Edmonton’s RDF Facility – CONCEPT to IMPLEMENTATION. SWANA Northern Lights Conference, Edmonton, AB – June 20, 2013 Lena Aitken, Project Engineer, City of Edmonton Uwe Eschenhorst, Project Manager, Vecoplan LLC. Outline. History of Edmonton’s journey to Refuse Derived Fuel (RDF) production.

salma
Download Presentation

Edmonton’s RDF Facility – CONCEPT to IMPLEMENTATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Edmonton’s RDF Facility – CONCEPT to IMPLEMENTATION SWANA Northern Lights Conference, Edmonton, AB – June 20, 2013 Lena Aitken, Project Engineer, City of Edmonton Uwe Eschenhorst, Project Manager, Vecoplan LLC

  2. Outline • History of Edmonton’s journey to Refuse Derived Fuel (RDF) production. • RDF – what is it? • RDF Project – from concept to final design • Welcome Vecoplan! • Major Equipment Supplier • Design Build Construction Management Services

  3. History • Cloverbar Landfill is getting full! • 2009 was estimated closure date • Starting premise – there IS a better solution to landfilling • City already had very established recycling and composting programs, currently diverting 60% of the waste • Looking to process the remaining 75,000 tonnes/yr of Composting residuals and 5,000 tonnes/yr of MRF residuals. • Specific targets include: • Increase Edmonton’s landfill diversion rate from 60% to 90% • Reduce Edmonton’s need for landfilling, without going to traditional combustion systems.

  4. 2010 15 years of development 1995

  5. IPTF Biofuels Facility RDF – What is it? • RDF is the feedstock for the future biofuels facility

  6. March 2010 Pre-Processing Area Transfer Station August 2009 IPTF Functions and Phasing November 2012 Phase 2 Phase 3 RDF Facility Phase 1

  7. Transfer Station MSW Organics to ECF RDF to Biofuels RDF Facility Pre-process Area - MRF Residuals - ECF Residuals - Wood Waste RDF – What is it? • Produced in the 3rd Phase of the Integrated Process and Transfer Facility (IPTF) • Sort out the most suitable material from the trash and residuals. • Process it to achieve homogenous, quality, and uniform material.

  8. RDF Project – Concept to Design Considerations along the way…. • Low speed shreddervs. High speed shredder • Separate explosion proof building required to house the high speed shredders. • Equipment Supply & Design Build Construction Management vs. Design–Bid–Build • Equipment manufacturing firm designs and supplies equipment systems with demonstrated performance. • Performance guarantee for the production of RDF.

  9. RDF Concept in the Beginning In-Feed Primary Shredding Screening Heavies Removal Fines Bunker Heavies Bunker Ferrous Removal Non-Ferrous Removal ‘RDF Block Diagram’ that was used in the Request For Proposal Ferrous Bunker Non-Ferrous Bunker Secondary Shredding RDF Conveying

  10. RDF Project Milestones

  11. Final RDF Design

  12. Welcome Vecoplan! • Major Equipment Supplier • Design Build Construction Management Services for the IPTF Phase 3 (RDF) Project • Project Manager: Uwe Eschenhorst