280 likes | 436 Views
10 th Cohesion Fund 1164/94/ISPA Monitoring Committee Meeting – 25 January 2012 GENERAL REPORT ON MEASURES managed by Ministry of Transport, Information Technology and Communications Presented by Galina Vassileva, Dipl. Eng Deputy Head of CF 1164/94 MA. Danube Bridge at Vidin – Calafat.
E N D
10th Cohesion Fund 1164/94/ISPA Monitoring Committee Meeting – 25 January 2012 GENERAL REPORT ON MEASURES managed by Ministry of Transport, Information Technology and Communications Presented by Galina Vassileva, Dipl. Eng Deputy Head of CF 1164/94 MA
Danube Bridge at Vidin – Calafat Danube Bridge Vidin – Calafat Presentation:
Contract Details Contract 1: New Cross Border Combined Bridge over the Danube River at Vidin – Calafat Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC) Contractor: FCC Construccion SA (Spain) Engineer: Ingerop / High-Point Rendel / JV (France/UK) Contract Value: € 105 432 747.03 Commencement Date: 1st March 2007 Revised Completion Date: 9th June 2011 Paid from 01.05.2011 to 31.12.2011 € 10 251 170.82 Paid total until 31.12.2011 € 90 793 434.89 Physical progress until 31.12.2011 72% Financial progress until 31.12.2011 86% Danube Bridge Vidin – Calafat Presentation:
40m Spans Rail Approach Bridge – General View Abutment A1 to Pier PA10 – January 2012 Danube Bridge Vidin – Calafat Presentation:
80m Spans Road Approach Bridge Piers PB6 to PB1 – January 2012 Danube Bridge Vidin – Calafat Presentation:
Main Bridge 180 Spans Pier PB9 – January 2012 Danube Bridge Vidin – Calafat Presentation:
Main Bridge 180 Spans – General View Abutment A3 to PB9 – January 2012 Danube Bridge Vidin – Calafat Presentation:
Contract Details Contract 3:Danube Bridge Vidin – Calafat: Adjoining Bulgarian Infrastructure Works Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC) Contractor:FCC Construccion SA (Spain) Engineer: High-Point Rendel / Ingerop / Salfo (UK/France/Greece) Contract Value: € 62 600 456.00 Commencement Date: 28 December 2007 Revised Completion Date: 3 June 2011 Paid from 01.05.2011 to 31.12.2011 € 12 530 329.97 Paid total until 31.12.2011 € 48 074 310.39 Physical progress until 31.12.2011 87% Financial progress until 31.12.2011 77% Danube Bridge Vidin – Calafat Presentation:
Approach to New Border Freight Station from Sofia Danube Bridge Vidin – Calafat Presentation:
Bregovo Road Junction Danube Bridge Vidin – Calafat Presentation:
Main Highway Under Novo Selo Road Overpass Danube Bridge Vidin – Calafat Presentation:
General Arrangement of Bridge - Artists Impression General Arrangement of Bridge - Actual October 2011 Danube Bridge Vidin – Calafat Presentation:
Plovdiv – Svilengrad Electrification & Upgrading of Corridors IV and IX Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
Project/Contracts Details • Phase 1: EuropeAid/117495/D/W/BG Electrification & Upgrading of the Railway Section Kroumovo - Parvomai • Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC) • Contractor: TERNA S.A. (Greece) • Engineer: Typsa/Systra/Louis Berger/Rubicon Engineering/Trademco • Contract Value: € 99 792 441.00 • Commencement Date: 25th May 2006 • Revised Completion Date: 31st December 2011 • Status as per 31.12.2011: Operational, Taking-Over Certificate signed on 21.12.2011 • Paid from 01.05.2011 to 31.12.2011: € 4 336 977.71 • Paid Total until 31.12.2011: € 93 624 124.86 • Physical Progress until 31.12.2011: 100% • Financial Progress until 31.12.2011: 94% Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
Railway bridge at Katunitsa Station Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
Kochovo Halt Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
Popovitsa Station Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
The Prime Minister Mr. Borisov and the Minister of TITCMr. Moskovski traveling in the driver’s cabin of an electrical locomotive along Krumovo – Parvomai section at a speed of 163.6 kmph Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
Project/Contracts Details • Phase 2: EuropeAid/123600/D/WKS/BG Electrification & Upgrading of the Railway Section Parvomai - Dimitrovgrad • Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC) • Contractor: ASTALDI S.P.A. (Italy) • Engineer: Typsa/Systra/Louis Berger/Rubicon Engineering/Trademco • Contract Value: € 68 000 000.00 • Commencement Date: 02nd October 2007 • Revised Completion Date: 09th November 2011 • Status as per 31.12.2011: Operational, Taking-Over Certificate signed on 20.12.2011 • Paid from 01.05.2011 to 31.12.2011: € 7 050 493.31 • Paid Total until 31.12.2011: € 61 780 662.73 • Physical Progress until 31.12.2011: 100% • Financial Progress until 31.12.2011: 91% Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
Karadzhalovo Station Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
Karadzhalovo Road Overpass Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
Yabalkovo Station Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
Project/Contracts Details • Systems: EuropeAid/124429/D/WKS/BG Signalling and Telecommunications Systems and SCADA for the Whole of the Line • Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC) • Contractor: THALES (Austria)/ALCATEL-LUCENT (Romania) • Engineer: Typsa/Systra/Louis Berger/Rubicon Engineering/Trademco • Contract Value: € 38 615 986.66 • Commencement Date: 16th October 2007 • Revised Completion Date: 31st March 2012 • Status as per 31.12.2011: Operational for Plovdiv – Dimitrovgrad section • Paid from 01.05.2011 to 31.12.2011: € 6 312 383.66 • Paid Total until 31.12.2011: € 23 756 937.28 • Physical Progress for Plovdiv – Dimitrovgrad section: 90% • Financial Progress until 31.12.2011: 62% Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
Passenger Information Systems at Katounitsa Station Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
GSM-R Tower at Cheshnegirovo Halt Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX Presentation:
Ljulin Motorway – Sofia Ring Road to Daskalovo Junction Project
Ljulin Motorway – Sofia Ring Road to Daskalovo Junction ProjectCommemorative plague Commemorative Plague
10th Cohesion Fund 1164/94/ISPA MonitoringCommittee Meeting – 25 January 2012 Thank you for your attention!