GLAST Large Area Telescope: I & T Input to LAT Planning Meeting July 17 th and 18 th

Key milestones & timelines for GLAST Large Area Telescope project. Important dates from delivery to system testing. Detailed overview of testing phases & procurement status. Delays and revisions in engineering plans discussed.

riveramary
Download Presentation

GLAST Large Area Telescope: I & T Input to LAT Planning Meeting July 17 th and 18 th

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: I & T Input to LAT Planning Meeting July 17th and 18th Elliott Bloom SU-SLAC Subsystem Manager Brian Grist SU-SLAC Subsystem Engineer elliott@slac.stanford.edu, bgrist@slac.stanford.edu 650-926-2469 650-926-2998

  2. Key Milestone List to Delivery (Not Necessarily in Current PMCS) EM Plan, Procedures, EGSE and MGSE Complete 07/31/03 Receive CAL EM 08/08/03 Receive TKR mini-tower 08/22/03 EM Tower functional tests Complete 09/18/03 EM Tower Available for use by Flight Software 09/18/03 EM Calibration Complete 10/12/03 EM mechanical fit check using 1X4 Grid, TKR Mech tower, CAL 10/13/03 CAL EM at NRL Loading Doc; TKR mini-tower in Italian Customs 10/17/03 Support GSI Beam Test (CAL and TKR mini-tower) 11/14/03 All I&T Flight Techs on Staff (Mechanical and Electrical) 12/15/03 Flight Integration Training MGSE Ready 01/15/04 All Flight Integration Procedures Complete 02/15/04 All Flight Integration MGSE Complete with SDP 03/01/04 LAT Assembly Configuration EGSE Ready For Use 03/01/04 Integration Readiness Review 03/15/04 TKR A/B Available RFI 04/15/04 Grid Available RFI 05/20/04 CAL A/B Available RFI 05/20/04

  3. Multi-Tower EGSE (9/15/03) T&DF System (LAT) EGSE ACD or Sensor Simulator EGSE Crate CPU LCB WAN GASU 28 V Supply Central Database EBM VME AEM GEM Online Workstation TEMs Firewall CAL, TKR or Sensor Simulator SLAC

  4. Single Tower EGSE Configuration (GSI test) Electronics/Online • Online • Workstation • Test Exec • Configuration • Commanding • Telemetry • Event Processing • Monitoring • Visualization • Data base • Message logger • Alerts • Electronic log Subsystem/simulator Back door debug RS-232 Subsystem (or simulator) Central Database VME Chassis • CPU • Commanding • Telemetry • Monitoring • Hardware Drivers AEM/TEM WAN Ethernet Main Dataflow Ethernet • LAT-COMM • External Trigger Ethernet Router and Firewall DC Power External Hardware

  5. Key Milestone List to Delivery After Start of Flight I&T (Not in Current PMCS) Start Tower A/B Installation/Test 05/20/04 Start Tower 1/2 Installation/Test 07/01/04 Start Tower 13/14 Installation/Test 10/28/04 Finish Tower Installation/Test 11/11/04 Finish Installation of ACD/ELEX/X-LAT 12/23/04 Flight Configuration Ready for System Test 12/23/04 Complete System Test 04/21/05 LAT Shipped for Environmental Testing 07/21/05 Environmental Testing Complete 11/03/05 LAT RFI 12/01/05

  6. 28 V Supply LAT Assembly Configuration (3/1/04) LAT EGSE Spacecraft simulator ACD or Sensor Simulator SIU CPU Discretes 1553 1553 WAN LCB GASU Central Database EBM AEM SSR 3 EPUs GEM CPU Online Workstation LCB TEMs Firewall EGSE Crate Test Point on LAT EMI Skirt CAL, TKR or Sensor Simulator CPU LCB SLAC

  7. Spacecraft simulator Discretes 1553 28 V Supply SSR Complete Flight Unit Configuration & CU (12/24/04) LAT EGSE ACD SIU CPU 1553 WAN LCB GASU Central Database EBM AEM 3 EPUs GEM CPU Online Workstation LCB TEMs Firewall EGSE Crate Test Point on LAT EMI Skirt CAL, TKR CPU LCB SLAC

  8. Interdependencies • Dependent on deliveries from all subsystems to be able to do the core of our work. • EM CAL & TKR mini-tower deliveries. • EM GASU and flight software support from ELX. • All Flight Hardware and Software. • MGSE FEM Analysis • Budget for I&T Flight Electronic Techs and the hiring of those techs (4 full time people starting 12/15/03) is currently the responsibility of ELX. I&T will schedule the work for these Techs. • System engineering test plans are required as input to I&T test plans and resulting procedures. • Mission level EGSE decisions can impact I&T EGSE schedule and budget.

