An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GIST GERB Status Report Nigel Morris 3rd May 2007

  2. GERB-3 Status • GERB-3 IEU returned from Alcatel • Modifications to three of the PCBs underway • QFM-3 has been removed from the IOU • Plan to repair QFM-3 is under discussion with GA

  3. GERB-4 Status • GERB-4 instrument delivered to Alcatel on 5th March 2007, but… • A problem with the flight FPA (#FM3) meant that this had to be removed. So, GERB-4 currently has a non-flight FPA fitted • FPA was found to have damage to bond wires and one of the ASICs • An investigation into the damage did not reveal conclusively how this could of occurred, but most likely explanation is that a slender object (such as an Allen key or screwdriver) was accidentally inserted into the open edge of the FPA

  4. FPA Damage

  5. GERB-4 FPA • Fortunately there is a third FPA (#FM2) and at least one good spare from the GERB 2/3 programme • Consortium reviewed both FPAs and came to the conclusion that there was not much to choose between them (no. of working pixels, TC, noise, etc.) • #FM2 has one advantage in that it is newer therefore this was chosen to replace the flight FPA • Calibration of the FPA is currently under way at Leicester

  6. Schedule • GERB-4 will be returned from Alcatel at the end of May 2007 (TBC) • Some minor NCRs will be investigated and if necessary repairs made. Otherwise it will be put into storage • FPA calibration will be complete by beginning of August • FPA will be fitted and aligned in GERB-4 IOU • Remainder of GERB-4 verification testing will take place over following weeks. • Ready for start of instrument level calibration around the beginning of September 2007.

  7. GERB-3 Schedule • After QFM is repaired, IOU will be re-assembled • GERB-3 instrument will then complete its verification programme • Will also be ready for calibration around the beginning of September, but will clearly follow on when GERB-4 is finished • Both GERBs will then go into storage at RAL.