PROJECT NETWORK DIAGRAM

PROJECT NETWORK DIAGRAM. PREPARED BY : NOR AZAH BINTI AZIZ KOLEJ MATRIKULASI TEKNIKAL KEDAH. OBJECTIVES. Define Network Diagram Purpose of Network Diagram Method : Activity On the Node (AON) Identify ES, EF, LS, LF using Forward Pass Calculation and Backward Pass calculation

royal
Download Presentation

PROJECT NETWORK DIAGRAM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PROJECT NETWORK DIAGRAM PREPARED BY : NOR AZAH BINTI AZIZ KOLEJ MATRIKULASI TEKNIKAL KEDAH

  2. OBJECTIVES • Define Network Diagram • Purpose of Network Diagram • Method : Activity On the Node (AON) • Identify ES, EF, LS, LF using Forward Pass Calculation and Backward Pass calculation • Identify Critical Path • Identify Slack Time

  3. INTRODUCTION • A PND is a pictorial representation of the sequence in which the project work can be done. • The activities and its duration are the basic building blocks needed to construct a graphic picture of the project • Its provide - the earliest time at which work can be begin on every activity that makes up the project - the earliest expected completion date of the project

  4. IMPORTANCE OF ND • ND can be used for ; i) Planning : gives a clear graphical picture of the relationship between project activities ii) Implementation : when updating the project file with activity status and estimate to completion data, the ND is then automatically updated and can be printed or viewed iii) control : while updated ND will retain the status of all activities, the best graphical report and controlling project work will be Gantt Chart

  5. METHODS • THE ACTIVITY ON THE NODE ( AON) • Basic unit of analysis in ND is the activity • Each activity is represented by a rectangle ( activity node) • Arrows represent the predecessor/successor relationship between activities • Every activity in the project will have its own activity node ( each rectangle)

  6. METHODS • THE ACTIVITY ON THE NODE ( AON) B D A F C E PDM format of a project network diagram

  7. METHODS • THE ACTIVITY ON THE NODE ( AON) Dependencies • A dependency is simply a relationship that exists between pairs of activities • 4 types of activity dependencies A B FS : A finishes, B start

  8. METHODS • THE ACTIVITY ON THE NODE ( AON) Dependencies FF : A finishes, B finish A A A B SS : A start, B start

  9. METHODS • THE ACTIVITY ON THE NODE ( AON) Dependencies A B SF : A starts, B finish

  10. THE ACTIVITY ON THE NODE ( AON)

  11. Creating an initial project network schedule • THE ACTIVITY ON THE NODE ( AON) B 3 D 5 Start A 1 End F 3 E 2 C 2 Forward Pass calculations

  12. EST, LST, EFT, LFT • CPM uses the following times for an activity EST - Early Start time is the earliest time the activity can begin LST - Late Start Time is the latest time the activity can begin - still allow the project to be completed on time EFT - Early Finish Time is the latest time the activity can end LFT - Late Finish Time is the latest time the activity can end - still allow the project to be completed on time

  13. Forward Pass calculations

  14. Backward Pass calculations

  15. CRITICAL PATH METHOD (CPM) • An effective way to analyze complex projects • Represent the critical set of activities to complete a project • Help to focus on essential activities which are critical to run the project • Allows the project manager to concentrate on important activities • CP is the longest path on ND and the most important part • Any delays on the CP will lead to delay of the project

  16. CRITICAL PATH METHOD (CPM)

  17. FLOAT • Also known as slack, total float and path float • Is computed for each task by subtracting EFT from the LFT ( @ the early start from the late start) • Is the amount of time the task can slip without delaying the project finish date. • Free float is the amount of time a task can slip without delaying the early start of any task that immediately follows it.

  18. Slack Time calculations

  19. EXAMPLE 1. TABLE 1 shows the activities and the durations required to complete a construction project, including the precursor activity. Refering to the TABLE 1: i) draw the project network diagram. ii) state the activities on the critical path. iii) calculate the minimum duration of the project.

  20. 13 4 17 D 13 0 17 0 0 7 6 13 1919 17 2 19 0 7 7 ES D EF activity A END F START 14 3 16 0 0 7 0 0 7 0 13 17 0 19 19 19 E 7 5 12 14 1 17 C B 9 2 14 LS F LF project network diagram