  9. Flight Hardware Procurements • No flight hardware procured by I&T. All flight components come from a subsystem.

  10. Flight Hardware Manufacturing Plan Status • LAT-MD-01376 LAT Integration & Test Plan In Work • LAT-MD-01137 LAT EM Test Plan In signoff • LAT-MD-01533 EGSE Plan In revision • LAT-MD-00446 SVAC Plan Released • LAT-MD-01587 SVAC Test Plan Released • LAT-MD-01598 LAT Weight and CG Test Plan Released • LAT-MD-01462 MGSE Development Plan In signoff • LAT-MD-01836 LAT Dynamics Test Performance Plan Draft in Cyberdocs • LAT-MD-01837 LAT Thermal Test Performance Plan Draft in Cyberdocs • LAT-MD-01838 LAT EMI Test Performance Plan Draft in Cyberdocs • LAT-MD-00676 LAT Assembly Sequence In revision • LAT-MD-01386 LAT Facilities Plan Released • LAT-MD-01586 LAT Survey & Alignment Performance Plan In signoff • LAT-MD-01055 LAT Electrical Test Performance plan Released • LAT-MD-00440 LAT Particle Test Plan In signoff

  11. Engineering Model Testing Closure Status • I&T Tests of the TKR mini-tower were done and the results reported to the Engineering meeting at June 10 Engineering Meeting. Data is still being worked. • EM tower (CAL EM and TKR mini-tower) due in August to I&T • Complete EM Tower functional test by September 18th and then make available to Flight Software. • Complete EM Calibration by October 12th. • Need 1x4 Grid and TRK EM Mechanical tower a week before Mechanical fit check to assemble TRK EM into grid. • Perform a mechanical fit check using 1x4 Grid, TKR Mechanical Tower, and EM CAL on October 13th. • CAL EM on the NRL loading dock and the TKR mini-tower in Italian Customs by October 17th. • Support the GSI Beam Test, including the CAL and the TKR mini-tower(run Carbon in the daytime) November 14th – 24th.

  12. Open Flight Design Issues/ Status Trades • CAL-Grid interface design, impacts I&T MGSE, assembly, processes, and procedures. Design not completed. • Grid EMI Skirt design impacts I&T assembly, processes and procedures. Design not completed. • X-LAT plate design impacts I&T MGSE, assembly, processes and procedures. Design not completed. • Radiator interface and MGSE design impact I&T, assembly, processes and procedures. Design not completed. • Environmental test sensor requirements impact I&T assembly, processes and procedures. Requirements have not been finalized. • LAT pointing knowledge requirements are under review by the project. I&T test plans cannot be finalized until we know the final requirements.

  13. -2% variance -5% variance Cost/Schedule Status (May Month End) Cost Variance – GREEN Schedule Variance – YELLOW Beam test change request has been approved and has been incorporated for the June Report. The monthly Cost and Schedule Variances are trending negative

  14. Issues/Concerns/Suggestions/Risks • Late delivery to I&T of EM parts and EGSE software test scripts. • Late delivery has delayed preparations for LAT, particularly in areas of IFCT and SVAC. Possible impact on EGSE. • Part of EGSE/MGSE verification strategy depends on I&T EM program. • Finalization of all LAT test plan requirements is not complete post CDR. This is resulting in compressed schedule and potential increased cost for I&T. Current estimates are September for completing all test plans from the Design Team. • Delivery of flight hardware to I&T may be late. • I&T EGSE is proceeding with in-house developed test executive software. Change to another system for Observatory and/or IOC will require major cost change request. • Spacecraft interface detail uncertainty. • Environmental test fixtures. • EGSE interface. • MGSE handling fixtures. • SIIS fidelity uncertainty. • Delivery of flight hardware to I&T may be late. • When will a decision be made about where to go for Environmental Testing? This will impact preparations and design of Vib and T/V fixtures.