Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: I&T Integration Kickoff Meeting MGSE March 9th, 2004 Eric M. Gawehn SU-SLAC MGSE Department Manager egawehn@slac.stanford.edu 650 – 926 – 3622 Office 650 – 796 – 2576 Cell. AGENDA.
E N D
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: I&T Integration Kickoff Meeting MGSE March 9th, 2004 Eric M. Gawehn SU-SLAC MGSE Department Manager egawehn@slac.stanford.edu 650 – 926 – 3622 Office 650 – 796 – 2576 Cell
AGENDA • MGSE Required for Assembly / Disassembly of the LAT ( SLAC Ops ) • Hardware List • Long Lead Items • Status • Readiness Verification • Procedures • List • Training • Schedule
- Items Needed at Integration Start - Provided by Other Group, or Needed Later LAT MGSE Hdwr List, Cont. • Long Lead Items • LAT 4 x 4 Rotation / Support Stand (including drive system and flex coupling) • Personnel Access Platform { Interfaces to Rotation Stand Weldment } • GPR and GPR to Grid attach bracketry • Support Shaft-Flange Assemblies, GPR to Rotation / Support Stand • LAT Z Axis Vertical Lift Fixture • LAT Z Axis Horizontal Lift Fixture • Proof test weights for LAT Lift Fixture, GPR, GPR to Grid brackets, Support Shaft Flange Assemblies and Rotation Stand • 1x4 Lift Fixture • Short Lead Items • CAL –Z Up Lift Fixture, Complete and Ready for Use • CAL +Z Up Lift Fixture • TKR Lift Fixture – Provided by TKR • TKR Alignment System • Crane Scale; Being Modified; Will Require Re-Calibration • CAL Alignment Tool • EM-2 Single Bay Mod ( Updated TKR Interface Plate )
- Items Needed at Integration Start - Provided by Other Group, or Needed Later LAT MGSE Hdwr List, Cont. • Short Lead Items, Continued • CAL Alignment Rods • TKR to TKR No Touch During Ascent Verification Tool • CAL Inversion Stand • Metrology Bay for Shimming E-Box Height with respect to CAL Grid Interface • TWR ( TKR, CAL, TEM, TEM PS ) Mass Simulators • Lift Fixture relocation dollies; Use Lead Stack dollies from EM Series • LAT Z Axis Horizontal Support Braces / Counterweight Moment Arms • Menning Plate Installation Equipment • Interim Integration E-Box support brackets TBD • ACD Low Profile Integration Stand • Brackets to hold Lift Fixture Spreaders on top of Bonded Stores Containers • Ambient Test Thermal Control System • 1 x 4 EM-Calibration Unit Rotation Stand
LAT MGSE Images ACD Low Profile Integration Stand ACD on 8’ by 8’ Dolly Integration Stand is Placed to Allow Range of Motion for PAPs
LAT MGSE Procedures • Assemble MGSE Per Design Drawings • Procedures will point to drawings • Procedures will capture trace ability for installation of Certified Fasteners • Special Procedures and Travelers for Qualification Steps • Training Procedures to ensure team is ready • 4x4 Integration Stand • For Range of Motion Checks Prior to PAP Relocation Events • Lift Fixtures • Stand Relocations in Rm 104 • Shipment Preps