1 / 12

IENG 471 - Lecture 04 - 2

Learn how to estimate equipment fractions for facility planning and process design. Calculate machine requirements, idle time, unit cost, and total space needed. Explore reliability and maintainability factors.

saari
Download Presentation

IENG 471 - Lecture 04 - 2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IENG 471 - Lecture 04 - 2 Schedule Design: The Sequel IENG 471 Facilities Planning

  2. Assignments • Assignment (Due Today - Now): • HW: (HW 2) • Product BOM • Product Operation Process Chart • Product Precedence Diagram • Next Assignment: • HW: (HW 3) See Assignment Link • required input for each of the workstations • equipment necessary for each machine • steady state cycle time for each machine • ideal machine assignment for each machine • compute the idle time • unit cost at each workstation • total cost per good unit • square footage for each workstation and the total space required IENG 471 Facilities Planning

  3. Equipment Requirements • Equipment Fractions are the number of machines of one type required to produce the required volume of product(s) • Some machines can be used to perform multiple operations… • So, if idle time on the machine exists, and there are multiple products scheduled, then fewer total machines may be required! • Some machines may not be able to perform the required operation(s) fast enough to reach the required volume with only one machine… • So, more copies of the machine may be required! IENG 471 Facilities Planning

  4. Estimating Equipment Fractions • The equipment fraction for each req’d machine is based on all of the operations the machine will perform • Good thing we got those Operations Process Charts! • To find the number of machines of a type for the facility: • The number of workstations for a shift (F) is: where: • S is the standard time to perform the operation, per unit • Q is the quota of output units per shift • E is the efficiency of production on the machine, expressed as a percentage of the standard operation time • H is the hours available for production on the machine during the shift (or whatever unit of time matches parameter S) • R is the availability (reliability*) of the machine, expressed as % of the “up time” that the machine is available to work (%H) IENG 471 Facilities Planning

  5. Reliability • Reliability is a measure of how often a system fails: • How long (on average) you can run it until it stops working right • How do you know that it’s not working right? • MTTF (Mean Time To Failure) or • MTBF (Mean Time Between Failures) IENG 471 Facilities Planning

  6. Maintainability • Maintainability (serviceability) is a measure of how long it takes to return the system to proper operation: • Sum of the times required to: • diagnose the problem • obtain repair parts / tools • repair the failed components • return the unit to operating conditions • MTTR (Mean Time To Repair) IENG 471 Facilities Planning

  7. % Availability =MTTF MTTF + MTTR Availability • Availability is a function of Reliability and Maintainability: • It is the percentage of time that you can count on using it for production IENG 471 Facilities Planning

  8. Equipment Fractions - continued • Since the number of machines is an integer • The lower bound on the number of machines required is 4 – the sum of the equipment fractions • The upper bound on the number of machines required is 6 – the sum of the ceiling values for each operation… • But … IENG 471 Facilities Planning

  9. Equipment Fractions - continued • We should adjust the required number of machines to also account for: • Frequency of changeover (flexibility) • Set-up times • Preventative maintenance • Manufacturing policies… • Therefore, the four machines estimate might not really be feasible … it assumed that everything was best case scenario! IENG 471 Facilities Planning

  10. Ex: Injection Mold Rubber Feet • Process for juicer is: • Mold & trim feet – 2% scrap rate • Transport trimmed feet to line – 1% scrap rate • Assemble juicer – 0.5% scrap rate • 3 grams of rubber needed per foot • Find the number of feet to be processed at each workstation! • Find the raw rubber needed for this process! IENG 471 Facilities Planning

  11. Ex: Injection Mold Rubber Feet • Shift is 8 hr, but reduced by two 15 min breaks, and 35 min machine warm-up (to heat the mold and material). • Production schedule requires 2450 sets of feet daily • MTTF is 38 hours • MTTR comprises 5 min to diagnose, 55 min to obtain spare parts, 7 min to fix, 18 min to re-warm • Run one shift per day • Obtain one set of four feet per cycle • Cycle time is 40 s (steady state) • Find the equipment fraction for this process! IENG 471 Facilities Planning

  12. Questions • What is the machine fraction if, instead: • A Manufacturing Engineer suggests using a four unit mold instead of a single unit mold? • An Industrial Engineer suggests running three shifts, eliminating daily warm-up time? • An improved facility design reduces the time to get spare parts to 2 min, and the re-warm time to 1 min? IENG 471 Facilities Planning

More Related