1 / 28

10 th Cohesion Fund 1164/94/ISPA Monitoring Committee Meeting – 25 January 2012

10 th Cohesion Fund 1164/94/ISPA Monitoring Committee Meeting – 25 January 2012 GENERAL REPORT ON MEASURES managed by Ministry of Transport, Information Technology and Communications Presented by Galina Vassileva, Dipl. Eng Deputy Head of CF 1164/94 MA. Danube Bridge at Vidin – Calafat.

ruby
Download Presentation

10 th Cohesion Fund 1164/94/ISPA Monitoring Committee Meeting – 25 January 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 10th Cohesion Fund 1164/94/ISPA Monitoring Committee Meeting – 25 January 2012 GENERAL REPORT ON MEASURES managed by Ministry of Transport, Information Technology and Communications Presented by Galina Vassileva, Dipl. Eng Deputy Head of CF 1164/94 MA

  2. Danube Bridge at Vidin – Calafat Danube Bridge Vidin – Calafat Presentation:

  3. Contract Details Contract 1: New Cross Border Combined Bridge over the Danube River at Vidin – Calafat Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC) Contractor: FCC Construccion SA (Spain) Engineer: Ingerop / High-Point Rendel / JV (France/UK) Contract Value: € 105 432 747.03 Commencement Date: 1st March 2007 Revised Completion Date: 9th June 2011 Paid from 01.05.2011 to 31.12.2011 € 10 251 170.82 Paid total until 31.12.2011 € 90 793 434.89 Physical progress until 31.12.2011 72% Financial progress until 31.12.2011 86% Danube Bridge Vidin – Calafat Presentation:

  4. 40m Spans Rail Approach Bridge – General View Abutment A1 to Pier PA10 – January 2012 Danube Bridge Vidin – Calafat Presentation:

  5. 80m Spans Road Approach Bridge Piers PB6 to PB1 – January 2012 Danube Bridge Vidin – Calafat Presentation:

  6. Main Bridge 180 Spans Pier PB9 – January 2012 Danube Bridge Vidin – Calafat Presentation:

  7. Main Bridge 180 Spans – General View Abutment A3 to PB9 – January 2012 Danube Bridge Vidin – Calafat Presentation:

  8. Contract Details Contract 3:Danube Bridge Vidin – Calafat: Adjoining Bulgarian Infrastructure Works Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC) Contractor:FCC Construccion SA (Spain) Engineer: High-Point Rendel / Ingerop / Salfo (UK/France/Greece) Contract Value: € 62 600 456.00 Commencement Date: 28 December 2007 Revised Completion Date: 3 June 2011 Paid from 01.05.2011 to 31.12.2011 € 12 530 329.97 Paid total until 31.12.2011 € 48 074 310.39 Physical progress until 31.12.2011 87% Financial progress until 31.12.2011 77% Danube Bridge Vidin – Calafat Presentation:

  9. Approach to New Border Freight Station from Sofia Danube Bridge Vidin – Calafat Presentation:

  10. Bregovo Road Junction Danube Bridge Vidin – Calafat Presentation:

  11. Main Highway Under Novo Selo Road Overpass Danube Bridge Vidin – Calafat Presentation:

  12. General Arrangement of Bridge - Artists Impression General Arrangement of Bridge - Actual October 2011 Danube Bridge Vidin – Calafat Presentation:

  13. Plovdiv – Svilengrad Electrification & Upgrading of Corridors IV and IX Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  14. Project/Contracts Details • Phase 1: EuropeAid/117495/D/W/BG Electrification & Upgrading of the Railway Section Kroumovo - Parvomai • Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC) • Contractor: TERNA S.A. (Greece) • Engineer: Typsa/Systra/Louis Berger/Rubicon Engineering/Trademco • Contract Value: € 99 792 441.00 • Commencement Date: 25th May 2006 • Revised Completion Date: 31st December 2011 • Status as per 31.12.2011: Operational, Taking-Over Certificate signed on 21.12.2011 • Paid from 01.05.2011 to 31.12.2011: € 4 336 977.71 • Paid Total until 31.12.2011: € 93 624 124.86 • Physical Progress until 31.12.2011: 100% • Financial Progress until 31.12.2011: 94% Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  15. Railway bridge at Katunitsa Station Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  16. Kochovo Halt Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  17. Popovitsa Station Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  18. The Prime Minister Mr. Borisov and the Minister of TITCMr. Moskovski traveling in the driver’s cabin of an electrical locomotive along Krumovo – Parvomai section at a speed of 163.6 kmph Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  19. Project/Contracts Details • Phase 2: EuropeAid/123600/D/WKS/BG Electrification & Upgrading of the Railway Section Parvomai - Dimitrovgrad • Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC) • Contractor: ASTALDI S.P.A. (Italy) • Engineer: Typsa/Systra/Louis Berger/Rubicon Engineering/Trademco • Contract Value: € 68 000 000.00 • Commencement Date: 02nd October 2007 • Revised Completion Date: 09th November 2011 • Status as per 31.12.2011: Operational, Taking-Over Certificate signed on 20.12.2011 • Paid from 01.05.2011 to 31.12.2011: € 7 050 493.31 • Paid Total until 31.12.2011: € 61 780 662.73 • Physical Progress until 31.12.2011: 100% • Financial Progress until 31.12.2011: 91% Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  20. Karadzhalovo Station Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  21. Karadzhalovo Road Overpass Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  22. Yabalkovo Station Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  23. Project/Contracts Details • Systems: EuropeAid/124429/D/WKS/BG Signalling and Telecommunications Systems and SCADA for the Whole of the Line • Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC) • Contractor: THALES (Austria)/ALCATEL-LUCENT (Romania) • Engineer: Typsa/Systra/Louis Berger/Rubicon Engineering/Trademco • Contract Value: € 38 615 986.66 • Commencement Date: 16th October 2007 • Revised Completion Date: 31st March 2012 • Status as per 31.12.2011: Operational for Plovdiv – Dimitrovgrad section • Paid from 01.05.2011 to 31.12.2011: € 6 312 383.66 • Paid Total until 31.12.2011: € 23 756 937.28 • Physical Progress for Plovdiv – Dimitrovgrad section: 90% • Financial Progress until 31.12.2011: 62% Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  24. Passenger Information Systems at Katounitsa Station Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  25. GSM-R Tower at Cheshnegirovo Halt Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:

  26. Ljulin Motorway – Sofia Ring Road to Daskalovo Junction Project

  27. Ljulin Motorway – Sofia Ring Road to Daskalovo Junction ProjectCommemorative plague Commemorative Plague

  28. 10th Cohesion Fund 1164/94/ISPA MonitoringCommittee Meeting – 25 January 2012 Thank you for your attention!

More Related