1 / 8

Power – Challenges, difficulties and experiences

Power – Challenges, difficulties and experiences. November, 2012. CPO of Qatalum, Steve Davison. Qatalum power supply - in a nut shell. Design philosophy Captive power plant, designed for island operation Generating capacity according to smelter demand plus one generating unit in spare

rufina
Download Presentation

Power – Challenges, difficulties and experiences

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Power – Challenges, difficulties and experiences November, 2012 CPO of Qatalum, Steve Davison

  2. Qatalum power supply - in a nut shell Design philosophy • Captive power plant, designed for island operation • Generating capacity according to smelter demand plus one generating unit in spare Operating philosophy • Power plant generates the power to the smelter and zero import • 99.95% of the time in grid connected mode • Summer operation with 6 generators, maintenance during winter Organisation • Operation and maintenance of Power Plant + HV: 100 employees • Administrative resources shared with the smelter Agreements • Grid and emergency agreements with the grid operator Kahramaa • Gas agreement with QP (Qatar Petroleum)

  3. Fuel Gas Steam Turbine 13 LP LP Genr Genr ~ ~ ~ ~ Genr Genr Genr HP HP GT GT GT GT HRSG HRSG HRSG HRSG ~ ~ Cooling Water System Condr Condr SW Make-Up SW Blow Down to Fume Treatment Steam Turbine 2 Cast House 220kV GIS 400kV Grid Interconnection Carbon Plant 33kV Distribution Rectifiers Qatalum Power Supply - Asset Overview GT11 GT12 Steam Turbine 23 Genr GT21 GT22

  4. 9th August 2010 incident Incident • Early morning of 9th August, a grid system detected earth fault lead to a complete black-out of the Qatalum facility • After approx. 3.5 hrs the smelter loading could commence • Long power outage and unstable smelter reasons for smelter freeze Effects on the power plant • Smelter ramp-up stopped • Power Group concentrates on rectification and commissioning of the steam cycle • End August 2011 power plant handed over to Power Group Improvements • Several investigations suggested improvements • Two large projects – 2nd ICT and 11kV modification

  5. Cooling Tower fire - early morning 17th March

  6. Cooling Tower rebuild Rebuild • Same cooling tower (SPIG) • Foundation and basin re-used • Fire protection will be implemented Status • Installation complete Nov 2012 • Fire protection to be installed 3Q 2013

  7. Reliability of the current power supply Gas Turbines Generators • Particular high reliability since CT fire • Dusting problems on two GT generators • Steam Turbines • Both successfully returned to service after cooling tower fire • Power Management System (PMS) • Improvements to be implemented • Interconnector, HV & Rectifiers • Second interconnector by April 2013 • First ICT so far no reliability issues • Strong focus on reliability and minimal downtime • Fuel Supply • Second gas supply pipeline commissioned 7 24 August 2014

  8. Thank you شـــكراً

More Related