1 / 6

HARPS-NEF Program

Learn about the HARPS-NEF program progress, schedule, budget, and ING/WHT facility questions discussed during the December 6 & 7, 2007 PDR. Harvard University, funding through Origins of Life Initiative, and major hardware contributors.

Download Presentation

HARPS-NEF Program

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HARPS-NEF Program Project Manager Tim Norton HARPS-NEF PDR December 6 & 7, 2007

  2. HARPS NEF Project Teams • Harvard University • Funding through the Harvard University Origins of Life Initiative • Overall Instrument Responsibility at the Center for Astrophysics • Harvard College Observatory • Smithsonian Astrophysical Observatory • Geneva Observatory • HARPS Design & Background • Science and Engineering Resource Contributor • Major Funded Hardware Contributor • ING’s William Herschel Telescope • ING Facility & Operations as agreed thru MOU HARPS-NEF PDR December 6 & 7, 2007

  3. HARPS-NEF Program Schedule HARPS-NEF PDR December 6 & 7, 2007

  4. Schedule Comments • Fast schedule to Build/Assemble/Test relies on significant reuse of design • Orders MUST be placed in January with expected 9-12 month lead times for gratings/grisms/optics • Procurements before CDR of items with 4-6 month lead times (i.e. major machining) • Installation at WHT requires early facility agreement/processing • Design verification requires early prototype and/or field work ( i.e. fiber run/rotator) HARPS-NEF PDR December 6 & 7, 2007

  5. Budget Overview • Commitment from Harvard • Geneva Proposal Accepted for Hardware Funding • Status of Major Capital Expenditures • CCD order placed with E2V • Cryostat Build at ESO in Process, Model Delivered • Calibration Light Box Fabrication in Process • RFQ’s submitted/received responses: • Echelle Grating (ASz prepared Spec & RFQ) • Cross Dispersion Grism (ASz prepared Spec & RFQ) • Collimator Parabola (ASz working alternate vendors) • Camera Optics (RFQ updates in process) HARPS-NEF PDR December 6 & 7, 2007

  6. ING/WHT Facility Questions • Facility Modifications and Installations: • What does the ING/WHT require in terms of building modification processes, documentation, building code review, inspection or other? • Does the ING/WHT recommend we use local contractors or can we make arrangements for staff support? • Site preparation, electrical preparation, general labor for construction services • Prototype of Fiber Routing • Will access to the WHT be available for prototyping? • When is the best time (least impact to WHT operations)? HARPS-NEF PDR December 6 & 7, 2007

More Related