1 / 48

Carl L Raish

2013 Four-CP Response for Transmission- and Distribution-Connected ESIIDs in ERCOT Competitive Area. Carl L Raish. 4 CP Response Methodology. Analysis was limited to ESIIDs in competitive ERCOT areas with ‘BUSIDRRQ’ profile types

rollin
Download Presentation

Carl L Raish

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2013 Four-CP Response for Transmission- and Distribution-Connected ESIIDs in ERCOT Competitive Area Carl L Raish DSWG - June 25, 2014

  2. 4 CP Response Methodology • Analysis was limited to ESIIDs in competitive ERCOT areas with ‘BUSIDRRQ’ profile types • Transmission charges are based on ESIID-specific load during CP intervals • ESIIDs classified by connection at transmission or distribution voltage level • Classified days as CP Days, Near-CP Days and Non-CP Days • Near-CP days were iteratively determined • Started with 12 possible days • Removed days from list if no response detected for the date • Ended up with 7 Near-CP days • Non-CP days were all remaining non-holiday weekdays (June 1 – Sep 30) • Classified ESIIDs based on Weather Sensitivity and Load Factor • Weather sensitivity (R2 for week-day use vs average temperature >= 0.6) • Load Factor based on week-day afternoon usage (1:00 PM – 6:00 PM) • High LF > 0.85 • Medium LF > 0.60 • Low LF ≤ 0.60

  3. 4 CP Response Methodology (continued) • ESIIDs were classified into three response categories based on how they modified usage on CP and Near-CP days • Reduced Day Use -- ESIIDs that lowered usage from 9:00 AM – 5:00 PM) on CP/Near-CP days. • Reduced CP Hour Use -- ESIID that lowered usage during 4:00 PM – 5:00 PM on CP/Near-CP days (but did not reduce day use). • Did not respond – All remaining ESIIDS

  4. 4 CP Response Methodology (continued) Number of Transmission ESIIDs by Response Type

  5. 4 CP Response Methodology (continued) Number of Distribution ESIIDs by Response Type * WS response and type needs additional analysis

  6. 4 CP Response Methodology (continued) • Baselines were created at the ESIID-level using Non-CP days (May 1 – Sep 30). • Average of 10 days before and 10 days after the CP/Near-CP day. • Baselines were aggregated in groups by response type and load factor category • WS baseline was ERS Regression baseline • Scalar day-of-adjustment applied at the aggregated group level. • Day-of-adjustment window: 0:15 AM – 1:00 PM • Baseline energy for the adjustment window was scaled to the actual energy for the CP/Near-CP day • No scalar adjustment was applied to the group with ‘day-use’ response • Adjusted and unadjusted baselines are shown on graphs for non-responding ESIIDs • In general these ESIIDs had actual use higher than the baseline on CP/Near-CP days than the unadjusted baseline • If these ESIIDs are included in the overall class performance, their increased usage would offset reductions by the remaining ESIIDs

  7. 4 CP Response Methodology (continued) • September 3, 2013 CP day special handling • Load shapes were different … probably related to being the day following the Labor Day holiday. • Tables and graphs show reductions for baselines with and without day-of-adjustment • Reductions based on scalar adjusted baselines reflect the actual load reduction on that day • Reductions based on unadjusted baselines are probably closer to reductions on more normal CP days.

  8. 15-Minute Reductions on 4 CP Days - 2013 Transmission Connected ESIIDs

  9. 15-Minute Reductions on 4 CP Days - 2013 Distribution Connected ESIIDs

  10. 15-Minute Reductions on 4 CP Days - 2013 Transmission plus Distribution Connected ESIIDs Largest Combined Summer 2013 reduction occurred on August 7

  11. Identify Near-CP Days – June 2013 4CP @ IE 17:00 Near-CP w/ response

  12. Identify Near-CP Days – July 2013 Near-CP no response 4CP @ IE 17:00 Near-CP w/ response

  13. Identify Near-CP Days – August 2013 4CP @ IE 17:00 Near-CP no response Near-CP w/ response

  14. Identify Near-CP Days – September 2013 4CP @ IE 16:45 Near-CP no response Note: Sep 1, 2013 Sunday, Sep 2 Labor Day

  15. 15-Minute Reductions on Near Peak Days - 2013 Transmission Connected ESIIDs Largest Summer 2013 reduction occurred on August 1

  16. 15-Minute Reductions on Near Peak Days - 2013 Distribution Connected ESIIDs Largest Summer 2013 reduction occurred on June 28

  17. 15-Minute Reductions on Near CP Days - 2013 Transmission plus Distribution Connected ESIIDs

  18. Hour-ending 17:00 Reductions on 4 CP Days - 2013 Transmission Connected ESIIDs

  19. Hour-ending 17:00 Reductions on 4 CP Days - 2013 Distribution Connected ESIIDs

  20. Hour-ending 17:00 Reductions on 4 CP Days - 2013 Transmission plus Distribution Connected ESIIDs Largest Combined Summer 2013 reduction occurred on August 7

  21. Hour-ending 17:00 Reductions on Near Peak Days - 2013 Transmission Connected ESIIDs

  22. Hour-ending 17:00 Reductions on Near Peak Days - 2013 Distribution Connected ESIIDs

  23. Hour-ending 17:00 Reductions on Near CP Days - 2013 Transmission plus Distribution Connected ESIIDs

  24. Reduction Percent by Load Factor - Transmission

  25. Reduction Percent by Load Factor - Distribution

  26. Percent Reduction by Load Factor - Transmission

  27. Percent Reduction by Load Factor - Distribution

  28. June CP Day Load – Responding ESIIDs - 2013 Transmission Connected ESIIDs

  29. June CP Day Load – Responding ESIIDs - 2013 Distribution Connected ESIIDs

  30. June CP Day Load – Responding ESIIDs - 2013 Transmission Plus Distribution Connected ESIIDs

  31. July CP Day Load – Responding ESIIDs - 2013 Transmission Connected ESIIDs

  32. July CP Day Load – Responding ESIIDs - 2013 Distribution Connected ESIIDs

  33. July CP Day Load – Responding ESIIDs - 2013 Transmission Plus Distribution Connected ESIIDs

  34. August CP Day Load – Responding ESIIDs - 2013 Transmission Connected ESIIDs

  35. August CP Day Load – Responding ESIIDs - 2013 Distribution Connected ESIIDs

  36. August CP Day Load – Responding ESIIDs - 2013 Transmission Plus Distribution Connected ESIIDs

  37. September CP Day Load – Responding ESIIDs - 2013 Transmission Connected ESIIDs

  38. September CP Day Load – Responding ESIIDs - 2013 Distribution Connected ESIIDs

  39. September CP Day Load – Responding ESIIDs - 2013 Transmission Plus Distribution Connected ESIIDs

  40. June CP Day Load by Reduction Type - 2013 Transmission Connected ESIIDs

  41. June CP Day Load by Reduction Type - 2013 Distribution Connected ESIIDs

  42. July CP Day Load by Reduction Type - 2013 Transmission Connected ESIIDs

  43. July CP Day Load by Reduction Type - 2013 Distribution Connected ESIIDs

  44. August CP Day Load by Reduction Type - 2013 Transmission Connected ESIIDs

  45. August CP Day Load by Reduction Type - 2013 Distribution Connected ESIIDs

  46. September CP Day Load by Reduction Type - 2013 Transmission Connected ESIIDs

  47. September CP Day Load by Reduction Type - 2013

  48. Questions? ON OFF craish@ercot.com 512/248-3876

More Related