units

  34. Energy Rates • Energy Rates Natural Gas Rates • May 2005 Texas Commercial Rate: $8.67/MMBtu • Dec 2005 Texas Commercial Rate: $14.68/MMBtu Electric Rates • May 2005 Texas Commercial Rate: $22.86/MMBtu • Dec 2005 Texas Commercial Rate: $23.45/MMBtu

More Related