MARKET SYSTEM RELEASE UPDATE Modifications Committee Meeting 31 January 2012. SEM R1.10.0 – Oct. 2011. Scope for SEM R1.10.0 was as follows: Release was deployed successfully on Friday October 21 st , 2011 in conjunction with the deployment of the new Auction Management Platform (AMP). .
E N D
MARKET SYSTEM RELEASE UPDATEModifications Committee Meeting31 January 2012
SEM R1.10.0 – Oct. 2011 • Scope for SEM R1.10.0 was as follows: • Release was deployed successfully on Friday October 21st, 2011 in conjunction with the deployment of the new Auction Management Platform (AMP).
SEM R1.11.0 – Dec. 2011 • Scope for SEM R1.11.0 was as follows: • Release was deployed successfully on December 15th, 2011. • Change Requests were raised during testing with AMP. • Changes were delivered by MIUN Calculation solution vendor and not CMS vendors (ABB / Navita). • Changes did not impact on interfaces between the CMS and Participant systems.
SEM R2.0.0 – Intra-Day Trading - Scope • Scope for SEM R2.0.0 is as follows: • SEM_PC_CR284 added to scope on Dec 2nd 2011. Change to the vendor design to ensure alignment of IDT solution with High Level Design Summary agreed at the Modifications Committee. • SEM_PC_CR287 added to scope on Dec 12th, 2011. Minor change included to align with the T&SC and to ensure Participants could effectively manage Credit Cover under IDT.
SEM R2.0.0 – Intra-Day Trading – Project schedule • Major activities and associated schedule for the project are as follows: • The project is on schedule across all workstreams. • * subject to successful completion of testing
SEM R2.0.0 – Intra-Day Trading – Technical Workstream • Major activities and associated schedule for the Technical Workstream:
SEM R2.1.0 – Oct. 2012 • The Modification Proposals approved for inclusion in scope for SEM R2.1.0 are as follows:
SEM R2.1.0 – Oct. 2012 • The release cut-off date for the October 2012 release to the Central Market Systems was Friday, November 18th, 2011. • Two meetings of the Change Control Forum (CCF) were held to determine the non-T&SC release scope, i.e. Changes routed through the SEM Design Service (SDS). • A SEM R2.1.0 release scope proposal paper has been issued to the RAs outlining the complete release scope. • Once approval has been received from the RAs the release scope will be published to the industry.
SEM R2.2.0 – Apr. 2013 • The release cut-off date for the April 2013 release to the Central Market Systems is : Friday, June 22nd, 2012 • All approved Modifications Proposals will be allocated to this release (subject to available capacity).