1 / 31

Network techniques for Project Management

Network techniques for Project Management. Meaning of Project & PM Basic Network techniques. Introduction to Project Management. A temporary endeavour undertaken to create a unique product or service (PMI, 2004, P.5) Variety and unique in nature Mainly used for large R& D activities

rosalinar
Download Presentation

Network techniques for Project Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Network techniques for Project Management • Meaning of Project & PM • Basic Network techniques

  2. Introduction to Project Management • A temporary endeavour undertaken to create a unique product or service (PMI, 2004, P.5) • Variety and unique in nature • Mainly used for large R& D activities • Project management mainly developed by military

  3. Two basic Network techniques • PERT an acronym for Program Evaluation Review Technique • Originally developed to facilitate the planning and scheduling the Polaris Fleet Ballistic Missile project of US • PERT is Probabilistic • CPM an acronym for Critical Path Method • developed in 1957 by the DuPont company in US to solve scheduling problems in industrial setting. • CPM is concerned with the trade off between cost and time.

  4. Definitions used in PERT CPM • Activity: A time consuming task. An effort that require resources and take a certain time for completion i.e. designing a part, connecting a bridge girder • Event: A milestone. Is a specific point in time indicating beginning or ending of one or more activities. Does not consume time or resources.

  5. Rules for Network Construction • Each activity must have a preceding and a succeeding event • Each event should have a distinct number • There should be no loops in project network • Each activity is represented by a uniquely numbered arrow.

  6. Example of PERT Draw the network diagram Determine critical path Calculate event slack and activity float Find the standard deviation of CP duration Compute the probability of completing the project in 25 weeks

  7. PERT Analysis Uses 3 time estimates for each activity Optimistic time (a) Pessimistic time (b) Most likely time (m) These estimates are used to calculate an expected value and variance for each activity (based on the Beta distribution)

  8. PERT Analysis • Expected activity time (t) • t = (a + 4m + b) • 6 • Variance = [ (b – a) / 6 ]2 • Standard deviation = SQRT(variance) • = (b – a) • 6

  9. Project Variance and STD Deviation • Project variance (σp2) • = ∑ (variances of all critical path activities) • σp2 = 0.11 + 0.11 + 1.0 + 1.78 + 0.11 • = 3.11 • Project standard deviation (σp) • = SQRT (Project variance) • σp = SQRT ( 3.11) = 1.76

  10. PERT Analysis Z = (Target time – expected time) σp Z = (16 - 15) = 0.57 1.76 This means 16 weeks is 0.57 standard deviations above the mean of 15 weeks.

  11. 7 2 6 10 4 5 10 1 3 7 7 2 5 5 8 4 5

  12. CPM • Cost -Time Relationship • Expediting projects • Expediting activities requires additional resources, which means increasing the cost of the project. • Slope gives us the cost increase associated with a reduction of one unit of the activity duration • Slope =Cc-Cn/Tn-Tc

  13. Example 1 • Find the all normal schedule and cost • Find the all-crash schedule and cost • Find the least cost plan for all crash time schedule • Find the least cost plan for an intermediate time schedule of 22 weeks.

  14. CPM Contd..all normal solution 3 D9 1 • 0-1-2-4-5 is the critical path • Duration=5+7+5+8=25 weeks. • Cost=1860 G6 H0 A5 C7 4 E5 I8 5 2 0 B9 F11

  15. CPM Contd.. All crash solution D7 3 1 • 0-1-3-4-5 is the critical path • Duration is 17 days • Cost=2860 G4 H0 A4 C4 4 I6 E2 5 F7 B7 2 0

  16. Find the minimum cost for the Crash time D7 3 1 • 0-1-3-4-5 is the critical path • Duration is 17 days • Cost=2860 G4 H0 A4 C4 4 I6 E2 5 F7 B7 2 0

  17. Find the minimum cost for the Crash time D 7 3 1 • Step 1- Get the non critical activities with their slope • Step-2 Select the activity which has largest slope & expand as much as possible to achieve as a large a cost reduction is possible • Step-3 Expand the next largest activity slope and continue until all path become critical. G 4 H 0 C 4 A 4 4 I 6 E 2 5 F 7 B 7 2 0

  18. Find the minimum cost for the Crash time D7 3 1 • Step 1- Get the non critical activities with their slope =B-50 C-30,E-70,G-60,F-80 • Step-2 Select the activity which has largest slope & expand as much as possible to achieve as a large a cost reduction is possible= Select F for 2 days expansion cost 160 • Step-3 Expand the next largest activity slope and continue until all path become critical.=E one day is possible at$70 in similar manner G by 2 days cost 120 finally activity B can be expanded by one day “ $50 saving. • So total cost savings are :160+70+120+50=400.Thus the revised cost for 17 days are 2860-400=$2460 G4 H0 A4 C4 4 I6 E2 5 F7 B7 2 0

  19. Determine the least cost plan for any desired number of days ie Least cost plan for 22 days • First step is to list all critical activities and their slope • The activity with the least slope will be compressed first, because decreasing the project time by one day will result in smallest increase in cost.in this case activity C & I can be selected, arbitrarily C is selected but how many days -the most is up to is crash time 4 days here. However such a reduction may create one or more additional critical path. The minute an additional CP is created, the compression should be stopped. Thus here C is reduced from 7 days to 4 days at a cost of 90.So the least cost plan for 22 days is 1860+90=1950

  20. Example2 • The following data were obtained from a study of the time required to overhaul a small power plant. • Find the all normal schedule and cost • Find the all-crash schedule and cost • Find the least cost plan for all crash time schedule • Find the least cost plan for an intermediate time schedule of 17 weeks.

  21. Example2 • The following data were obtained from a study of the time required to overhaul a small power plant. • Find the all normal schedule and cost 1-2-6-7=16 ,1-2-4-6-7=31, 1-2-4-5-7=25,1-3-4-6-7=28,1-3-4-7=22 and cost= 4+4+6+2=16 • Find the least cost plan for all crash time schedule • Find the least cost plan for an intermediate time schedule of 17 weeks. 6 6 2 5 5 11 10 1 7 4 6 4 5 3 5 7

  22. Example2 • The following data were obtained from a study of the time required to overhaul a small power plant. • Find the all crash schedule and cost 1-2-6-7=6 ,1-2-4-6-7=14, 1-2-4-5-7=13,1-3-4-6-7=9,1-3-4-5-7=8 and cost= 6+7+9+4= 26 • Find the least cost plan for all crash time schedule • Find the least cost plan for an intermediate time schedule of 17 weeks. 6 2 2 1 3 5 5 1 7 4 4 1 1 3 5 2

  23. Example2 The following data were obtained from a study of the time required to overhaul a small power plant. • Find the least cost plan for all crash time schedule. • Find the least cost plan for an intermediate time schedule of 17 weeks. 6 6 2 5 5 11 10 1 7 4 6 4 5 3 5 7

  24. Project Management Framework

  25. P

  26. Project Management Framework

  27. Project Management Framework

  28. Project Management Framework

  29. Project Management Framework

  30. Project Management Framework

  31. Project Management Framework

More Related